Loading...
HomeMy WebLinkAboutAgreement_General_7/9/2020_Johnson Davis, Inc.PROJECT WORK AUTHORIZATION NO.1 WITH JOHNSON-DAVIS FOR PIPELINE CONSTRUCTION PROJECTS THIS PROJECT WORK AUTHORIZATION NO. 1 is entered into and effective this I day of A tU A40 , by and between the VILLAGE OF TEQUESTA, a Florida municipal corporation with offices located at 345 Tequesta Drive, Tequesta, Florida 33469-0273, organized and existing in accordance with the laws of the State of Florida, hereinafter the "Village"; and JOHNSON-DAVIS, INC., a Florida corporation with offices located at 604 Hillbrath Drive, Lantana, Florida 33462, hereinafter the "Contractor" and collectively with the Village, the "Parties". 1.0 Authorization This Project Work Authorization is issued pursuant to the Agreement for Pipeline Continuing Construction services between the Village and the Contractor, dated June 11, 2020, hereinafter the "Agreement". If there are any conflicts between the terms and conditions of this Project Work Authorization and the Agreement, the terms and conditions of the Agreement shall prevail. 2.0 Project Description: The Utilities Department has identified a need to replace approximately 3,300 linear feet of asbestos cement water main on South Beach Road. 3.0 Scope of Services Under this Project Work Authorization, the Contractor will provide the construction services to the Village as detailed in the Drawings and Technical Specifications prepared by Kimley-Horn & Associates incorporated herein as Exhibit "A". 4.0 Schedule The services to be provided under this Project Work Authorization shall be Substantially Complete within one hundred and fifty (150) calendar days and Finally Complete within one hundred and eighty (180) calendar days from the Village's issuance of a Notice to Proceed. 5.0 Liquidated Damages Contractor shall pay the Village $250 for each day that expires after the time (as duly adjusted pursuant to the Agreement) specified in the Schedule above for Substantial Completion or Final Completion until the Work is substantially complete or finally complete respectively. 6.0 Compensation In consideration for the above Scope of Services and within the Agreement, pricing shall be pursuant to the Agreement. In consideration for the above Scope of Services and pursuant to Exhibit `B", the Village shall pay the Contractor a total amount not to exceed four hundred nineteen thousand, one hundred eighty-one dollars and forty-three cents ($419,181.43). IN WITNESS WHEREOF, the parties hereto have executed this Agreement on the date and year first above written. ATTEST: �ka��Ae__ Lori McWilliams, MMC Village Clerk N-DAVIS, INC. By: Robert A Hop ; Vice President (Corporate Seal) VI4y:A E OF TEQUESTA --PIZ Brenan, ayor Q '6?-po '?. eal) SEAL D= INCORPORATED: Ex. A SECTION 01010 SUMMARY OF WORK PARTI - GENERAL 1.01 WORK COVERED BY THESE CONTRACT DOCUMENTS The Contractor shall furnish all labor and materials necessary to perform the water main replacement as shown on the plans in Tequesta, Florida. The project shall include all piping, fittings, couplings, accessories and appurtenances, site restoration, temporary provisions to maintain water service to residents to the extent practical, testing, bacteriological clearance of the water main, pressure testing of the water main, water service connection, removal and/or grout filling of the existing piping as specified, obtaining all required permits, compliance with permit conditions, Village of Tequesta (Village) Water Utility Standards and Palm Beach County (PBC) Standards, and any other items depicted on the drawings and described in these documents and reference materials. In addition to infrastructure improvements, this project shall include roadway, swale and shoulder restoration located in the public right-of-way including pavement, signage, driveways, fencing, landscaping and other miscellaneous items. These items shall be restored as shown on the construction drawings but at a minimum they should be restored to their original condition or better. Contractor's Duties- 1. Except as specifically noted, provide and pay for- a. Mobilization and demobilization b. Labor, materials, and equipment C. Tools, construction equipment, and fuel d. Water and utilities required for construction e. Temporary utilities, provisions, and controls f. Freight and sales tax g. Maintenance of traffic h. Surveying and field engineering i. Locating and protecting existing utilities j. Compliance with all of the conditions of the permits issued and required to be obtained by the Contractor for this project k. Coordination of schedule with all property owners effected by the water main installation and service relocation 1.02 CONTRACTS A. Construct the Work under a Unit Price contract. 01010-1 B. Subcontractors (when used) shall be supervised by and work directly for the contractor. 1.03 WORK BY OTHERS AND FUTURE WORK A. The Owner reserves the right to add to the work in accordance with the Contract Documents. 1.04 WORK SEQUENCE A. Sequence of work will be discussed and decided at the Pre-Work Conference. B. To the greatest extent practical, the new water main areas will need to be placed into service prior to the existing water main being abandoned and all customers shall be served during the duration of construction with minimum disruption. Where this is not feasible, the contractor shall employ temporary connections as needed. C. Work shall only be performed during the authorized construction hours and days as specified by the Village of Tequesta. If work needs to be performed outside of the authorized hours and/or days to allow the work to progress, special permission from the Village shall be requested by the Contractor a minimum of 14 days before this work is to begin. D. The Contractor shall coordinate closely with the Village of Tequesta for an optimal construction schedule that minimizes disruption to service and normal traffic flow. Evening and weekend work hours may be required and shall be coordinated with the Village of Tequesta prior to commencement. 1.05 CONTRACTOR-FURNISHED PRODUCTS AND RESPONSIBILITIES A. Products furnished to the site and paid for by the Contractor- 1. All products necessary to complete the work described herein these contract documents and specifications. B. Contractor's Responsibilities- 1. Review and incorporate Owner-reviewed shop drawings, product data, and samples into the construction of the project. 2. Prepare, apply for, and obtain permits that are specified to be obtained by the Contractor. 3. Provide for the notification of residents for work on private property, including door hangers, individual meetings, public meetings, etc. 4. Receive and unload products at site; inspect for completeness or damage jointly with Owner. 01010-2 5. Repair or replace items damaged after receipt. 6. Arrange and pay for product delivery to site. 7. Handle, store, install, and delivered products. 8. Submit claims for transportation damage and replace damaged, defective, or deficient items. 9. Arrange for manufacturers' warranties, inspections, and service. 1.06 CONTRACTOR'S USE OF THE PREMISES A. All work shall be within the limits of the County right-of-way (ROW) and easements to the greatest extent practical. The Contractor shall be responsible for maintenance of traffic when working within the public ROW. This project will require close coordination between the Village, County and the Contractor during construction. B. The Contractor shall be fully responsible for the safety and security of the construction area including any temporary measures required to maintain its protection. The Contractor will be responsible for any damages or theft incurred to his tools, equipment, machinery, and new work in-place not yet fully accepted by the Owner. C. The Contractor shall be responsible for maintenance of traffic when working within the public ROW. D. The Contractor shall maintain vehicular and pedestrian access to driveway entrances to the greatest extent practical. A minimum of one traffic lane should remain open to the greatest extent practical. 1.07 PERMITS REQUIRED A. The Contractor will be responsible for complying with all conditions specified in each of the project's permits and licenses. A description of the project permits is described in Specification 01060. PART 2 — PRODUCTS NOT USED. PART 3 — EXECUTION NOT USED. END OF SECTION 01010-3 This page intentionally left blank. 01010-4 SECTION 01020 MAINTENANCE AND PROTECTION OF PROPERTIES PART 1 - GENERAL 1.01 MAINTENANCE OF AREA UNDER CONSTRUCTION A. The Contractor should use the following as a guideline to plan and control the areas under construction. 1. No trench shall remain open at the end of each workday. 2. Restrict the length of open excavation (down to pipe zone) to a maximum of 100-LF. 3. Contractor shall be responsible to restore local traffic access at end of each workday whenever possible & reasonable. 4. Contractor shall coordinate with the Owner to ensure detour routes will be clear. 5. Contractor shall provide bridging or temporary backfill of an open trench within a reasonable time period when requested to allow access to residential and commercial driveways throughout the duration of work. 6. All driveways shall be open and accessible each night at the end of work, unless approved otherwise by the Village. B. All closed trenches should receive a temporary rock surface in order to accommodate local vehicular and pedestrian traffic each night. Temporary surface shall be a minimum of four inches road base material, compacted, graded and maintained by the Contractor. C. The Contractor shall perform his construction activities within the following time periods: Within 3 days after acceptance of the trench backfill, the base shall be restored including priming and/or sealing and shall be open for traffic. The asphalt wearing surface shall be replaced no later than 2 weeks after completion of the base course with complete surface restoration within the ROW including grassing, sodding and all concrete work within 4 weeks after completion of restoration of the base course. Any restoration or repair work required to be completed on private property must be completed within either 48 hours of completion of work or in the case of repair to construction damage, following notification for the need for such repair. 