HomeMy WebLinkAboutAgreement_General_08/24/2018_Florida Design - Kimley HornKimley»>Horn
August 24, 2018
Michael Cuozzo, Manager
Village of Tequesta
345 Tequesta Drive
Tequesta, FL 33469
RE: Water Treatment Plant Upgrades
Dear Mr. Cuozzo:
As you are aware, we recently finalized plans, received a permit, advertise for bids and received the bids
(August 14, 2018) on the above -referenced project. This project fundamentally includes long -needed
upgrades to outdated electrical and control elements of the plant (where parts have become difficult or
impossible to find due to the age of the equipment) as well as the replacement of the sulfuric acid and
sodium hydroxide chemical tanks that have far outlived their normal useful life. All of these project
elements have been needed for at least the last several years and were identified as needed short-term
improvements on the Equipment Condition Assessment request completed more than 5 years ago.
The bids received are summarized below; a copy of the low bid is enclosed.
Florida Design Contractor's Inc. $1,801,500
TLC Diversified $1,825,000
Florida Design Drilling Corp. $2,000,000
We requested information from the apparent low bidder for evaluation in order to determine their ability
to satisfy the qualification criteria set forth in the bidding documents. A copy of the request and their
response is enclosed. It should be noted as part of the evaluation that the low bidder has prior successful
experience with the Village and considerable additional favorable project experience with the Engineer.
With regard to the subcontractors, we also have favorable experience with the instrumentation contractor.
The electrical subconsultant is not familiar to us and, as such, we have secured and contacted several
of their references. We find that their experience level satisfies the requirements of the bid documents
and the references reached were generally positive (see enclosed reference check sheet).
In addition, please take note that the bid form included a place to identify (circle) the manufacturer of the
chemical tanks that will be used, The low bidder did not circle either. Subsequently, we inquired as to
the intent. Their response is included as Attachment F to their letter. We find the response to be
acceptable and consistent with the requirements of the technical specifications. As a result, and as
described in IB 1.12, we recommend that this matter be considered an informality and/or technical error
and the requirement to identify the proposed manufacturer on the bid form waived.
Kimley>»Horn
Page 2
The bid contained an additive alternate for the provision of the third acid feed pump. The low bidder
price for this additive alternate was $65,000. We do not believe the benefit realized by this alternate
warrants the proposed cost.
As a result of the above, we recommend award of this project to Florida Design Contractors, Inc. for their
low bid amount of $1,801,500.
Should you have questions or require anything further, please call.
Very truly yours,
KIMLEY HORN AND ASSOCIATES INC.
41V4—
William D. Reese, P.E.
Project Engineer
enclosures
BID
VILLAGE OF TEQDESTA
WATER TREATMENT PLANT UPGRADES
Bid of Florida Desin Contractors, Inc,
�
(Name)
1326 South Killian Drive, Lake Park, FL 33403
'
(Address)
to furnish all materials, equipment and labor and to perform all Work in accordance with the
Contract Documents for the Village of Tequesta Water Treatment Plant Upgrades.
To: Village ofTeqV8sba
345TequeotmDrive
TeqUeato.FL334O8
Gentlemen:
The undersigned bidder hos carefully examined the Contract Documents and the Site of the
proposed Work and |efamiliar with the nature and extent ofthe Work and any local conditions
that may inany manner affect the Work tobadone.
The undersigned agrees to do all the Work and furnish all nnoteha|m called for bythe Contract
Documents, in the manner prescribed therein and to the standards of quality and performance
established by the Engineer for the base lump oUnl hid amount listed in the spaces herein
provided, for each ofthe items orcombination ofitems stipulated.
The undersigned accepts all ofthe terms and conditions ofthe advertisement and/or Invitation
to Bid and Instructions to Bidders. |OdVdiOQ` but not limited to, those dealing with disposition of
bid security.
The undersigned represents that this bid is genuine and not made in tile interest of, or on behalf
of, any undisclosed peraon, finn or corporation; bidder has not directly or indirectly induced or
solicited any other bidder to submit o false or sham bid; bidder has not any person firm or
corporation to refrain from bidding; bidder has not sought by collusion to obtain for itself any
advantage over other bidder orover Owner.
The undersign covenants that K is qualified to do business in the State of Florida, Pa]no Beach
County and the Village VfTequesto. and has attached evidence ofbidder's qualification tOdo
business as such, urifnot attached, bidder covenants to obtain and deliver such evidence
within five days ofrequest byOwner toproduce such evidence.
B-1
Q
BASE LUMP ,SUM ,BID AMOUNT
The base lump sum bid amount for the Village of Tequesta Water Treatment Plant Upgrades
including all work specified in these documents is:
- - - -- - - -
....... _.. _ ........... and WL.Z- s ($� � )
Note, the bidder shall include a $75,000 bidding allowance in the Base Lump Sum Bid
Amount, This amount shall be to cover additional work on this project, not otherwise
identified by these documents and is subject to separate written approval by the
Engineer.
Additive Alternative: The Contractor shall supply and install upgrades to the H2SO4 feed
system (to include an additional feed pump) and appurtenant other changes) as shown on Plan
Sheet M-07, E-16, E-17. E-18,1-28,1-29 and 1-30. The Additive Alternative amount is:
dollars andQLcents
Ac panyi5p this bid is a certified or cashier's check or a bid bond in the amount of
$ — _ (not less than 5% of the bid) made payable to the Village of Wellington
which is to be forfeited as liquidated damages if, in the event this bid is accepted, the
undersigned fails to execute the agreement and furnish and pay for satisfactory performance
and payment bonds under the conditions and within the time specified in the bid; otherwise said
certified or cashier's check or bid bond is to be returned to the undersigned. Additional
requirements for the bid bond are set forth in the Invitation to Bid and Instructions to Bidders.
The undersigned agrees within fifteen (15) days from the date of acceptance of this bid, to
execute the agreement and furnish and pay for performance and payment bonds satisfactory to
the Owner, in the amount of 100% of the Contract price, guaranteeing the faithful performance
of the work and payment of bills. Said bonds shall be in accordance with the requirements of
Section 255.05, Florida Statutes and satisfy all criteria set forth in this document.
The undersigned also agrees to substantially complete the entire project scope of work within
two hundred seventy (270) days after the date when the Contract Time commences to run and
to be completed and ready for final payment within three hundred fifteen (315) days after the
Contract Time commences to run.
The undersigned further agrees to reimburse the Owner, for each calendar day elapsing
between the date herein specified as the date of substantial completion and the actual date of
such substantial completion of the contract Work in the amount of $500 per calendar day as
liquidated damages.
The undersigned further agrees to reimburse the Owner, for each calendar day elapsing
between the date herein specified as the date of final completion and the actual date of such
final completion of the Contract Work in the amount of $300 per calendar day as liquidated
damages.
B-2
040097017
C
I!
N
The undersigned further agrees to reimburse the Owner for each hour elapsing between the
b[Den noOtrs[tUo|k/ allocated for total or partial plant shutdown and actual p|mrd shutdown period
|Dthe amount of$1QQper full hour aeliquidated damages.
