HomeMy WebLinkAboutResolution_04-03/04_10/06/2003• RESOLUTION N0.4-03/04
A RESOLUTION OF THE VILLAGE COUNCIL OF THE
,~ VILLAGE OF TEQUESTA, PALM BEACH COUNTY,
FLORIDA, AMENDING THE CONTRACT WITH CABLE
>> CONSTRUCTORS, INC., OF HAINES CITY, FLORIDA, WITH
s AN EXISTING CONTRACT PRICE IN THE AMOUNT OF
$111,514.38, TO ADD $39,575.00 FOR THE U.S. HIGHWAY 1
CROSSING, AUTHORIZING THE VILLAGE MANAGER TO
~ EXECUTE THE APPLICABLE CONTRACT ON BEHALF OF
THE VILLAGE, AND APPROPRIATING ADDITIONAL
FUNDS AND BUDGETING SUCH FUNDS IN FISCAL YEAR
2004 IN THE WATER UTILITY FUND #401 FOR SUCH
PURPOSE.
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE
COUNCIL OF THE VILLAGE OF TEQUESTA, PALM BEACH COUNTY,
FLORIDA, AS FOLLOWS:
Section 1: Amendment of the contract with Cable Constructors, Inc., of Haines City,
Florida, in the existing amount of $111,514.38 to add $39,575.00 for the U.S.
Highway 1 crossing, which is hereby approved and the Village Manager of the
Village of Tequesta is authorized to execute the same on behalf of the Village.
Authorizing Additional funds to be appropriated and budgeted in the fiscal year 2004
in the Water Utility Fund #401 for such purpose. The change order is attached as
Exhibit "A" and incorporated as part of this resolution.
THE FOREGOING RESOLUTION WAS OFFERED by Council Member
Genco, who moved its adoption. The motion was seconded by Council Member
Watkins, and upon being put to a vote, the vote was as follows:
FOR ADOPTION AGAINST ADOPTION
Edward D. Resnik
Russell J. von Frank
Joseph N. Capretta
Geraldine A. Genco
Pat Watkins
•
n
u
The Mayor thereupon declared this Resolution duly passed and adopted this
6t" day of October, A.D., 2003.
,~ 3 A
Mayor Edward D. Resnik
ATTEST:
,,
:~ 2~c z
Actin Village Clerk
•
U
t
CHANGE ORDER
•
•
No. 2
~~
PROJECT: PINE TREE DRIVE IMPROVEMENTS
DATE OF ISSUANCE: AUGUST 7, 2003 EFFECTIVE DATE: UPON OWNER APPROVAL
OWNER: VILLAGE OF TEQUESTA
OWNER's Contract No.: N/A
CONTRACTOR: CABLE CONSTRUCTORS, INC. (CCI) ENGINEER: REESE, MACON & ASSOCIATES, INC.
You are directed to make the following changes in the Contract Documents.
Description: 12" HDPE directional bore of US 1 and associated tie-ins.
Reason for Change Order: Establish ur;it cosis for this addition.
Attachments: (List documents supporting change) Contractor Unit Price Schedule.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: 75 Days (Aug. 25, 2003)
$61,941.38 Ready for final payment: 100 Days (Sept. 22, 2003)
days or dates
Net changes from previous Change Orders No. 1 to No. = Net change from previous Change Orders No. 1 to No.
$ 49 573.00 10 Da s
Contract Price prior to this Change Order Contract Times prior to this Change Order
$111,514.38 Substantial Completion: 85 Days (Sept. 5, 2003)
Ready for final payment: 110 Days (Oct. 2, 2003)
days or dates
Net Increase of this Change Order Net Increase of this Change Order
$39 575.00 10 Da s
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
$151,089.38 Substantial Completion: 95 Days (Sept. 15, 2003)
Ready for final payment: 120 Days (Oct. 10, 2003)
da s or dates
RECOMMENDED:
REESE, MACON & ASSOCIATES
By:
Engineer (Authori ed Signa re)
THOMAS C.
• 8_ 8-03
Date
APPROVED:
VILLAGE OF TEQUESTA
By. _ ~
Owner (Authorized igna •e
MICHAEL COUZZO, VILL E MANAGER
Date: Y~'
ACCEPTED:
CCI
By: ./,
ontractor (Authorized Signature)
~~6~~ fi2~1~'riz~ SST.
Date: ~ ~~'~~
G:\E\WP60\Change Orders\C02 03-106 Pine Tree Dr.wpd
r -+~
CCI SITE DEVELOPMENT
• PROPOSAL FORM
VILLAGE OF TEQUESTA
US 1 WM CROSSING
~,
ITEM
--------------- QUANTITY
-------- U.M.
---- UNIT PRICE
-------- COST
-------
Mobilization 1 LS $8,000.00 $8,000.00
12" HDPE 20 LF $45.00 $900.00
12" x 10" ,Reducer 2 EA $400.00 $800.00
12" 90 degree Bend 4 EA $425.00 $1,700.00
HDPE Inserts 4 EA $75.00 $300.00
DIP Vertical 20 LF $30.00 $600.00
10" Gate Valve 1 EA $1,370.00 $1,370.00
10" Spool Piece 1 EA $400.00 $400.00
•
"
10
90 Degree Bend 1 EA $380.00 $380.00
10" Tap Slv. & Vlv. 1 EA $4,000.00 $4,000.00
ARV 1 EA $4,000.00 $4,000.00
12" D-Bore HDPE 220 LF $65.00 $14,300.00
Sample Points 2 EA $400.00 $800.00
Sod 175 SY $3.00 $525.00
Sidewalk 30 SY $30.00 $900.00
GroutPipe 3 CY $200.00 $600.00
TOTAL $39,575.00
* Includes any dewatering equipment, if required.
•