1.02 PROTECTION OF EXISTING AND ADJACENT PROPERTIES 01020-1 A. All shrubbery, paved streets and walks, driveways, fences and walls, adjacent structures and equipment shall be fully protected against damage during each stage of the project. Any damage by the Contractor shall be fully restored to original condition unless indicated otherwise on the drawings or by the Owner. B. The use of heavy vibratory rollers in compacting the fill has the potential to cause some movement of any nearby structures founded on shallow mats/footings. For these reasons, the use of heavy vibratory drum rollers is not recommended in residential and commercial areas. Trench backfill should be compacted using walk behind vibratory equipment. As part of the pre-construction activities, the Contractor is required to perform a condition survey of buildings adjacent to the roadways as a basis for establishing preconstruction building assessments for defense or verification of construction damage claims. It may be necessary for the Contractor to provide a vibration monitoring plan as part of his construction activities. C. Contractor shall protect all property that may be affected by his work or operations. The location and extent of underground and covered facilities are not guaranteed, and the Contractor is cautioned to proceed with care in order to prevent the undermining or damage to existing structures, piping, or facilities. D. In the event any of the Contractor's activities were to disrupt or endanger any facilities, he shall at his own expense make all necessary repairs or replacements necessary to correct the situation to the satisfaction of the Engineer. Such work shall progress continuously to completion on a 24-hour per day, seven workday basis. The Contractor shall be responsible for the services of repair crews on call 24 hours per day for emergencies that arise involving work under this Contract. 1.03 SITE CONDITIONS A. Site Investigation and Representation 1. The Contractor acknowledges satisfaction as to the general nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, availability of labor, water, electric power, roads, and uncertainties of weather, or similar physical conditions, the character of equipment and facilities needed preliminary to and during the prosecution of the work, and all other matters which can in any way affect the work or the cost thereof under this contract. 2. Failure by the Contractor to become acquainted with the physical conditions and all the available information will not relieve the 01020-2 Contractor from responsibility for properly estimating the difficulty or cost of successfully performing the work. 3. The Contractor warrants that as a result of examination and investigation of all the aforesaid data, the Contractor can perform the work in a good and workmanlike manner and to the satisfaction of the Owner. The Owner assumes no responsibility for any representations made by any of its officers or agents during or prior to the execution of this Contract, unless (1) such representations are expressly stated in the Contract, and (2) the Contract expressly provides that the responsibility therefore is assumed by the Owner. B. Information on Site Conditions 1. Subsurface Investigations a. The Contractor shall be responsible for having determined to his satisfaction, prior to the submission of his bid, the nature and location of the work, the conformation of the ground, the character and quality of the substrata, the types and quantity of materials to be encountered, the nature of the groundwater condition, the character of equipment and facilities required preliminary to and during the performance of the work, the general and local conditions and all other matters which can in any way affect the work under this Contract. The prices established for the work to be done shall reflect all costs pertaining to the work. Any claims for extras based on the substrata or ground water table conditions will be disallowed. b. The Contractor further acknowledges that he assumes all risk contingent upon the nature of the subsurface conditions actually encountered by him in performing the work covered by the Contract, even though such actual conditions may result in the Contractor performing more or less work than he originally anticipated. 1.04 PROTECTION OF EXISTING UTILITIES A. Contractor's Responsibility for Utility Properties and Service 1. Where the Contractor's operations could cause damage or inconvenience to telephone, television, power, water, or sewer systems, the operations shall be suspended until all arrangements necessary for the protection of these utilities and services have been made by the Contractor with the owner of the utility affected. 2. Notify all utility offices which are affected by the construction operation at least 48 hours in advance. Under no circumstances 01020-3 should any utility be exposed without first obtaining permission from the appropriate agency. Once permission has been granted, locate, expose, and provide temporary support for all existing underground utilities. 3. The Contractor shall be solely and directly responsible to the Owner and operators of such properties for any damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of any injuries or damage which may result from the construction operations under this Contract. 4. Neither the Owner nor its officers or agents shall be responsible to the Contractor for damages as a result of the Contractor's failure to protect utilities encountered in the work. 5. In the event of interruption to domestic water, sewer, storm drain, or other utility services as a result of accidental breakage due to construction operations, promptly notify the proper authority. Cooperate with said authority in restoration of service as promptly as possible and bear all costs of repair. In no case shall interruption of any water or utility service be allowed to exist outside working hours unless prior approval is granted. 6. The Contractor will take steps to collect and dispose of all sewage that leaks and/or spills during the performance of this contract. Any leakage or spillage will be cleaned up to the satisfaction of the Department of Environmental Protection. 7. In the event the Contractor encounters sanitary service or water service lines that interfere with trenching, he may, by obtaining prior approval of the property owner, Owner or Fire Department as applicable, and the Engineer, cut the service, dig through, and restore the service with similar and equal materials at the Contractor's expense. 8. The Contractor shall replace in kind, at his own expense, all existing utilities or structures removed or damaged during construction, unless otherwise provided for in these Contract documents or ordered by the Engineer. This includes any irrigation systems along the corridor. B. Interfering Structures 1. Take necessary precautions to prevent damage to existing structures whether on the surface, aboveground, or underground. 2. Protect underground and aboveground existing structures from damage, whether or not they lie within the limits of the easements obtained by the Owner. Where such existing fences, gates, driveways, sheds, buildings, or any other structure must be removed in order to properly carry out the construction, or are damaged during construction, restore to their original condition to the satisfaction of the Village and the property owner involved at the Contractor's own 01020-4 expense. Notify the Engineer of any damaged underground structure and make repairs or replacements before backfilling. 3. Without additional compensation, the Contractor may remove and replace in a condition as good as or better than original, such small miscellaneous structures as fences, mailboxes, and signposts that interfere with the Contractor's operations. C. Field Relocation 1. During the progress of construction, it is expected that minor relocations of the work will be necessary. Such relocations shall be made only by direction of the Engineer. If existing structures are encountered which prevent the construction, and which are not properly shown on any Contract Drawings, notify the Engineer before continuing with the construction in order that the Engineer may make such field revisions as necessary to avoid conflict with the existing structures. If the Contractor shall fail to do so, notify the Engineer and proceeds with the construction despite this interference when an existing structure is encountered, he shall do so at his own risk. 1.05 PRESERVATION, RESTORATION, AND CLEANUP A. Site Restoration and Cleanup 1. At all times during the work, keep the premises clean and orderly, and upon completion of the work, repair all damage caused by equipment and leave the project free of rubbish or excess materials of any kind. 2. Stockpile excavated materials in a manner that will cause the least damage to adjacent lawns, grassed areas, gardens, shrubbery, or fences, regardless of whether these are on private property, or on state, county, or the Village rights-of-way. Remove all excavated materials from grassed and planted areas and leave these surfaces in a condition equivalent to their original condition. 