The Contractor acknowledges existence of, and guarantees full compliance with the Florida
Trench Safety Act.
The Bidder acknowledges the receipt ofAddenda No'n.
The hd|oxvn0 is a complete list of the sVbcortnauk)[G to be used if the undersigned is awarded
the Contract for this project. Failure to list all nuboonƒns:bJno will give the Owner the right to
require a change in subcontractors without any Change in the contract time or cost, or rejection
ofthe bid. Subcontractors performing more than $25,000 in work (equipment and labor) on the
project must be named below as well as subcontractors for disciplines listed below. List
subcontractors other than for the indicated disciplines to the extent necessary to satisfy the
$25.000 criteria. Subcontractors named below may not be changed bythe Contractor. The
Owner may request achange under the terms of applicable sections ofthe General Conditions.
If a work type category listed below is to be performed by the General Contractor, vv[ita the
words "Not bySubcontractor" onthe applicable line.
Type of Work
Electrical
Instrumentation
(System Integrator)
Name, address, and telephone number of Subcontractor
�L
C C |s 63YU J
B-3
The Contractor shall circle the name ofthe manufacturer for the following equipment items that
will beused and was used 1Othe computation ofthe Base Lump Sum Bid Amount. Circle only
one of the DG0md rn@OWfantunano for each item, Failure to circle one of the named
manufacturers in each category may maou|t in rejection of the entire bid.
ITEM MANUFACTURER
Chemical Tank Manufacturer PolyurDcea sing,Snvdar
This bid is Submitted by: Name (print) Thomas Fl. Clarke who is an
Officer of the above firm duly authorized to sign bids and enter into contracts. I certify that this
bid is made without prior understanding, agreement, or connection with any corporation, firm, or
person submitting a bid for the same materials, supplies, or equipment, and is in all respects fair
and without collusion or fraud. I understand collusive bidding is a violation of State and Federal
law and can result in fines, prison sentences, and civil damage awards. I agree to abide by all
conditions of this bid
Dated this 14th day of August .2018
Contractor: Florida Design Contractors, Inc.
Address: 1326 South Killian Drive,
Lake Park, FL 33403
If this bid is rendered by a o0qpo0Upn` the corporate seal attested by the secretary shall be
affixed below. Any agent signing this bid shall attach to this form evidence of legal authority.
B4
' THE AMERICAN INSTITUTE OF ARCHITECTS
AIA Document A310
Bid Bond
KNOW ALL MEN BY THESE PRESENTS, THAT WE Florida Design Contractors Inc.
1326 S. Killian Drive, Lake Park, FL 33403
as Principal, hereinafter called the Principal, and Fidelity and Deposit Company of Maryland
1299 Zurich Way, 5th Floor Schaumburg IL 60196-1056
a corporation duly organized under the laws of the State of
MD
as Surety, hereinafter called the Surety, are held and firmly bound unto Village of Tequesta
345 Tequesta Drive, Tequesta, FL 33469
as Obligee, hereinafter called the Obligee, in the sum of Five Percent of Amount Bid
Dollars ($ 5% ),
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs,
executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitted a bid for Village of Tequesta - WTP Upgrades
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with
the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or
Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt
payment of labor and materials furnished in the prosecution thereof, or in the event of the failure of the Principal to enter
such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the
penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith
contract with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise
to remain in full force and effect.
Signed and sealed this
Kath
(Witness)
14th day of August 1 2018
Florida Desi tors c
(Prind rincip (seal)
B:
T as H. Cla President (Title)
Fidelity and Deposit Company of Maryland
/1 r(Surety) n (Sea!)
Attorney -in -Fact b. Michael Stevens r (Title)
AIA DOCUMLNr A310 • BID BOND • AIA • FEBRUARY 1970 ED. • THE AMERICAN
INs'ri,rUTE OF ARCHITECTS, 173- N.Y. AVE., N.W., WASHINGTON, D.C. 20006
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS: That the ZURICH AMERICAN INSURANCE COMPANY, a corporation of the State of New
York, the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, a corporation of the State of Maryland, and the FIDELITY
AND DEPOSIT COMPANY OF MARYLAND a corporation of the State of Maryland (herein collectively called the "Companies"), by
MICHAEL BOND, Vice President, in pursuance of authority granted by Article V, Section 8, of the By -Laws of said Companies, which
are set forth on the reverse side hereof and are hereby certified to be in full force and effect on the date hereof, do hereby nominate,
constitute, and appoint Don A. LAMBERT JR., Don A. LAMBERT, III and D. Michael STEVENS, all of Jupiter, Florida, EACH its
true and lawful agent and Attorney -in -Fact, to make, execute, seal and deliver, for, and on its behalf as surety, and as its act and deed: any
and all bonds and undertakings, and the execution of such bonds or undertakings in pursuance of these presents, shall be as binding upon
said Companies, as fully and amply, to all intents and purposes, as if they had been duly executed and acknowledged by the regularly elected
officers of the ZURICH AMERICAN INSURANCE COMPANY at its office in New York, New York., the regularly elected officers of the
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at its office in Owings Mills, Maryland., and the regularly elected
officers of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at its office in Owings Mills, Maryland., in their own proper
persons.
The said Vice President does hereby certify that the extract set forth on the reverse side hereof is a true copy of Article V, Section 8, of
the By -Laws of said Companies, and is now in force.
IN WITNESS WHEREOF, the said Vice -President has hereunto subscribed his/her names and affixed the Corporate Seals of the said
ZURICH AMERICAN INSURANCE COMPANY, COLONIAL AMERICAN CASUALTY AND SURETY COMPANY, and
FIDELITY AND DEPOSIT COMPANY OF MARYLAND, this 24th day of August, A.D. 2017.
ATTEST:
t
ZURICH AMERICAN INSURANCE COMPANY
COLONIAL AMERICAN CASUALTY AND SURETY COMPANY
FIDELITY AND DEPOSIT COMPANY OF MARYLAND
��Y �o O[�Os� •"•'N 1NSVq:``''[��a
.v r
• s
SEAL
�on7 Itp �� 6�ti tflDe i 6p
Assistant Secretary Vice President
Dawn E. Brown Michael Bond
State of Maryland
County of Baltimore
On this 24th day of August, A.D. 2017, before the subscriber, a Notary Public of the State of Maryland, duly commissioned and qualified, MICHAEL
BOND, Vice President, and DAWN E. BROWN, Assistant Secretary, of the Companies, to me personally known to be the individuals and officers
described in and who executed the preceding instrument, and acknowledged the execution of same, and being by me duly swom, deposeth and saith, that
he/she is the said officer of the Company aforesaid, and that the seals affixed to the preceding instrument are the Corporate Seals of said Companies, and that
the said Corporate Seals and the signature as such officer were duly affixed and subscribed to the said instrument by the authority and direction of the said
Corporations.
