HomeMy WebLinkAboutResolution_79-99/00_08/10/2000•
RESOLUTION NO. 79-99/00
A RESOLUTION OF THE VILLAGE COUNCIL OF
THE VILLAGE OF TEQUESTA, .PALM BEACH
COUNTY, FLORIDA, AWARDING A CHANGE ORDER
FOR COUNTRY CLUB DRIVE STREET LIGHT
CONDUIT INSTALLATION TO RIC-MAN
INTERNATIONAL, INC., OF POMPANO BEACH,
FLORIDA, IN THE AMOUNT OF $64,693.50,
SUBJECT TO FUNDS BEING APPROPRIATED IN
FY 2001 BUDGET, HAVING A TOTAL PROPOSED
FY 2001 BUDGET ALLOCATION OF $81,076 AND
AUTHORIZING THE ACTING VILLAGE MANAGER
TO EXECUTE THE CONTRACTUAL CHANGE ORDER
ON BEHALF OF THE VILLAGE.
L~
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF TEQUESTA, PALM BEACH COUNTY,
FLORIDA, AS FOLLOWS:
Section 1. A Contractual Change Order with Ric-Man
International, Inc., of Pompano Beach, Florida, for
Country Club Drive Street Light Conduit Installation,
in the amount of $64,693.50, attached hereto as
Exhibit "A" and incorporated by reference as part of
this Resolution, is hereby approved subject to funds
being appropriated for such in FY 2001, and the Acting
Village Manager is authorized to execute the
applicable contractual change order on behalf of the
Village of Tequesta.
THE FOREGOING RESOLUTION WAS OFFERED
Schauer who moved its
motion was
Walker ,
vote was as follows:
seconded by
and upon being pu
by Councilmember
adoption. The
Councilmember
t to a vote, the
•
FOR ADOPTION AGAINST ADOPTION
•
•
Joseph N. Capretta
Elizabeth A. Schauer
Bas~.l E. Dalack
Sharon D. j~Jalker
The Mayor thereupon declared the Resolution duly
passed and adopted this 10th day of August, A.D, 2000.
MAYOR OF TEQUESTA
ATTEST:
oann Mangani llo
Village Clerk
Resolution.CountryClubStreetLightRicMan(3)
'j L .•
,';~ ~seph N. Capr to
~1
1
- Exhibit "A"
CHANGE ORDER 99-161.1
No. 4
• PROJECT: Teguesta Country Club/Bermuda Terrace: Water Main Replacement & Drainage System Improvements -Phase I
DATE OF ISSUANCE: July 5, 2000 EFFECTIVE DATE: Upon Village Approval
OWNER: Village of Tepuesta
OWNER's Contract No. N/A ~-. - _~
CONTRACTOR: Ric Man International .Inc. ENGINEER: Reese, Macon and Associates,~Ina.
You are directed to make the following changes in the Contract Documents. , , „ ~ ~ 201
Description: Identify unit costs for items not in original contract. ~
I
Reason for Change Order: Installation of conduiUnull boxes for street lights; Country Club Drive. j VIL!_AuF. OF TEOUES?A
r~,.,,,,,r r,=^T.
Attachments: (list documents supporting change) Unit Cost breakdown as supplied by Ric Man Internatic>ri~h_Iu~~._,____'._.: ~.._..
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIIvIES:
Original Contract Price Original Contract Times
Substantial Completion: 240 days
$ 2,069,000.00 _ Ready for final payment: 270 days _
days or dates
Net changes from previous Change Orders No. 1 to No. 3 Net change from previous Change Orders No.l to No. 3
• $ 201,656.15 (Pending) 45
days
Contract Price prior to this Change Order Contract Times prior to this Change, Order
$ 2,270,656.15 (Pending C.O. #1/2 &3 Approval)
Net Increase (decrease) of this Change Order
$ 64,693.50
Contract Price with all approved Change Orders
$ 2,335,349.65
Thomas C. Jensen, P.E.
RECOMME/LADED:
By: `
Date : 7 ~ 7i ~ - as
Reese, Macon & Associates, Inc.
• tcjchordteg4/99-161.1
Substantial Completion: 285 Days
Ready for final payment: 315 Davs
days or dates
Net Increase(decrease) of this Change Order
20 Days
days
Contract Times with all approved Change Orders
Substantial Completion: 305 Days
Ready for final payment: 335 Days
days or dates
M 1-C h a e l R. C o u z z 0, J T. Rene Castillo ecre
APPROVED: Village Manager ACCEPT
` By: ,U
Owner (Author' a Si atu ) Contracto ized Signature)
Date: !~ j'' ~„ ~ y..~.,,, p ' Date: 7 ~~ dv
Village of equesta Ric Man International, Inc.
`I ~1 ~~ ~..
.~ ~~ -
CHANGE ORDER No.4
• Tequesta Country ClubBermuda Terrace
Water Main Replacement & Drainage system Improvements
Phase I
VILLAGE OF TEQUESTA
TEQUESTA COUNTRY CLUBBERMUDA TERRACE
WATER MAIN REPLACEMENT AND
DRAINAGE SYSTEM IMPROVEMENTS
UNIT PRICE BID SCHEDULE W/
RIC MAN'S UNIT COSTS
I. STREET LIGHT CONDUIT
A. COUNTRY CLUB DRIVE
1. PVC C~nduit*
a. 2" 4,300 LF $ 5.50 $23,650.00
2. Pull Boxes* 77 Ea. $ 80.50 $ 6,198.50
3. Directional Bore (HDPE/PVC)
a. Country Club Drive
(60 LF Ea.) 18 Ea. $661.25 $11,902.50
4. Crossings (Tunneling)
a. Roadway (40 LF Ea.) 3 Ea. $460.00 $ 1,380.00
b. Driveway (15 LF Ea.) 60 Ea. $287.50 $17,250.00
4. Sod 750 SY $ 5.75 $ 4,312.50
TOTAL $64,693.50
•
* Installation only, material supplied by FPL.
tcjchgordteg4/99-161.1