3. All existing drainage ditches and culverts shall be reopened and graded, and natural drainage restored. Restore culverts broken or damaged to their original condition and location. 4. Upon completion of pipe laying and backfilling operations, clean all former grassed and planted areas, leaving all disturbed areas free from rocks, gravel, clay, or any other foreign material. The finished surface shall conform to the original surface and shall be free- draining and free from holes, ruts, rough spots, or other surface features detrimental to a seeded area. B. Finishing of Site, Borrow, and Storage Areas 01020-5 1. Upon completion of the project, all areas used by the Contractor shall be properly cleared of all temporary structures, rubbish, and waste materials and properly graded to drain and blend in with the abutting property. Areas used for the deposit of waste materials shall be finished to properly drain and blend with the surrounding terrain. C. Street Cleanup During Construction 1. Thoroughly clean all spilled dirt, gravel, or other foreign material caused by the construction operations from all streets and roads at the conclusion of each day's operation to the satisfaction of the Owner. Sidewalks, unless under construction, shall be kept clear of material, and available for pedestrian use at all times. D. Dust Prevention 1. Give all unpaved streets, roads, detours, haul roads or disturbed areas used in the construction area an approved dust-preventive treatment or periodically water to prevent dust. Applicable environmental regulations for dust prevention shall be strictly enforced. E. Preservation of Irrigation and Drainage Ditches 1. After backfilling of the trenches, restore all irrigation and storm drain ditches destroyed, damaged, or otherwise modified during construction to a condition equivalent, in the opinion of the Engineer, to the condition of the ditch before construction. Ditches so reconstructed shall be built in their original locations. END OF SECTION 01020-6 SECTION 01030 HURRICANE PREPAREDNESS PART 1 - GENERAL 1.01 HURRICANE PREPAREDNESS PLAN A. The Contractor's attention is drawn to the possibility of hurricane or severe storm conditions occurring at the site of work during the course of Contract Work. B. Within fourteen (14) days of the date of the Notice to Proceed, the Contractor shall submit to the Engineer and Owner a Hurricane Preparedness Plan. The plan should outline the necessary measures which the Contractor proposes to perform at no additional cost to the Owner in case of a hurricane or severe weather warning. C. In the event of inclement weather, or whenever the Owner shall direct, the Contractor shall, and will, cause Subcontractors to carefully protect the Work and materials against damage or injury. Work and materials damaged due to inclement weather shall be removed and replaced at the expense of the Contractor. 1. Hurricane Watch: Upon designation of a hurricane watch, the Contractor shall be responsible for storing all loose supplies and equipment on the job site that may pose a danger. In addition, the Contractor shall remove all bulkheads and plugs in pipelines that would impede drainage in the event of flooding. Structures that may be in danger of floatation shall be flooded. The Contractor shall also cooperate with the Owner in protecting any other structures at the site. 2. Hurricane Warning: No mobile "temporary facility" under the control of or on the property of the Owner shall be staffed during a hurricane warning. Contractor facilities meeting these criteria shall be evacuated. Reasonable steps shall be taken to protect all such facilities and their contents from damage and to avoid the facility causing damage to the surroundings. Reasonable steps shall be taken to protect existing improvements from damage and to avoid damage to the surroundings caused by staged materials, equipment, or other facilities related to the project. D. The Contractor may be required to backfill excavation depending on the severity of the approaching storm or the expected amount of rainfall. Additionally, erosion protection and inlet protection may also be required 01030-1 by the Owner depending on the site conditions at the time of the Hurricane Watch. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01030-2 SECTION 01050 FIELD ENGINEERING AND SURVEYING PART 1 - GENERAL 1.01 DESCRIPTION A. The Contractor shall provide and pay for field engineering and surveying services required for the project. B. The Owner's representative will identify existing control points, as required. 1.02 RELATED REQUIREMENTS SPECIFIED ELSEWHERE: A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Section 01010 - Summary of Work C. Section 01300 — Submittals and Progress Schedules D. Section 01720 - Project Record Drawings 1.03 QUALIFICATIONS OF SURVEYOR A. Professional Land Surveyor (PLS) registered in the State of Florida. 1.04 SURVEY REFERENCE POINTS A. Existing horizontal and vertical control points for the project are those designated on the drawings. B. The Contractor shall locate and protect survey control and reference points. The Contractor shall provide additional benchmarks as required to construct the project. C. Control datum for survey is that indicated on Drawings. D. Protect survey control points prior to starting site work; preserve permanent reference points during construction. E. Promptly report the loss or destruction of any reference point or relocation required because of changes in grades or other reasons to the Engineer. 01050-1 F. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Engineer. 1.05 PROJECT SURVEY REQUIREMENTS A. Establish lines, grades, and elevations by instrumentation or similar appropriate means utilizing recognized engineering survey practices. B. Horizontal alignment for the proposed construction will be controlled by property lines, easement boundaries, and existing structures. The Contractor shall be responsible to establish reference lines and necessary offsets to establish piping alignment, and equipment and structure location. C. Vertical alignment for the proposed construction will be based on the existing grades and benchmarks identified on the drawings. The Contractor shall be responsible to establish proposed grades. The grade stakes shall be provided by the Contractor. D. Establish a minimum of two permanent bench marks on site, referenced to established control points per project area. Record locations, with horizontal and vertical data, on project record documents. E. Periodically verify layouts by same means. F. Prior to destruction of existing improvements, record existing grades to be used in reconstruction to assure proper flow of surface water runoff is maintained after restoration. 1.06 RECORDS A. Maintain a complete, accurate log of all control and survey work as it progresses. B. Upon completion of the project, prepare record drawings in accordance with related specification section. 1.07 SUBMITTALS A. Submit name and address of Surveyor/Engineer to Owner. B. On request, submit copies of field notes and documentation verifying the accuracy of the survey work. 01050-2 1.08 EXAMINATION A. The Contractor is responsible for verifying survey control points prior to initiation of work. B. The Contractor shall promptly notify Engineer of any discrepancies discovered. 1.09 QUALITY CONTROL A. Quality control of the Work shall be the Contractor's responsibility and Contractor shall make every effort to produce the best quality work, as specified on the drawings and specifications. B. Forty-eight (48) hour notification to the Engineer by the Contractor shall be required for all specified field investigations unless otherwise noted. PART 2 — PRODUCTS NOT USED. PART 3 — EXECUTION NOT USED. END OF SECTION 01050-3 This page intentionally left blank. 01050-4 SECTION 01060 REGULATORY REQUIREMENTS AND NOTIFICATIONS PART 1 - GENERAL 1.01 GENERAL REQUIREMENTS A. Obtain and pay for all permits and licenses as required for construction of the project. B. Schedule all inspections and obtain all written approvals of the agencies required by the permits and licenses. C. Comply with all conditions specified in each of the permits and licenses. D. The Contractor shall keep a copy of all permits and easements complete with conditions, attachments, exhibits, and modifications at the work site and provide copies of the permits to the appropriate subcontractors. The Contractor is responsible for ensuring that the permit conditions are explained to the appropriate construction personnel. 1.02 PERMITS OBTAINED BY OWNER The Owner will apply and pay for the following permits- 1. PALM BEACH COUNTY HEALTH DEPARTMENT: The General Permit for Construction of a Water Main Extension for PWSs from the Palm Beach County Health Department for the project has been obtained for this project by the Owner. A copy of this permit has been included in Appendix A. The contracts shall conform to the conditions of this permit as part of this contract. 1.03 PERMITS OBTAINED BY CONTRACTOR A. Contractor shall prepare, submit and obtain the appropriate right of way permit(s) from Palm Beach County Public Works Department. A copy of the application has been included in Appendix B. The Contractor shall conform to the conditions of this permit as part of this contract. B. The Contractor shall prepare and pay for the Notice of Intent (NOI) to use the Generic Permit for Stormwater Discharge from Construction Activity, which will include Stormwater Pollution Prevention Plan (SWPPP) as required by F.A.C. 62-621.300(4) and the Environmental Protection Agency 01060 - 1 (EPA) as part of the National Pollutant Discharge Elimination System (NPDES). (See Appendix B) 1. Contractor shall prepare, submit and obtain the appropriate dewatering permits and/or any temporary stormwater discharge permits from the South Florida Water Management District and/or Florida Department of Environmental Protection. 