IN TESTIMONY WHEREOF, I have hereunto set my hand and affixed my Official Seal the day and year first above written.
(� � �'v'�'-rl'_ d'•. All°l�' � `'
Constance A. Dunn, Notary Public
My Commission Expires: July 9, 2019
POA -F 031-0102A
EXTRACT FROM BY-LAWS OF THE COMPANIES
"Article V, Section 8, Attorneys -in -Fact. The Chief Executive Officer, the President, or any Executive Vice President or Vice President
may, by written instrument under the attested corporate seal, appoint attorneys -in -fact with authority to execute bonds, policies,
recognizances, stipulations, undertakings, or other like instruments on behalf of the Company, and may authorize any officer or any such
attorney-in-fact to affix the corporate seal thereto; and may with or without cause modify of revoke any such appointment or authority at any
time."
CERTIFICATE
I, the undersigned, Vice President of the ZURICH AMERICAN INSURANCE COMPANY, the COLONIAL AMERICAN
CASUALTY AND SURETY COMPANY, and the FIDELITY AND DEPOSIT COMPANY OF MARYLAND, do hereby certify that the
foregoing Power of Attorney is still in full force and effect on the date of this certificate; and I do further certify that Article V, Section 8, of
the By -Laws of the Companies is still in force.
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the ZURICH AMERICAN INSURANCE COMPANY at a meeting duly called and held on the 15th day of December 1998.
RESOLVED: "That the signature of the President or a Vice President and the attesting signature of a Secretary or an Assistant Secretary
and the Seal of the Company may be affixed by facsimile on any Power of Attorney ... Any such Power or any certificate thereof bearing such
facsimile signature and seal shall be valid and binding on the Company."
This Power of Attorney and Certificate may be signed by facsimile under and by authority of the following resolution of the Board of
Directors of the COLONIAL AMERICAN CASUALTY AND SURETY COMPANY at a meeting duly called and held on the 5th day of
May, 1994, and the following resolution of the Board of Directors of the FIDELITY AND DEPOSIT COMPANY OF MARYLAND at a
meeting duly called and held on the 10th day of May, 1990.
RESOLVED: "That the facsimile or mechanically reproduced seal of the company and facsimile or mechanically reproduced signature
of any Vice -President, Secretary, or Assistant Secretary of the Company, whether made heretofore or hereafter, wherever appearing upon a
certified copy of any power of attorney issued by the Company, shall be valid and binding upon the Company with the same force and effect
as though manually affixed.
IN TESTIMONY WHEREOF, I have hereunto subscribed my name and affixed the corporate seals of the said Companies,
this 14 day of August 120 18.
o 01.-141111
V�1y'
.f "4 s • ��t 3° ea t m • �
;05 8EAL,t�
David McVicker, Vice President
TO REPORT A CLAIM WITH REGARD TO A SURETY BOND, PLEASE SUBMIT ALL REQUIRED
INFORMATION TO:
Zurich American Insurance Co.
Attn: Surety Claims
1299 Zurich Way
Schaumburg, IL 60196-1056
DRUG FREE WORKPLACE
Preference shall be given to businesses with drug-free workplace programs. Whenever two or
more Bids are equal with respect to price, quality and service are received by the Village for the
procurement of commodities or contractual services, a Bid received from business that certified
that it has implemented a drug free workplace program shall be given preference in the award
process. Established procedures for processing tie bids will be followed if none of the tie
vendors have a drug-free workplace program, In order to have a drug-free workplace program,
a business shall:
1. Publish a statement notifying employees that the unlawful FnanUfacture, d|sthbution,
dispensing, S\ or use ofo controlled substance is prohibited in the workplace and
specifying the actions that will be taken against employees for violations of such prohibition.
2. Inform employees about the dangers of drug abuse in the workplace, the business's
Of maintaining a drug-free workplace, any available drug counseling, [mhmbi|itaUon, and
employee assistance progr@nOg, and the penalties that may be imposed upon employees for
drug abuse violations.
3. Give each employee engaged in providing the commodities orcontractual services that are
under Bid a copy of the statement specified in subsection (1).
4. In the statement specified in subsection (1), notify the employees that, as condition of
working on the commodities or contractual oendoeo that are under Bid, the employee will
abide bvthe terms ofthe statement and will notify the employer Vfany conviction of, orplea
of guilty or nolo contendere to, any violation of Chapter 893 orOfany controlled substance
|avv of the United States or any state, for a violation occurring in the workplace no later than
five (5)days after such conviction.
5. Impose asanction on, or require the satisfactory participation in a drug abuse assistance or
rehabilitation program if such is available in the employee's oornnnunity, by any employee
who ismoconvicted.
6. Make a good faith effort to continue to maintain a workplace through
implementation cfthis section.
As to the person a��i d to sign the statement, I certify that this firm complies fully with the
@/14/2D18
Date
SUBMIT THIS FORM WITH BID.
Dmnot execute unless representations made are valid.
|B'9
u*000ron
Kimsey»>Horn
August 15, 2018
Thomas H. Clarke, President
Florida Design Contractors, Inc.
1326 S, Killian Drive
Lake Park, FL 33403
RE: Village of Tequesta, Water Treatment Plant Upgrades
Dear Mr, Clarke:
Your lump sum bid on the above -referenced project in the amount of $1,801,500 is the apparent low bid.
We further note that the Additive Alternate bid in the amount of $65,000 is also the low bid for that item.
Please accept our congratulations,
In order to evaluate the bid, we will need a few additional items, as set forth below.
1. Please supply a certificate of incorporation or other documentation that confirms that Florida
Design Contractors, Inc. has been in the General Contracting business for at least the past 10
years. See IB 1.09, 1.
2. Please supply documentation that confirms that Florida Design Contractors, Inc. is properly
licensed to perform as a General Contractor, See IB 1.09, 2,
3. Please supply a list of five similar projects completed within the past 10 years to satisfy the
criteria set forth in IB, 1.09.3. Please provide, for each project, the client name, date completed,
brief project description, final project cost, and contact person with phone number.
4. Please provide a notarized statement certifying that Florida Design Contractors, Inc. has not
defaulted to a bonding company for completion of any of the projects referenced under Item 3
above.
5. Please supply information satisfying the requirements of IB, 1.09, 5 relative to the electrical
subcontractor. This includes projects over the past 10 years of electrical value greater than
$250,000, evidence of proper licensing and evidence that the subcontractor has been in
business under its current name for the past five years. For example projects, please supply
contact person, dates and other information similar to item 3 above.
6. For the instrumentation contractor, please supply information to satisfy the requirements of IB
1.09, 6. Please supply in a format similar to the information to be supplied for the electrical
subcontractor.
Kimley»>Horn
Page 2
7. Please refer to page B-4 of the bid form and note that a manufacturer for the chemical tanks has
not been named. Please advise whether this was intentional or an error, and if the latter, identify
which manufacturer is intended for inclusion.
Please forward the above responses at your earliest opportunity. Once again, congratulations on
submittal of your apparent low bid. Should you have questions or require any additional information,
please call my office.