1.04 NOTIFICATION A. The Contractor is required to notify the Owner and any applicable permitting agency who requires notification as part of their permit condition within the timeframe stated on the permit. If no time exists, notification shall be a minimum of 48 hours prior to initiating construction. B. Utility Companies: Contractor shall notify the Sunshine State One Call of Florida (SSOCF) service at 811, 48 hours prior to digging for direct bury and 10 days prior to digging or initiating construction of underwater construction activities, as required by Florida Statues Chapter 556 throughout the duration of the construction project. C. The Contractor shall give the Engineer not less than seven (7) calendar days notice of the time and place (or places) where he will start the work. 1.04 PERMIT CONDITIONS A. Contractor shall comply with and furnish all items necessary to satisfy any general or specific conditions that are a part of the Owner obtained permits. PART 2 — PRODUCTS NOT USED PART 3 — EXECUTION NOT USED END OF SECTION 01060 - 2 SECTION 01090 REFERENCE STANDARDS PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Abbreviations and acronyms used in Contract Documents to identify reference standards. 1.02 QUALITY ASSURANCE A. Application: When a standard is specified by reference, comply with requirements and recommendations stated in that standard, except when requirements are modified by the Contract Documents, or applicable codes establish stricter standards. B. Publication Date: The publication in effect on the date of issue of Contract Documents, except when a specific publication date is specified. C. For Products or workmanship specified by association, trade, or other consensus standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes. D. Conform to reference standard by date of issue current on bid date. E. Obtain copies of standards when required by the Contract Documents. F. Maintain copy at project site during submittals, planning, and progress of the specific work, until Substantial Completion. G. Should specified reference standards conflict with Contract Documents, request clarification from the Engineer before proceeding. H. Neither the contractual relationship, duties, nor responsibilities of the parties in Contract nor those of the Engineer shall be altered by the Contract Documents by mention or inference otherwise in any reference document. 1.03 ABBREVIATIONS, NAMES, AND ADDRESSES OR ORGANIZATIONS A. Obtain copies of reference standards direct from publication source, when needed for proper performance of work, or when required for submittal by Contract Documents. 01090 - 1 B. The following, as appropriate to project, is a list of referenced standards and their mailing addresses for requesting copies of standards: AA Aluminum Association 818 Connecticut Avenue, NW Washington, D.C. 20006 AASHTO American Association of State Highway and Transportation Officials 444 North Capitol Street, NW Washington, D.C. 20001 ACI American Concrete Institute Box 19150 Redford Station Detroit, MI 48219 Al Asphalt Institute Asphalt Institute Building College Park, MD 20740 AISC American Institute of Steel Construction 1221 Avenue of the Americas New York, NY 10020 AISI American Iron and Steel Institute 1000 16t" Street, NW Washington, D.C., 20036 ANSI American National Standards Institute 1430 Broadway New York, NY 10018 ASME American Society of Mechanical Engineers 345 East 47t" Street New York, NY 10017 ASPA American Sod Producers' Association Association Building Ninth and Minnesota Hastings, NE 68901 ASSE American Society of Sanitary Engineers 960 Illuminating Building Cleveland, OH 44113 01090 - 2 ASTM American Society for Testing and Materials 1916 Race Street Philadelphia, PA 19103 AWPA American Wood-Preservers Association 7735 Old Georgetown Road Bethesda, MD 20014 AWS American Welding Society 2501 NW 7t" Street Miami, FL 33125 AWWA American Water Works Association 6666 W. Quincy Avenue Denver, CO 80235 CDA Copper Development Association 57t" Floor, Chrysler Building 405 Lexington Avenue New York, NY 10017 CLFMI Chain Link Fence Manufacturers Institute 1101 Connecticut Avenue Washington, D.C. 20036 County Palm Beach County Engineering and Public Works 2300 N. Jog Road West Palm Beach, FL 33411 CRSI Concrete Reinforcing Steel Institute 180 North LaSalle Street, Suite 2110 Chicago, IL 60601 FDEP Florida Department of Environmental Protection 3900 Commonwealth Blvd. Tallahassee, FL 32399 FDOT Florida Department of Transportation Haydon Burns Building 605 Suwannee Street Tallahassee, FL 32301 FM Factory Mutual System 1151 Boston-Providence Turnpike Norwood, MA 02062 01090 - 3 FS Federal Specifications General Services Administration Specifications and Information Distribution Section (WFSIS) Washington Navy Yard, Bldg. 197 Washington, D.C. 20407 MUTCD Manual on Uniform Traffic Control Devices Federal Highway Administration (FHWA) 1200 New Jersey Ave., SE Washington, DC 20590 NEMA National Electrical Manufacturers Association 2101 L Street, NW Washington, D.C. 20037 NFPA National Fire Protection Association 470 Atlantic Avenue Boston, MA 02210 NFPA National Forest Products Association 1619 Massachusetts Avenue, NW Washington, D.C. 20036 NSF National Sanitation Foundation NSF Building 3475 Plymouth Road Ann Arbor, MI 48106 NSWMA National Solid Waste Management Association 1120 Connecticut Avenue, NW Washington, D.C. 20036 PCA Portland Cement Association 5420 Old Orchard Road Skokie, IL 20076 PCI Prestressed Concrete Institute 20 North Wacker Drive Chicago, IL 60606 PS Product Standard U.S. Department of Commerce Washington, D.C. 20203 01090 -4 SFWMD South Florida Water Management District 3301 Gun Club Road West Palm Beach, FL 33406 TCA Technical Aid Series Construction Specifications Institute 1150 Seventeenth Street, NW Washington, D.C. 20036 UL Underwriters Laboratories, Inc. 333 Pfingston Road Northbrook, IL 60062 Village Village of Tequesta Utilities Department 345 Tequesta Drive Tequesta, FL 33469 PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01090 - 5 This page intentionally left blank 01090 - 6 SECTION 01050 MEASUREMENT AND PAYMENT PART 1 - GENERAL 1.01 DESCRIPTION This section defines the method which will be used to determine the quantities of work performed, materials supplied and establishes the basis upon which payment will be made. A The Unit Cost Prices stated in the Contract shall be considered payment in Full for the completion of all work. Payment shall be made under each item only for work as it is not specifically included under other items. B. The Contractor shall furnish all labor, equipment and material required to complete the construction and testing of the watermain extension and associated appurtenances. C. The following explanation of the Measurement and Payment for the bid items is provided; however, the omission of reference to any item shall not alter the intent of the Bid Form or relieve the Contractor of the necessity of constructing a complete project under this Contract. 1.02 ESTIMATED QUANTITIES Where quantities are shown, they are approximate and are given only as a basis of calculation upon which the award of the contract is to be made. The Village orEngineer do not assume any responsibility for the final quantities, nor shall Contractor claim misunderstanding because of such estimate of quantities. Final payment will be made only for the satisfactorily completed quantity of each item. 1.03 MEASUREMENT STANDARDS All work completed under the Contract shall be measured according to United States Standard Methods. 1.04 METHOD OF MEASUREMENT Measurement of Length - Unless otherwise specified for the particular items involved, all measurements of distance for items to be paid for on the basis of length shall be taken horizontally or vertically. Measurement of Area - In the measurement of items paid for on the basis of area of finished work, the lengths and/or widths to be used in the calculations shall be the actual dimensions measured along the surface of the completed work within the neat lines shown or designated. At intersections, the measurement used for length of side area will be 01150 - 1 measured from the outside edge of the width allowed along the main trench. 1.06 PAYMENT Lump Sum Items -Where payment for items is shown to be paid for on a lump sum basis, no separate payment will be made for any item of work required to complete the lump sum item. Unit Price Items - Where payment for items is shown to be paid for on a unit price basis, separate payment will be made for the items of work described herein and listed on the Bid Form. Any related work not specifically listed, but required for satisfactory completion of the Work, shall be considered to be included in the scope of the appropriate listed work items. 1.06 COSTS INCLUDED IN PAYMENT ITEMS No separate payment will be made for the following items and the cost of such work shall be included in the applicable pay items of work. • Clearing and grubbing. • Trench excavation, including necessary pavement removal, except as otherwise specified. • Structural fill, backfill, density testing and grading. • Site cleanup. • Foundation and borrow materials, except as hereinafter specified. • Stormwater pollution prevention plan. • Survey layout and as builts. • Testing and placing system in operation. • Any material and equipment required to be installed and utilized for tests. • Maintaining the existing quality of service during construction. • Appurtenant work as required for a complete and operable system. • Cost for security (if special circumstances apply, approval must be received by the Engineer, in writing). • Material storage areas. • Disposal of excess fill and debris. • Scheduling and calling for utility locates. • Dewatering. • Preconstruction site videos. • Preparation of record drawings. • Mechanical joint restraint systems (to be included in the unit cost of the DI fittings). Site cleanup-Contractor's attention is called to the fact that cleanup is considered a part of the work of construction. No payment will be made until cleanup is essentially complete. Work Outside Authorized Limits — No final payments will be made for work constructed outside the authorized limits of work. 01150 - 2 1.07 APPLICATIONS FOR PAYMENT Applications for Payment shall be prepared by the Contractor and submitted to the Engineer in accordance with the schedule established by the General Conditions of the Contract and the Agreement. Applications for Payment shall be submitted in the number and form established by the Engineer at the Preconstruction Conference. The form shall be completely filled out and executed by an authorized representative of the Contractor. Supporting data such as schedules of stored materials shall be attached to each copy of the Application. 1.08 CHANGE ORDER PROCEDURE As defined in the General Conditions, a Change Order is a written order to the Contractor signed by the Village authorizing an addition, deletion or revision in the Work, or an adjustment in the Contract Price or the Contract Time which is issued afterthe execution of the Agreement. The following procedure shall be used in processing Change Orders: For Additions to the Work— The Village shall issue a written order to the Contractor directing him to accomplish the additional work. The Contractor shall review the order and if they feel that the additional work entitles him to additional payment or additional time, they may submit a claim as prescribed in the General Conditions of the Contract. For Deletions from the Work — The Village shall issue a written order to the Contractor directing him to make the change. If the Village feels that the contract price should be reduced as a result of the change, the Village shall make a claim for the reduction as provided in the General Conditions of the Contract. PART 2 — PRODUCTS NOT USED. PART 3 — EXECUTION 3.01 GENERAL CONDITIONS A MOBILIZATION & GENERAL CONDITIONS FOR INFRASTRUCTURE (GC-1) The quantity to be paid for under this pay item shall be on a lump sum basis. The Contractor's lump sum price shall include full compensation for all work related to mobilization and demobilization, and any other related work, except for any work designated to be paid for separately or to be specifically included in the costs of other work under the Contract. 01150 - 3 Payment shall be made at the Contract lump sum price and shall include, but not be limited to, the preparatory work and operations in mobilizing for beginning work on the project, including those operations necessary for the movement of personnel, equipment, supplies, videos/photos, clearing and grubbing, site cleanup, project setup, sanitary facilities, labor associated with permit acquisition, construction staging area preparation and closure, project signage, project coordination/management and incidentals to the project site and establishment of temporary provisions, controls, and utilities. This item shall include those permits that are required to be obtained by the contractor. This item shall also include field surveying/layout and complete record drawings in accordance with the project specifications and the applicable standards. The items specified in this Section consist of the costs of any pre and post construction expenses necessary for the start and completion of the project, excluding the cost of construction materials. The sum of mobilization and demobilization shall not exceed 5% of Total bid price. Partial Payments for mobilization shall be as follows: Construction Percent Allowable Percent of Complete Lump Sum for Mobilization 5% 25% 10% 50% 25% 75% 100% 100% B. MAINTENANCE OF TRAFFIC (GC-2) This pay item shall include the costs for all work related to the maintenance of traffic during the construction of the improvements as shown on the pans, and any other related work, except for any work designated to be paid for separately or to be specifically included in the cost of other work under the Contract. Maintenance of traffic shall be paid for at the Contract lump sum cost as listed on the Contract Bid Proposal completed and accepted. The Contract lump sum price shall include, but not be limited to, all signage, temporary striping, flagmen, barricades, temporary asphalt, temporary stabilized access around the construction equipment, notification to residents, assistance to provide garbage collection, mail/package delivery and daily access (if needed) of other utility support vehicles, all in accordance with Section 01570, Traffic Regulation. C. BONDS & INSURANCE REQUIREMENTS (GC-3) This pay item shall include the costs of bonds and any required insurance for the start of work, including temporary environmental controls, sanitary facilities and permits. 01150 - 4 Bonds and insurance shall be paid for at the Contract lump sum cost as listed on the Contract Bid Proposal completed and accepted. This pay item also includes a one-time Indemnification payment which will be made with the first Application for Payment at the Contract lump sum price as listed on the Contract Bid Proposal. D. SURVEY LAYOUT & RECORD DRAWINGS (GC-4) The quantity to be paid for under this Section shall be on a lump sum basis. Payment shall be made at the percentage of the item is complete and accepted by the Owner and shall include, but not be limited to, laying out the proposed improvements in the field, setting temporary and permanent benchmarks, grade stakes, etc., preparation of final Record Drawings, preparation of partial records drawings suitable for submittal to PBCHD for partial water main clearances, all in accordance with the project specifications and Village Standards. The Record Drawings shall be provided certified by a Florida licensed land surveyor. 3.02 WATER MAIN INSTALLATION A. PVC WATERMAIN (WM-1) The quantity to be paid or under this Section shall be to the nearest foot along the centerline of the pipe for the size of pipe installed as shown on the drawings, complete and accepted. No deduction shall be made for the length of valves and fittings installed in the line. Where the measurement terminates at a valve, bend, tee or other fittings, the centerline of the valve or fitting shall be the point of termination. Payment shall be made at the Contract unit price per lineal foot and shall include, but not be limited to, furnishing all materials, labor, and equipment required to install the PVC watermain piping, including layout, trench safety, permits, excavation of any type material including rock, disposal of unsuitable materials, providing suitable bedding material, backfill, compaction, density testing, grading, dewatering, cleaning, temporary pipe pigging/cannon flushing of the main and all other testing (with any temporary fittings/valves required), along with the preparation of record drawings shall be included in the cost of the pipe for a complete and functional system. The cost to adjust other utilities (electric, cable, telephone, etc.) if required, and the coordination with that utility, shall also be included in the pipe cost. B. DI WATERMAIN (WM-2) The quantity to be paid or under this Section shall be to the nearest foot along the centerline of the pipe for the size of pipe installed as shown on the drawings, complete and accepted. No deduction shall be made for the length of valves and fittings installed in the line. Where the measurement terminates at a valve, 01150 - 5 bend, tee or other fittings, the centerline of the valve or fitting shall be the point of termination. Payment shall be made at the Contract unit price per lineal foot and shall include, but not be limited to, furnishing all materials, labor, and equipment required to install the DI watermain piping, including layout, trench safety, permits, excavation of any type material including rock, disposal of unsuitable materials, providing suitable bedding material, backfill, compaction, density testing, grading, dewatering, cleaning, temporary pipe pigging/cannon flushing of the main and all other testing (with any temporary fittings/valves required), fence restoration if applicable, along with the preparation of record drawings shall be included in the cost of the pipe for a complete and functional system. The cost to adjust other utilities (electric, cable, telephone, etc.) if required, and the coordination with that utility, shall also be included in the pipe cost. C. RSGV W/ VALVE BOX (WM-3) The quantity to be paid for under this Section shall be per unit as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price and shall include, but not be limited to, furnishing all materials, labor and equipment required to install each type and size of the gate valves required, including the valve box or collar, as noted, for a complete and functional system. D. FIRE HYDRANT ASSEMBLY (WM-4) The quantity to be paid for under this Section shall be at the Contract unit price per unit as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price and shall include, but not be