Very truly yours,
KIM LEY MaRN AND ASSOCIATES INC.
William D. Reese, P.E.
Project Engineer
enclosures
FLORIDA
-CONTR
August 22, 2018
William Reese
Kimley-Horn
Email: William.reese@kimley-horn.com
Project: Village of Tequesta- WTP Upgrades
Mr. Reese:
0
CGC040304
DESIGN
T 0 R S
Per your letter dated August 15, 2018 and marked Village of Tequesta Water Treatment Plant Upgrades,
we have enclosed and completed the request for documentation numbers one through seven. We have
included the requested credentials for our Electrical and Instrumentation subcontractors.
We look forward to working with Kimley-Horn and making this a successful project. Should you have any
questions or require additional information please feel free to call.
Respectfully,
7-110Was ff. Clarke
Thomas H. Clarke
President
Florida Design Contractors
Cc: Tammy Gideon, FDC
1
A: 1326 South Killian Drive, Lake Park, FL 33403 1 W: ,igncontractors.com I L• #CGC-040304
0: 561-845-1233 1 F: 561-848-5992 1 E: tclarke@floridadesigncontractors.com
FLORIDA
DESIGNI
CONTRACTORS
Attachment A License/Company Information
Brpartmrnt of #§tatr
I certify that the attached is a true and correct copy
Articles of Incorporation of FLORIDA DESIGN CONTRACTOR
corporation organized` under the 'Laws of the State of ' Flor
on October 1, 1991, as shown by the records of thi
The document number of this corporation is S84434.
Aben unbrr mp banb aub tlj
0rrat *Pal of for z---,tatr of Par
at Tallalp.55rr, tlje Capital, tlji�
3rd bap of Octobe
CR2EO22 (2-91)
IJcm ffiMH4
secru#zcr of ;�$tute
HN't�R�E�c��BMDnC�nCDnCDnCDnCDnC
RICK SCOTT, GOVERNOR
JONATHAN ZACHEM, SECRETARY
STATE OF FLORIDA
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION
CONSTRUCTION INDUSTRY LICENSING BOARD
THE GENERAL CONTRACTOR HEREIN IS CERTIFIED UNDER THE
PROVISIONS OF CHAPTER 489, FLORIDA STATUTES
CLARKE, THOMAS HARMAN
FLORIDA DESIGN CONTRACTORS, INC.
1326 S KI LLIAN DR
LAKE PARK FL 33403
LICENSE NUMBER: CGC040304
EXPIRATION DATE: AUGUST 31, 2020
Always verify licenses online at MyFloridaLicense.com
FF% =
LL Do not alter this document in any form.
LL
This is your license. It is unlawful for anyone other than the licensee to use this document.
❑ Fr
CONSTITUTIONAL TAX COLLECTOR
,° rrriag 11,11;n Re'Ich County
Serving you,
TYPE OF BUSINESS
23-0102 CW GENERAL CONTRACT OR
P.O. Box 3353, West Palm Beach, FL 33402-3353
www.pbctax.com Tal: (561) 355-2264
OWNER
CLARKE THOMAS H
This document is valid only when receipted by the Tax Collector's Office.
FLORIDA DESIGN CONTRACTORS INC
FLORIDA DESIGN CONTRACTORS INC
1326 S KILLIAN DR
LAKE PARK, FL 33403-1919
I lilt it III I If1III11f 1111111fill] III it IIIII III
ANNE N/1. GANNON
(0 CONSTITUTIONAL TAX COLLECTOR
Scuwittg Puhn Beach C011111y
Serving t/ou.
-LOCATED AT -
1326 S KILLIAN DRIVE
LAKE PARK, FL 33403-1919
CERTIFICATION # RECEIPT -!DATE PAID AMT PAID BILL #
'.,GCC40304 I WT606736 - 07:19/17 I $3fi9.6n 840'144394
STATE OF FLORIDA
PALM BEACH COUNTY
81-7 201712018 LOCAL BUSINESS TAX RECEIPT
LBTR Number: 199602411
EXPIRES: SEPTEMBER 30, 2018
This receipt grants the privilege of engaging in or
managing any business profession or occupation
within its jurisdiction and MUST be conspicuously
displayed at the place of business and in such a
manner as to be open to the view of the public.
P.O. Box 3353, West Palm Beach, FL 33402-3353
www.pbctax.com Tel: (561) 355-2264
**LOCATED AT**
1326 S KILLIAN DRIVE
LAKE PARK, FL 33403-1919
TYPE OF BUSINESS OWNER CERTIFICATION tt RECEIPT WDATE PAID AMT PAID BILL #
23-0051 GENERAL CONTRACTOR CLARKE THOMAS H CGC040304 U17.606736-07/19/17 $27.50 840144395
This document is valid only when receipted by the Tax Collector's Office.
FLORIDA DESIGN CONTRACTORS INC
FLORIDA DESIGN CONTRACTORS INC
1326 S KILLIAN DR
LAKE PARK, FL 33403-1919
AW1111M
STATE OF FLORIDA
PALM BEACH COUNTY
133-6 2017/2018 LOCAL BUSINESS TAX RECEIPT
LBTR Number: 199602410
EXPIRES: SEPTEMBER 30, 2018
This receipt grants the privilege of engaging in or
managing any business profession or occupation
within its jurisdiction and MUST be conspicuously
displayed at the place of business and in such a
manner as to be open to the view of the public.
OT, iQ79- W-'I
FLORIDA
DESIGN
CONTRACTORS
Attachment B Similar Project Experience
1000
Village of Tequesta WTP
1095 Phase II & III - RO Expansion
Project Description:
The Reverse Osmosis Water Treatment Plant included an existing 1.2 MGD RO System with the
space to upgrades to a 3.6 MGD facility. The 2.4 MGD upgrade was conducted in two separate
projects. The first upgrade consisted of adding one 1.2 MGD skid in 2006-2007 and then
followed by a third and finall 1.2 MDG skid in 2010-2011.
Addition of the 2.4 MGD capacity also required addition of; two micron cartridge filters, two 1,400
gpm Horizontal Well Pumps, 1,600 gpm Horizontal Split Case High Service Pump, 2,500 gpm
Vertical Turbine Clearwell Transfer Pump, two 1,250 gpm Vertical Turbine RO High Pressure
Pumps all associated piping and valve modifications, electrical and I&C upgrades and minor
architectural and structural upgrades.
A new Odor Control System was installed to remove the odors which consisted of; one
degasifier, two two-stage scrubbers, two recirculation pumps, PVC piping and FRP ductwork.
Lastly, demolition of the existing chlorine gas system and replacement with a liquid Sodium
Hypochlorite system. The new chemical system included a prefabricated concrete building for
the five chemical transfer pumps and a cast -in-place containment area for the two 8,750 gallon
FRP bulk Sodium Hypochlorite storage tanks.