limited to, furnishing all materials, labor and equipment required to install the fire hydrant assemblies including excavation of an type of material including rock, trench safety, dewatering, connection to the proposed or existing pipe, installation of the fire hydrant, valve, pipe, and fittings according to Village standards, fence restoration, if applicable, and any other items required for a complete and functional system. This line item also includes restoration and protective bollards if the setback or clear-zone limits cannot be met. E. DI FITTINGS (WM-5) The quantity to be paid for under this Section shall be at the Contract unit price per installed pound of fittings. Fittings installed by the Contractor to suit his schedule, realignment of he main or availability of materials shall not be paid for unless approved by the Engineer in writing. Payment shall be made at the Contract unit price per pound of fittings installed 01150 - 6 and shall include, but not be limited to, furnishing all materials, labor, and equipment required to install the fittings, including joint restraint, layout, and any other items required for a complete and functional system. F. TEMPORARY BLOWOFF ASSEMBLY (WM-6) The quantity to be paid for under this Section shall be at the Contract unit price per installed blowoff, complete and accepted. Payment shall be made at the Contract unit price per blowoff assembly installed and shall include, but not be limited to, furnishing all materials, labor, and equipment required for installation including joint restraint, layout and any other items required for a complete and functional system. G. SAMPLE POINTS (WM-7) The quantity to be paid for under this Section shall be per each unit shown on the drawings installed and successfully bacteriologically tested and accepted. Payment shall be made at the Contract unit price per sample point and shall include, but not be limited to, furnishing all materials, labor, and equipment required to construct the temporary sampling points for the proposed watermain piping in accordance with the Village and FDEP standards, to demolish upon successful completion of startup testing, and any other items required or a complete and functional system. Approval of payment will require complete bacteriological analysis by an independent, state-certified laboratory. H. WATER SERVICES (WM-8) The quantity to be paid for under this Section shall be per unit as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price per water service and shall include, but not be limited to, furnishing all materials, labor, and equipment required to reconnect or relocate the water meter services including excavation of any type of material, including rock, installation of road crossing services sleeves via approved trenchless technology, dewatering, connection of newly relocated water service piping to existing water meter, restoration, and any other items required for a complete and functional system. It is to be noted that the Contractor should also include costs to complete exploration to determine if a service relocation is required. This project does not include replacement of any water meter however, replacement water meters will be necessary if the existing meter is damaged during construction activities. The Contractor will be responsible for this cost. 01150 - 7 I. CONNECTION TO EXIST. 8" AC WATERMAIN (WM-9) The quantity to be paid for under this Section shall be per each connection completed and accepted. Payment shall be made at the Contract unit price per connection and shall include but not be limited to, furnishing all labor and equipment required to perform the connection to the existing water main including soft dig locates and existing main outer diameter verification, coordination with the Village for water main shutdown, coordination for boil-water notices as required, all temporary caps and plugs as shown on the plans, flushing, cleaning, pigging, pressure testing, grading, restoration, coordination with affected utility owners, and any other items required for a complete and functional system. 3.03 RESTORATION A. GRAVEL PARKING AREA (R-1) This quantity paid for under this Section shall be per square yard basis for either trench repair or gravel road repairs required to the parking areas as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price per square yard and shall include, but not be limited to, furnishing all materials, labor, and equipment required to repair the roadway that has been damaged due to the project efforts including base material, compaction, density testing, grading, gravel placement and verification of existing drainage patterns for a complete and functioning system. B. PBC ROAD RESURFACING (R-2) This quantity paid for under this Section shall be per square yard basis for either the pipe trench restoration or mill and resurface with the type of asphalt mix as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price per square yard and shall include, but not be limited to, furnishing all materials, labor and equipment required for grading and compaction, density testing, layout placement of base/sub base, asphalt or cold patch as necessary, sawcutting, asphalt placement, base preparation, striping (temporary and permanent) and verification of existing drainage patterns to repair the roadway that has been damaged due to the project efforts for a complete and functioning system. C. SOD (R-3) This quantity paid for under this Section shall be per square yards of sod installed completed and accepted. 01150 - 8 Payment shall be made at the Contract unit price per square yard and shall include but not be limited to, soil preparation, watering, and sod installation (pegged as required) for a complete and functional system. 3.04 MISCELLANEOUS WATERMAIN A. RELOCATE VOT WTP SAMPLE POINT (M-1) The quantity to be paid for under this Section shall be per unit as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price and shall include, but not be limited to, furnishing all materials, labor and equipment required to relocate the sample point required for system testing by the VOT WTP including coordination with the Village staff on new location, flushing and cleaning as required for a complete and functional system. B. 8" GATE VALVE (M-2) The quantity to be paid for under this Section shall be per unit as shown on the drawings, complete and accepted. Payment shall be made at the Contract unit price and shall include, but not be limited to, furnishing all materials, labor and equipment required to install each type and size of the gate valves required, including the valve box or collar, coordination with the Village for water main shutdown, boil water notices, flushing and cleaning, coordination with affected utility owners, and any other items required for a complete and functional system. C. WM REMOVAL /ABANDONMENT (M-3) The quantity to be paid for under this Section shall be per lineal foot of existing water main grout filled or abandoned and accepted. Payment shall be made at the Contract unit price per lineal foot and shall include, but not be limited to, furnishing all materials, labor, and equipment required to remove all existing surface material and protruding objects, excavation of any type of material including rock, trench safety, dewatering, pipe cutting and removal as required for grout ports, caps/seals/plugs on existing main grout filling of existing utilities as noted on the plans, trench backfilling, compaction, density testing, grout ports area restoration and any other items required for a complete and functional system. This pay item shall also include preparation of watermain abandonment plan, coordination with the Village, the hauling and legal off-site disposal of debris, and the removal, handling, and delivery of items to be salvaged and returned to the Village. All caps, plugs, or seals on existing mains or services to be abandoned/grout filled 01150 - 9 shall be paid for under this item. END OF SECTION 01150 - 10 SECTION 01152 APPLICATIONS FOR PAYMENT PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Submit Applications for Payment to Engineer in accordance with the schedule established by conditions of the Contract and Agreement between Owner and Contractor. 1.02 RELATED REQUIREMENTS A. In other parts of the Construction Documents: 1. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section 2. Agreement between Owner and Contractor 3. General Conditions and Terms of the Contract B. Specified in Other Sections- 1. Section 01010: Summary of Work 2. Section 01700: Contract Close-Out 1.03 FORMAT AND DATA REQUIRED A. Submit itemized applications typed in a format approved by Engineer. All applications for payment must be numbered, dated, and signed by the Contractor. B. Provide itemized data on payment application (format, schedules, line items and values accepted by Engineer). 1.04 PREPARATION OF APPLICATION FOR EACH PROGRESS PAYMENT A. Application Form: 1. Fill in required information, including that for Change Orders executed prior to the date of submittal of application 2. Fill in summary of dollar values 3. Execute certification with the signature of a responsible officer of the contract firm 4. Have resident project representative review and sign application prior to submission to Engineer 01152 - 1 1.05 SUBSTANTIATING DATA FOR PROGRESS PAYMENTS A. When the Owner or the Engineer requires substantiating data, Contractor shall submit suitable information, with a cover letter identifying- 1. Project 2. Application number and date 3. Detailed list of enclosures 4. For stored products: a. Item number and identification b. Description of specific material B. Submit one copy of data and cover letter for each copy of application. 