ARCADISi"L Oi 'tOG��a
7
T 11
Global Water
O
'Cy COU'Al
— ESTABLISHED 1979 —
CqM&A
AM
CI
Me Me
City of Pompano Beach
WTP Improvements
Project Description:
The WTP improvements included; modifications to an existing Ammonia Bulk Storage Feed
System, a new Bulk Sodium Hypochlorite Feed System, and Finished Water Yard Piping
improvements.
The Ammonia Bulk Storage Tank work included; distribution piping including diffusers into
the existing Clearwell and refurbishment of the existing Clearwell including coatings and baffles.
The Bulk Sodium Hypochlorite Feed System included the following; demolition of existing
chemical systems, installation of (3 ea) 10,300 gal chemical storage tanks, installation of (1 ea)
2,600 gal chemical day tank, installation of (3 ea) duplex chemical skids, all associated chemical
piping, concrete slab on grade with containment walls and pre -fabricated metal building.
The Finished Water Piping improvements included; 42" yard piping from the existing high
service pump station to the existing Clearwell and Filters, new flanged suction piping and
header piping for (5 ea) High Service Pumps. This work included a 42" line stop to isolate flows
during a tie-in to the existing system.
The work also included all electrical and instrumentation and controls upgrades.
m ano6"R"'JDA
p TSC- ACOBS FLANbeach. J DESI
Florida's Warmest Welcome CONTRACTORS
1085 City of North Miami Beach
Norwood WTP - VOC Removal Project
--- -- _� 1s -- — g -- ID
XTY11
• : ash . .', � ,
Project Description:
The scope of work for this project included; expansion to the existing Forced Aeration
System, expansion to the existing Transfer Pump Station, modifications and rehabilitation to
the existing Hydrotreater #2 & #3, replacement of the existing lime feed system, exansion of
the existing Nanofiltration Degasification System and rehabilitation of the existing Biscayne
Aquifer Wells #4, #9 & #10.
Expansion to the existing Transfer Pump Station included; addition of (2 ea) Vertical Turbine
Transfer Can Pumps with a design capacity of 3,000 gpm per pump, 30" supply water piping,
and a stilling well.
Expansion to the existing Forced Aeration System included; installation of (1 ea) 1.44 MGD
forced draft aerator and relocation of (2 ea) 1.44 MGD existing forced draft aerators totaling
a 4.32 MGD forced draft aeration system, installation of a Antiscalant storage and feed system,
and 36" water piping.
The Degasification System expansion included a new Degasifier and FRP dutcwork
The replacement of the Lime Feed System included new equipment in the East Lime Silo.
CARBONAIR
EST. '1979 -
FLORIDA
DA
DESIGN
CONTRACTORS
1145
Immokalee Water & Sewer District WWTP
Wastewater Systems Improvements - Phase
10
Project Description:
The construction of a 0.75 MGD expansion to the existing WWTP including; a duplex
submersible plant influent wetwell pump station, a new headworks with mechanical
bar screens and a grit separation system, a new cast -in-place 1.5 MGD oxidation
ditch with (3) rotor -type aerators, a new 70 -foot diameter cast -in-place clarifier, a
new sludge holding tank with a floating surface aerator, a new duplex RAS/WAS
pump station, a new duplex secondary effluent wetwell pump station, a new 4 -
channel chlorine contact basin, a new 400 sf chlorine feed building and chlorine
system, a new 1,500 sf masonry administration building, a new 600 sf precast
concrete electrical building, a 550kW standby generator, site piping, electrical
system expansion, instrumentation and controls expansion, and all other related
items of construction for a complete 0.75 MGD expansion.
IMMOKALEE
WATER
SEWER
DISTRICT
JA =COM
_! ::;REEL.EYQniD HAPJ5EiV
- ESTABLISHED 1979 -
CONTRACTORS
CIVIL 8 ENVIRONMENTAL
1215
Hernando County Utilities
Seville WTF Modifications
Project Description:
Due to growing local area water demands, the Hernando County Utilities Department required a
new water treatment facility be constructed for these neighboring developments. Quality
water production would require collection of aquifier water, storage, disinfection and pump
capabilities.
An additional 0.86 MGD water supply was obtained by drilling (1) 16" diameter well to a depth of
250 below surface elevation. Installation of 10HP Submersbile Well Pump was controlled by a
Combination Starter Panel and miscellanous field instrumentation.
The well feed a 750,000 gallon Prestressed Concrete Ground Storage Tank constructed by the
Crom Corporation and a Submerisble Tank Mixer was used maintain proper disinfection.
The Pump Station was a Pre -Fabricated Pump Station fabricated by Engineered Fluid, Inc. The
Pump Station included; a 800A/480V Power Panel, (4) 480V Variable Frequency Drives rated for
for (4) 50HP Horizontal Split -Case High Service Pumps, a Triplex Sodium Hypochlorite Chemical
Feed & Storage System, Master SCADA & RTU Control Panel and process piping.
The project also included; a 500kVA Unit Substation, 350 kW Generator with a 800A Automatic
Transfer Switch, structural concrete, site piping, sitework & demo of the exist 1.6 MGD Facility.
ESTABLISHED 1979
EF
OCFROM
AAPCADIS q&ENVIRIOIAMITAL
MIN
1220
FGUA Lehigh Acres WWTP
Headworks Replacement
Project Description:
The existing headworks system was obsolete and not screening the influent properly. Over
time, excess grit and debris can cause damage to equipment and compromise the integrity of
the treated water.
Florida Design Contractors constructed a new headworks structure, as shown above, which
included a Mechanical Screening System, Grit Removal System, and Reclaimed Water
Distribution System to deliver seal and flushing water to the equipment listed above. The FGUA
was able to minimize expenses by utilizing reclaimed water in lieu of potable water for the seal
and flushing systems. The following major manufacturers were involved throught the process:
Mechanical Screening System — Huber Technology
Grit Removal System — Hydro International
Reclaimed Water Delivery — Patterson Pump
Instrumentation and Controls — BCI Technologies
-- ESTABLISHED 1979
moss
• - •
KELLEY
:
INC`, 014110kATEID
CONTRACTORS
CIVIL & ENVIRONMENTAL OW
1270
City of Marco Island
RWPF Headworks Replacement
Project Description:
This projected incorporated a new headworks facility to the City's existing 3.5 MGD plant.
The cast -in-place concrete headworks facility included; an influent flow meter assembly, (3)
in -channel drum screens, sluice and weir gates, diversion of influent and effluent piping
from the old headworks to the new headworks, a biological odor control system which
associated foul air FRP ductwork, influent channel coatings and electrical and I&C upgrades.
Once the new headworks facility was fully operational, we proceeded to demolish the
existing headworks facility.
The project also included converting an existing empty pre -stressed concrete ground
storage tank into an influent raw sewage storage tank with a blower, SS air piping and fine -
bubble diffusers.
�� Cardno�
Shaping the Future
City or t(,
-- ESTABLISHED 1979 --
• ' 1
CONTRACTORS
CIVIL i ENVIRONMENTAL UIFF
w'
FL"O.RIDAI
DESIGN
CONTRACTORS
Attachment C Bond Statement
-EST. 1979 - CGcoetonn4l
FLORIDA DESIGN
CONTRA TORS
August 20, 2018
Mr. William Reese
Kimley-Horn
1920 Wekiva Way
W. Palm Beach, FL 33411
Re: Village of Tequesta Water Treatment Plant Upgrades
Mr. Reese:
This letter will service and confirmation that Florida Design Contractors Inc. has not defaulted to a
x+1111 Id dV) coma f `r completion of an of the projects during its history.
C'ONTRq• p Q p Y p 1 g
<v�o.QORiig�r�,�
ef
S
O om
60�yPr
FLO
114111111%
Sworn and subscribed before me this 20th day of August 2018.
`�lFRY P4'<, Notary Public Mato of Florida
Jo-ann Escott
04 Nib c orrmissicn FF 929945
�FaF Fro° Expires 11128/20
1326 South Killian Drive West Palm Beach, FL 33403
(561) 845-1233 Florida DesignContractors.com
-.,- --." 'w"
FLORIDA
DESIGN
CONTRACTORS
Attachment D Electrical Subcontractor Credentials
RICK SCOTT, GOVERNOR JONATHAN ZACHEM, SECRETARY
a
bpr
STATE OF FLORIDA
DEPARTMENT OF BUSINESS AND PROFESSIONAL REGULATION
ELECTRICAL CONTRACTORS LICENSING BOARD
THE ELECTRICAL CONTRACTOR HEREIN IS CERTIFIED UNDER THE
PROVISIONS OF CHAPTER 489, FLORIDA STATUTES
LAESSIG, THOMAS
POWERLINE OF SOUTH FLORIDA INC
6839 CYPRESS COVE CRICLE - -
JUPITER FL :33:458!r►
LICENSE NUMBER: EC13003753
EXPIRATION DATE: AUGUST 31, 2020
Always verify licenses online at MyFloridaLicense.com
NMI �a
Do not alter this document in any form.
This is your license. It is unlawful for anyone other than the licensee to use this document.
1:37 PM POWERLINE OF SOUTH FLORIDA, INC
08/21/18
Accrual Basis Sales by Customer Detail
January 1, 2010 through August 21, 2018
Projects > $250,000 from 2008 till Present
JOB AMOUNT Contact
1. Springtree Wellfied Improvement $ 673,643.38 City of Sunrise Arcadis, Ron Mattingly Hillers Electrical Engineers M. Luther
Electrical Southeast Well Drilling August 2016 -April 2018 mluther@hillersee.com
561-451-9165
2. WTP#3 Scrubber 20416 $ 397,066.33 Palm Beach County Water Utility Department
PBCWUD WUD 12-083 Calvin Giodano & Assoc. Cardinal Contractors Electrical Design Assoc. L.Reyes
Electrical Feb 2013 -Nov 2015 Ireves@goeda.com
561-819-5556
3. Eastern Wellfield Improvements 20994 $ 253,838.80 City of West Palm Beach iohn.cairnes@mockroos.com0 561-683-3113 ext 275
Electrical Mock Roos & Assoc. C&W Electrical Engineers Southeast Drilling John Cairnes
June 2014 -Feb 2016 jreyes@Cweng.us 561-642-5333
Jose Reyes
4. WTP # 9 CAT Conv. $ 326,623.96 Palm Beach County Water Utility Department L. Reyes
WUD 13-075 Calvin Giordano & Assoc Electrical Design Assoc Ireves@goeda.com
Electrical Cardinal Contractors 561-819-5556
Oct 2013 -June 2014
Rchipman@baxterwoodman.com 561-655-8175 ext 7708
5 Membrane Concentrate Line Re -Route $ 258,177.00 City of Boca Raton R. Chipman
Electrical Mathew Consuling Hillers Electrical Engineers Poole & Kent S. Chamness
April 2013- Sept 2014 fchamness@hillersee.com 561-451-9165 ext 231
6 WTP#2 Wellfield Upgrades $ 695,000.00 Palm Beach County Water Utility Department R. Olson
WUD 12-005 Global Tec Hillers Electrical Engineers rolson@globaltechdb.com 561-997-6433
Electrical March 2013 -March 2014
7 Sawgrass WTP Effluent Injection Pump Station $ 750,000.00 City of Sunrise S. Chamness
Electrical Hazen & Sawyer Engineers Hillers Electrical Engineers Cardinal Contractors
March 2010 -Jan 2011 fchamness@hillersee.com 561-451-9165 ext 231
Page 1 of 2
1:37 PM POWERLINE OF SOUTH FLORIDA, INC
08/21/18
Accrual Basis Sales by Customer Detail
January 1, 2010 through August 21, 2018
JOB AMOUNT Contact
8 SCWRF Effluent Pump Upgrades $ 385,000.00 Palm Beach County Hiller Electrical Engineers RI Sullivan Contractors S. Chamness
Electrical Aug 2010 -Sept 2011 fchamness@hillersee.com 561-451-9165 ext 231
9 SCWRF Odor Control Upgrades $ 659,000.00 Plam eeacgh County Hillers Electrical Engineers Jordan Jones & Goulding S. Chamness
Electrical Cardinal Contractors fchamness@hillersee.com 561-451-9165 ext 231
Jan 2009 - March 2010
10. Indian River -South R. O. Improv mark.miller(c@kimley-horn.com 561-840-0258
Electrical $ 275,250.00 Indian River County Kimley Horn Smith Electrical Engineers M. Miller
Interstate Engineering 561-616-3911 ext 202
July 2008- Aug 2010 Larry@smithengineeringconsultants.com L. Smith
Page 2 of 2
FLORIDA
DESIGN
CONTRACTORS
Attachment E Instrumentation & Control Subcontractor Credentials
C* C. CONTROL
C O R P O R A T 1 0 N
�.
.1 N T E G R A T t N G T H E F U T U R E
STATEMENT OF QUALIFICATIONS
4
C.C. Control Corporation
5760 Corporate Way
West Palm Beach, Florida 33407
Phone: 561-293-3975
Fax 561-293-3976
www.cccontrolcorp.com
Statement of Qualifications
TABLE OF CONTENTS
SECTIONL• INTRODUCTION
SECTION II: PRODUCTS AND SERVICES
• CONCEPTUAL DESIGN
• DETAILED DRAWINGS
• SHOP FABRICATIONAND ASSEMBLY
• PROGRAMMING
• FIELD ASSISTANCE
• TRAINING
• AS B UILT DOCUMENTATION
SECTIONIII: KEYPERSONNEL
SECTIONIV• PROJECT EXPERIENCE
Statement of Qualifications
I. INTRODUCTION
C.C. Control Corporation is a Systems Integrator/Supplier of Control Panels,
Instrument Panels, Control and Instrumentation Systems, PLC Systems and SCADA
(Supervisory Control and Data Acquisition) Systems for all types of process control.