1.06 PREPARATION OF APPLICATION FOR FINAL PAYMENT A. Application for payment is required for progress payments. B. Only one application will be acceptable in any one calendar month. 1.07 SUBMITTAL PROCEDURE A. Submit Applications for Payment to Engineer at the time stipulated in the Agreement. B. Number: Four copies of each progress Application. C. When Engineer finds the Application properly completed and correct, he will transmit the applications for payment to the Owner. PART 2 - PRODUCTS NOT USED. PART 3 - EXECUTION NOT USED END OF SECTION 01152 - 2 SECTION 01153 CHANGE ORDER PROCEDURES PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDE A. Promptly implement Change Order Procedures 1. Provide full written data required to evaluate changes. 2. Maintain detailed records of work done on a time-and-material/force account basis. 3. Provide full documentation to Engineer on request. B. Designate in writing the member of Contractor's organization: 1. Who is authorized to accept changes in the Work 2. Who is responsible for informing others in the Contractor's employ of the authorization of changes in the Work. C. Owner will designate in writing the person who is authorized to execute Change Orders. 1.02 RELATED REQUIREMENTS A. The amount of established unit prices. B. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. C. Terms and Conditions of the Contract- 1. Methods of determining cost or credit to Owner resulting from changes in Work made on a time-and-materials basis. 2. Contractor's claims for additional costs. D. Specified in other Sections. 1. Section 01152: Applications for Payment 2. Section 01300: Submittals and Progress Schedules 3. Section 01600: Material and Equipment 4. Section 01720: Project Record Drawings 01153 - 1 1.03 PRELIMINARY PROCEDURES A. Owner or Engineer may initiate changes by submitting a proposal Request to Contractor. Request will include the following- 1. Detailed description of the Change, Products, and location of the change in the Project. 2. Supplementary or revised Drawings and Specifications. 3. The projected time span for making the change, and a specific statement as to whether overtime work is, or is not, authorized. 4. A specific period of time during which the requested price will be considered valid. 5. Such request is for information only, and is not an instruction to execute the changes, nor to stop work in progress. B. Contractor may initiate changes by submitting a written notice to Engineer, containing- 1. Description of the proposed changes 2. Statement of the reason for making the changes. 3. Statement of the effect on the Contract Sum and the Contract Time. 4. Statement of the effect on the work of separate contractors. 5. Documentation supporting any changes in Contract Sum or Contract Time, as appropriate. 1.04 DOCUMENTATION OF PROPOSALS AND CLAIMS A. Support each quotation for a lump sum proposal, and for each unit price which has not previously been established, with sufficient substantiating data to allow Engineer to evaluate the quotation. B. On request, provide additional data to support time and cost computation including the following- 1. Labor required. 2. Equipment required. 3. Products required: a. Recommended source of purchase and unit cost. b. Quantities required. 4. Taxes, insurance bonds. 5. Credit for work deleted from Contract, similarly documented. 6. Overhead and profit. 7. Justification for any change in Contract Time. 01153 - 2 C. Support each claim for additional costs, and for work done on a time-and- material / force account basis, with documentation as required for a lump sum proposal, plus the following additional information- 1. Name of the Owner's authorization agent who ordered the work, and date of the order. 2. Dates and time work performed, and by whom. 3. Time record, summary of hours worked, and hourly rates paid. 4. Receipts and invoices for- a. Equipment used, listing dates and times of use. b. Products used, listing quantities. C. Subcontracts. D. Document requests for substitutions for products as specified in Section 01600. 1.05 PREPARATION OF CHANGE ORDERS A. Engineer will prepare each Change Order. B. Form: Change Order format provided in the Contract Documents. C. Change Order will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of change. D. Change Order will provide an accounting of the adjustment in the Contract Sum and in the Contract Time. 1.06 LUMP SUM / FIXED PRICE CHANGE ORDER A. Content of Change Orders will be based on either- 1. Engineer's Proposal Request and Contractor's responsible Proposal as mutually agreed upon between Owner and Contractor. 2. Contractor's Proposal for a change, as recommended by Engineer. B. Owner and Engineer will sign and date the Change Order as authorization for the Contractor to proceed with the changes. C. Contractor shall sign and date the Change Order to indicate agreement with the terms therein. 1.07 UNIT PRICE CHANGE ORDER A. Content of Change Orders will be based on, either: 01153 - 3 1. Engineer definition of the scope of the required changes. 2. Contractor's Proposal for a change, as recommended by Engineer. 3. Survey of completed work B. The amount of the unit prices shall be- 1. Those stated in the Agreement. 2. Those mutually agreed upon between Owner and Contractor. C. When quantities of each of the items affected by the Change Order can be determined prior to start of the work- 1. Owner and Engineer will sign and date the Change Order as authorization for Contractor to proceed with the changes. 2. Contractor shall sign and date the Change Order to indicate agreement with the terms therein. D. When quantities of the items cannot be determined prior to start of the Work- 1. Engineer or Owner will issue a Change Order directing Contractor to proceed with the change on the basis of unit prices, and will cite the applicable unit prices. 2. At completion of the change, the Engineer will determine the cost of such work based on the unit prices and quantities used. a. Contractor shall submit documentation to establish the number of units of each item and any claims for a change in Contract Time. 3. Engineer will sign and date a second Change Order to establish the change in Contract Sum and in Contract Time. 4. Owner and Contractor will sign and date the second Change Order to indicate their agreement with the terms therein. 1.08 CORRELATION WITH CONTRACTOR'S SUBMITTALS A. Contractor shall periodically revise Schedule of Values and Request for Payment forms to record each change as a separate item of Work, and to record the adjusted Contract Sum. B. Contractor shall periodically revise the Construction Schedule to reflect each change in Contract Time. 1. Revise sub-schedules to show changes for other items of work affected by the changes. 01153 -4 C. Upon completion of work under a Change Order, enter pertinent changes in Record Documents. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01153 - 5 This page intentionally left blank. 01153 - 6 SECTION 01200 PROJECT MEETINGS PART 1 — GENERAL 1.01 DESCRIPTION A. The Owner shall schedule and administer preconstruction meetings, public involvement meetings/communications, and specially called meetings throughout the progress of the work. The Owner shall- 1. Distribute written notice of each meeting. 2. Make physical arrangements for meetings. 3. Preside at meetings. 4. Record the minutes, include all significant proceedings and decisions. 5. Reproduce and distribute copies of minutes: a. To all participants in the meeting. b. To all parties affected by decisions made at the meeting. B. The Contractor shall schedule and administer progress meetings. The Contractor shall- 1. Distribute written notice of each meeting. 2. Make physical arrangements for meetings. 3. Preside at meetings. 4. Record the minutes, include all significant proceedings and decisions. 5. Reproduce and distribute copies of minutes: a. To all participants in the meeting. b. To all parties affected by decisions made at the meeting. C. Representatives of the Contractor, subcontractors and suppliers attending the meetings shall be qualified and authorized to act on behalf of the entity each represents. 1.02 RELATED REQUIREMENTS SPECIFIED ELSEWHERE A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01010: Summary of Work 2. Section 01060: Regulatory Requirements and Notifications 01200-1 1.03 PRE-CONSTRUCTION MEETING A. To be held prior to the Notice to Proceed. B. Location: The project site, or as designated by the Owner/Engineer. C. Attendance- 1. Owner's Representative 2. Engineer's Representative 3. Contractor 4. Contractor's Superintendent 5. Major Subcontractors 6. Other's as appropriate D. Agenda- 1. Record of Attendance. 2. Project Summary Description. 3. Local Utilities to be affected or in the project area: a. Water lines b. Sewer lines C. Storm lines d. Gas lines e. Telephone lines f. Cable TV lines g. Electric lines h. Roadways 4. Contractor Responsibilities: a. Start date b. Completion date C. Work schedule d. Notification Requirements e. Regulatory Permit Requirements f. Testing g. Space utilization h. Rights-of-Way occupancy i. Progress Meetings j. Progress Payment Application k. As-builts (Records/Drawings) 01200-2 I. Photographs M. Shop drawings n. Subcontractors o. Project coordination 5. Owner Responsibilities: a. Progress Meeting Attendance b. Special meetings C. Partial and final payment d. Change Orders e. Public announcements and public relations f. Project acceptance 6. Engineer Responsibilities: a. Technical representative of Owner b. Interpreter of contract documents C. Periodic inspections of job progress d. Reviews partial and final payment applications e. Reviews Change Orders f. Checks and approves shop drawings g. Reviews record drawings h. Prepares Health Department Clearance Package i. Performs final inspection and issues certificate of completion 7. Resident Inspector Responsibilities: a. Owner's representative on site b. Review materials and work and reports any deficiencies to Owner/Engineer C. Reviews applications for payment d. Works with Contractor on public notification of work items e. Attends progress meetings f. Observes testing work g. Maintains daily diary of work tasks h. Furnishes reports to Owner/Engineer as deemed advisable. 