Founded in 1980, C.C. Control Corporation has been in business for over 35
years. That is a lot of experience in the Water and Wastewater venues serving
primarily South and Central Florida. Our entire operation is housed in a 13,200 sq./ft
facility constructed in 2002. The facility is equipped with state of the art computer
systems, AutoCad and ePlan stations, manufacturing tools, vehicles and other
miscellaneous equipment required to fabricate and support the operations.
C.C. Control Corporation has been a UL 508A and 698A certified shop since
1983.
Statement of Qualifications
II. PRODUCTS AND SERVICES
CONCEPTUAL DESIGN
With over 35 years of project management experience, C.C. Control
Corporation understands that solutions must be customized to fit your
environment. Your business requirements are unique and that's why we are
dedicated to getting to know you and understand your unique needs and goals.
We work with you from the beginning to define your requirements, which are the
foundation for making the right technology choices. From there we will help
develop the strategies to implement a system that meets your requirements and
exceeds your expectations.
DETAILED DRAWINGS
C.0 Control Corporation understands the importance of proper
documentation. We also understand the pain and in -efficiency caused by a poorly
documented automation system. We can research your process and provide
documentation packages that include schematic drawings developed with either
AutoCad or EPlan as well as system descriptions and sequence of operation
documents.
SHOP FABRICA TION AND ASSEMBLY
Our fabrication facility can provide custom electrical assemblies as part
of an automation project or as a stand-alone product. Panels are assembled to the
highest standards in our panel shop which covers construction, mounting, wiring,
inspection, testing, packaging and delivery. All our panels are shipped with
electrical drawings and layouts. In addition, UL 508A or UL 698A certification
can be provided for any panel. Our designers and technicians are in the same
facility which enables us to communicate closely on any issues that arise. We
thoroughly simulate and test each panel to ensure proper operation and safety
once installed in the field.
Statement of Qu alifie ations
PROGRAMMING
Our team was built on the foundation of automating projects.
Programmable logic controller is the proven choice when it comes down to
reliability and industrial hardness. Our automation specialists are senior level
programmers who have been developing PLC programs ranging from small
program modifications to full line control and integration. Our programs are
concise and well documented. We continually enroll in software maintenance and
support programs to ensure we are developing PLC logic with the most advanced
software. These support programs allow us to receive comprehensive technical
support, access to online resources, knowledge base articles and product
upgrades. We can provide efficient and effective PLC programming services
using a variety of PLC brands and Scada brands as follows:
• Allen Bradley
• Siemens
• GE Fanuc
• Modicon
• Motorola
• Omron
• SQD/Schneider Electric
• Bristol Babcock
• Rockwell Automation RSView
• GE Intellution
• GE iFix
• GE Cimplicity
• Trihedral VT Scada
• Wonderware
We have designed numerous Supervisory Control and Data Acquisition
systems with non-proprietary PLC's for central and remote telemetry
systems and have maintained an open architecture philosophy. Our
telemetry installations are easy to maintain, upgrade and troubleshoot. RF
telemetry, telephone modems, LAN's, WAN's or the internet are all
options for our SCADA systems distributed communications. Whether
for water treatment plants, distributed pumping stations, lift stations or
industrial facilities, C.C. Control Corporation can provide SCADA
systems tailored to meet your needs.
Statement of Qualifications
FIELD ASSISTANCE
Our technicians and programmers have many years of experience with
system startups and solving operational problems in the field. We can provide
equipment calibration, inspection, testing, ongoing maintenance, troubleshooting,
repairs, panel modifications and system programming. We offer comprehensive
24-hour emergency service and maintenance on our own systems and systems
installed and configured by others. On-going system support may be
accomplished via a modem or internet link to diagnose problems or make minor
system adjustments. We are dedicated to the performance of your system and the
success of your operation.
TRAINING
Equipment and software training can be provided on-site or at our facility
for operations and maintenance personnel. Hands-on approach and training
material is utilized for a comprehensive program that is custom tailored for each
client. Instructional videos can be provided for ongoing training of personnel.
AS -BUILT DOCUMENTATION
C.C. Control Corp. takes pride in the accuracy and completeness of our
drawings and documentation packages. Every system we build is accompanied
by a set of notebooks and/or electronic documents that contain as -built drawings,
program printouts, calibration, loop checkout reports, software backup files on
CD and operation and maintenance instructions.
Statement of Qualifications
III. KEY PERSONNEL
• James J. Hecht — President, Senior Project Engineer
• Luis L. Garcia — Vice President, Estimating and Sales
• Matthew Skidmore — Principal, Senior Project Engineer
• J.P. Mahieu — Estimating and Sales
• John Stock — Estimating and Sales
• Alejandro Mena — Project Engineer
• Jeffery Needs — Project engineer, EPlan, AutoCad designer
• Thomas Fedina — Purchasing Manager
• Colleen McKenna — Office Manager
• Frank Vitale — Service Manager
• Brandon Tufts — Service Technician
• Rob Whitney — Shop Manager
IV. PROJECT EXPERIENCE
City of Lake Worth RO Improvements - $1,350,000
Lake Worth, FL. 33460
Project Completion Date: 09/2011
Project Type: Water Treatment
o Major Components/Systems
■ SCADA system communication network with Ethernet network
switches, fiberoptic modules, communication patch panels and UPS
■ Main Control Redundant PLC System (A -B ControlLogix) for
ControlNet I/O Network
■ ControlNet Remote 1/0 Control Panels including Pre -Treatment
System, Membrane Control Panels, RO Treatment Chemicals,
Scrubber Chemicals, Permeate Degas, Concentrate Disposal and CIP
System
■ Instrumentation skids including Pre -Treatment, Post -Treatment,
Clearwell pH, Permeate Scrubber ph/ORP and Concentrate Disposal
■ (11) Control panel industrial computers running Trihedral VTScada
o SCADA integration of all control panels and instrumentation with newly
developed SCADA screens including system loop -checks and system start-up
utilizing
Statement of Qualifications
City of North Lauderdale WTP Improvements - $690,000
North Lauderdale, Fl. 33068
Project Completion Date: 04/2012
Project Type: Water Treatment
o Major Components/Systems
■ Main Control PLC (A -B ControlLogix) for Ethernet 1/0 Network
■ Ethernet Remote 1/0 Control Panels including Lime System, Gravity
Filters, Chlorine System, Sludge System and Finished Water
■ Plant Master Radio for wellfield control panels over 900 mHz Ethernet
radio system
■ (3) remote Ethernet wellfield control panels
■ Various instrumentation including insertion flowmeters, ultrasonic
level transmitters, pressure transmitters (gauge and differential),
turbidity, ammonia and pH analyzers
■ Redundant SCADA servers running Trihedral VTScada
o SCADA integration of all control panels and instrumentation with newly
developed SCADA screens including system loop -checks and system start-up
• Seacoast Utility Authority Repump Facility Modifications - $650,000
Palm Beach Gardens, FL 33410
Project Completion Date: 06/2014
Project Type: Water Treatment
o Major Components/Systems
■ Master Radio Control Panel for Ethernet I/O Network
■ (6) Raw water well remote 1/0 control panels utilizing 900mHz
Ethernet radios
■ (3) Water repump remote 1/0 control panels utilizing 900mHz
Ethernet radios
■ (6) Raw water well remote I/O control panels connected via. Fiber
optic Ethernet through (1) of the repump control panels
o Provided loop -check and start-up support for system integration
Statement of Qualifications
• Seacoast Utility Authority Hood Road WTP RO Improvements - $2,060,000
Palm Beach Gardens, FL 33410
Project Completion Date: 11/2014
Project Type: Water Treatment
o Major Components/Systems
■ Main Control PLC (A -B ControlLogix) for Ethernet I/O Network
■ Ethernet Remote I/O Control Panels including Nanofiltration System,
Deep Well, Chemical Systems and Supply Wells
■ Various instrumentation including magnetic flowmeters, venturi
flowmeters, ultrasonic level transmitters, pressure transmitters (gauge
and differential), pressure gauges and switches, pH, ORP and
conductivity analyzers
o Provided loop -check and start-up support for system integration
• City of Sunrise WWTP Biosolids Management - $420,000
Sunrise, FL. 33325
Project Completion Date: 06/2016
Project Type: Wastewater Treatment
o Project scope consisted of work at The Sawgrass WWTP and The Springtree
WWTP
o Major Components/Systems
■ Main Control PLC panel consisting on GE PACSystems Rx3i PLC
platform with local I/O expansion
■ PLC integration to communicate to new centrifuge PLCs over Ethernet
messaging for handshaking and controls
■ Various instrumentation including magnetic flowmeters, ultrasonic
level transmitters, pressure gauges, pressure switches and pressure
diaphragm seals
o SCADA integration utilizing Owner's existing GE Cimplicity Redundant
SCADA Servers
FLORIDA
DESIGN
CONTRACTORS
Attachment F Chemical Tank Manufacturer
Please excuse our error, Polyprocessing should have been selected on the Bid
Form.
Kimley>»Horn
Village of Tequesta Water Treatment Plant Upgrades
Reference Check and Project Verification
Powerline of South Florida, Inc.
Electrical Sub -consultant
Project Reference: City of Boca Raton
Membrane Concentrate Line Re-route
Reference Contact: Steve Chamness, Hillers Electrical Engineers
1. When was the project completed?
September 2014 is accurate
2. Project Cost?
Fees indicated are accurate
3. How many change orders on this project?
There were no major change orders, worked very well with this sub and he
didn't try to jump on change orders at all.
4. Was it completed on time?
Yes
5. Rate overall performance? 0 — 10
6. Would you work with them again?
Yes
Kimley>»Horn
Project Reference: City of Sunrise
Sawgrass WTP Effluent Injection Pump Station
Reference Contact: Steve Chamness, Hillers Electrical Engineers
1. When was the project completed?
Page 2
The fees indicated seemed to be accurate by memory, as Mr. Chamness was
unable to find the project number to verify.
2. Project Cost?
The fees indicated seemed to be accurate by memory, as Mr. Chamness was
unable to find the project number to verify.
3. How many change orders on this project?
There were change orders due to GC ripping out conduits that should not have
been; however, those were to the GC not the Hillers and were justified.
4. Was it completed on time?
There were issues causing delay due to inspectors wanting UL labels on
manholes but no delays were caused by this sub -consultant.
5. Rate overall performance? 0 — 10
6. Would you work with them again?
Yes
Kimley>»Horn
Project Reference: Palm Beach County
SCWRF Effluent Pump Upgrades
Reference Contact: Steve Chamness, Hillers Electrical Engineers
1. When was the project completed?
Page 3
The fees indicated seemed to be accurate by memory, as Mr. Chamness was
unable to find the project number to verify.
2. Project Cost?
The fees indicated seemed to be accurate by memory, as Mr. Chamness was
unable to find the project number to verify.
3. How many change orders on this project?
Mr. Chamness was unable to recall any change orders and reiterated that his
experience working with Tom who he has known for a long time, his that he is
really good about working stuff around and not charging additional change
orders unless it was due to him.
4. Was it completed on time?
Mr. Chamness was unable to recall issues related to the project completion
timeline.
5. Rate overall performance? 0 — 10
/R:
6. Would you work with them again?
Yes
Kimley»>Horn
Project Reference: Palm Beach County Water Utilities Dept
WTP #2 Wellfield Upgrades
Reference Contact: Rick Olsen, Globaltech
1. When was the project completed?
Timeframe is accurate, completed early 2014
2. Project Cost?
Page 4
$249,900 in according to Agreement with this sub. Mr. Olsen stated he felt that
the difference may be equipment purchase because Globaltech ended up
purchasing equipment. Although he couldn't remember specific details, he
stated it was nothing wrong on the part of the sub. The fees provided by the
sub is not correct but it was a probably O.D.P.
3. How many change orders on this project?
There were change orders but not due to issues with the sub. The County
asked that all electrical motors and panels be above 100 year flood elevation
so it was there were some delays and change orders due to that but nothing
due to Powerline's performance
4. Was it completed on time?
Yes, very close and no delays were due to the sub.
5. Rate overall performance? 0 — 10
Solid 8+
6. Would you work with them again?
Absolutely
Kimley»>Horn
Project Reference: Indian River County
Indian River South RO Improvements
Reference Contact: Mark Miller, Kimley-Horn and Associates Inc.
1. When was the project completed?
August 2009 (one year before date provided by sub)
2. Project Cost?
$ 894,000 (sub provided $275,250)
3. How many change orders on this project?
One for $75,000
4. Was it completed on time?
Yes, but there were delays
5. Rate overall performance? 0 — 10
9-10
6. Would you work with them again?
Page 5
Yes, we have worked with them recently. They are conscientious, deliberate
and methodical. Powerline knows their practice.
WTP VOT Upgrades (Kimley-Horn)
General comments:
(1) Acid pumps need to be replaced — this should be a priority item, not an additive bid item. Need
4 pumps installed, not 3 pumps.
(2) Filter Plant filter media needs removal and replacement (see K -H memo stating such on
26JAN2018) for all 6 filters. This should be part of this project.
(3) John & the operators do not want to lose GENSET 1 (small diesel). It has 1,900 hours of run-time
and easily go to 5-6,000 hours with proper maintenance — this would give us a proven backup to
maintain system pressure should GENSET II fail on us. GENSET 1 could remain on it's foundation
and be isolated via a soundproof partition from the adjacent Motor Control Center (MCC) &
Switch -Gear (SG). A small foundation could be built for a new MCC&SG for the new Variable
Frequency Drives in concert with the removal of the existing MC&SG C by leaving two existing
power feeds in service while installing the new MCC&SG. The split -system air conditioning
system would need to be relocated.
(4) Need an analysis on replacement of membranes for RO Trains 1 and 3 in two years. RO Train 2
needs membranes replaced this calendar year.
(5) Clean de-gassifiers 1 & 2.