1.04 PROGRESS MEETINGS A. The Contractor shall hold periodic meetings as required by progress of the work. B. Location of the meetings: Project site, or as designated by the Owner or Engineer. 01200-3 C. Attendance- 1. Owner's Representative 2. Engineer's Representative 3. Subcontractors as appropriate 4. Suppliers/others as appropriate 1.05 EMERGENCY MEETINGS A. Emergency meetings may be called by Owner, Engineer or Contractor with a minimum of three hours notice to resolve conditions of an emergency nature. 1.06 PUBLIC INVOLVEMENT MEETINGS/COMMUNICATIONS A. There may will be public involvement meetings and communications for the project. The Contractor shall participate in these meetings and communications as deemed necessary by the Owner. PART 2 — PRODUCTS NOT USED PART 3 — EXECUTION NOT USED END OF SECTION 01200-4 SECTION 01300 SUBMITTALS AND PROGRESS SCHEDULES PART 1 - GENERAL 1.01 WORK INCLUDED A. Submit, to the Owner and Engineer as applicable, shop drawings, estimated construction progress schedule, project data and samples required by specification sections. 1.02 RELATED WORK A. General Conditions and Terms of the Contract B. Specified in other Sections- 1. Section 01010: Summary of Work 1.03 SCHEDULES A. Promptly after award of contract, prepare and submit to the Engineer estimated construction progress schedules for the work, including a separate schedule listing dates for submission and dates reviewed shop drawings, project data and samples will be needed for each product. 1.04 FORM OF SCHEDULES A. Prepare schedules in suitable electronic format. A horizontal bar chart should be used as additional illustration and for revised progress schedules. 1. Provide separate horizontal bar for each trade or operation 2. Horizontal time scale: Identify the first work day of each week. 3. Scale and spacing: To allow space for notations and future revisions. 4. Minimum sheet size: 11" x 17" B. Format of listings: The chronological order of the start of each item of work. C. Identification of listings: By major specification section numbers. 01300-1 1.05 CONTENT OF SCHEDULES A. Construction Progress Schedule shall- 1. Show the complete sequence of construction by activity. 2. Show the dates for the beginning and completion of each major element of construction; specifically, list: a. Mobilization / Demobilization b. Subcontractor work C. Water Main construction. Provide specific timelines for expected completion of each project area. Dates of connections and phasing should be included. d. Testing e. Restoration 3. Show projected percentage of completion for each item, as of the first day of each month. B. Submittals Schedule for Shop Drawings, Product Date and Samples. Show- 1. The dates for Contractor's submittals. 1.06 PROGRESS REVISIONS A. Indicate progress of each activity to date of submission of schedule. B. Show changes occurring since previous submission of schedule. 1. Major changes in scope. 2. Activities modified since previous submission. 3. Revised projections of progress and completion. 4. Other identifiable changes. C. Provide a narrative report as needed to define- 1. Problem areas, anticipated delays, and the impact on the schedule. 2. Corrective action recommended, and its effect. 3. The effect of changes on schedules of other contractors working in the area. 01300-2 1.07 SUBMISSIONS A. Submit initial schedules within 7 days after award of Contract. 1. Engineer will review schedules with Owner and return review copy within 5 days after receipt. 2. If required, resubmit within 2 days after return of review copy. B. Submit updated progress schedules with each application for payment. 1.08 DISTRIBUTION A. Distribute copies of the reviewed schedules to- 1. Job site file. 2. Subcontractors. 3. Other concerned parties. B. Instruct recipients to report promptly to the Contractor, in writing, any problems anticipated by the projections shown in the schedules. PART 2 - PRODUCTS 2.01 SHOP DRAWINGS A. Original drawings, prepared by Contractor, Subcontractor, Supplier or Distributor, which illustrate some portion of the Work; showing fabrication, layout, setting or erection details including, but not limited to the following- 1. Watermain Piping, Valves, Fittings, and Appurtenances 2. Asphalt Mix Design 3. Gravel Parking and Pavement Base Course 4. Concrete Mix Designs (with specific locations), grouts, etc. 5. Signing and Striping Details B. Shop drawings shall be prepared by a qualified detailer. C. Identify details by reference to sheet and detail numbers shown on Contract Drawings. 2.02 PROJECT DATA A. Manufacturer's standard schematic drawings 01300-3 1. Modify drawings to delete information which is not applicable to project. 2. Supplement standard information to provide additional information application to project. B. Manufacturer's catalog sheets, brochures, diagrams, schedules, performance charts, illustrations and other standard descriptive data. 1. Clearly mark each copy to identify pertinent materials, products or models. 2. Show dimensions and clearances required. 3. Show performance characteristics and capacities. 4. Show wiring diagrams and controls. 2.03 SAMPLES A. Physical examples to illustrate materials, equipment or workmanship, and to establish standards by which completed work is judged. B. Office samples of sufficient size and quantity to clearly illustrate- 1. Functional characteristics of product or material, with integrally related parts and attachment devices. 2. Full range of color samples. 2.04 PAY REQUESTS A. Pay Requests shall be made in accordance with the requirements of the Agreement between Owner and Contractor. PART 3 - EXECUTION 3.01 CONTRACTOR RESPONSIBILITIES A. Review Shop Drawings, Project Data and Samples prior to submission. Contractor's approval stamp shall be on each submittal when received by the Engineer. Unstamped submittals will not be reviewed and will be returned as "rejected" to the Contractor. B. Verify- 1. Field measurements. 2. Field construction criteria. 3. Catalog numbers and similar data. 01300-4 C Coordinate each submittal with requirements of Work and the Contract Documents. D. Contractor's responsibility for errors and omissions in submittals is not relieved by Engineer's review of submittals. E. Contractor's responsibility for deviations in submittals from requirements of Contract Documents is not relieved by Engineer's review of submittals, unless Engineer gives written acceptance of specific deviations. F. Notify Engineer, in writing at the time of submission, of deviations in submittals from requirements of Contract Documents. G. Begin no work which requires submittals until return of submittals with Engineer's stamp and initials or signature indicating review. H. After Engineer's review, distribute copies. 3.02 SUBMISSION REQUIREMENTS A. Schedule submissions at least 14 days before dates reviewed submittalswill be needed. B. All submittals shall be made electronically. C Accompany submittals with transmittal letter, in duplicate, containing- 1. Date. 2. Project title and number. 3. Contractor's name and address. 4. Notification of deviations from Contract Documents. 5. Other pertinent data. D. Submittals must include- 1. Date of submittal and revision dates. 2. Project title and number. 3. The names of: a. Engineer. b. Contractor. C. Subcontractor. d. Supplier. e. Manufacturer. f. Separate detailer when pertinent. 4. Identification of product or material. 01300-5 5. Relation to adjacent structure or materials. 6. Field dimensions, clearly identified as such. 7. Identification of deviations from Contract Documents. 8. Contractor's stamp, initialed or signed, certifying review of submittal, verification of field measurements and compliance with Contract Documents. 3.03 RESUBMISSION REQUIREMENTS A. Shop Drawings. 1. Revise initial drawings as required and resubmit as specified for initial submittal. 2. Indicate on drawings any changes which have been made other than those requested by Engineer. B. Project Data and Samples- 1. Submit new datum and samples as required for initial submittal. 3.04 DISTRIBUTION OF SUBMITTALS AFTER REVIEW A. Distribute copies of Shop Drawings and Project Datum which carry Engineer's stamp, to- 1. Contractor's file. 2. Job site file. 3. Record Documents file. 4. Other prime contractors. 5. Subcontractors. 6. Supplier. 7. Fabricator. END OF SECTION 01300-6 SECTION 01410 TESTING LABORATORY SERVICES PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. The Contractor will employ and pay for the services of an independent testing laboratory to perform certain specified testing. All testing described in the Contract Documents shall be paid for by the Contractor. B. The Owner may employ and pay for the services of an independent testing laboratory to perform certain specified testing in addition to what is called for in the Contract Documents. 1. The Contractor shall cooperate with the laboratory to facilitate the execution of its required services. 2. Employment of a laboratory by the Owner shall in no way relieve Contractor's obligations to perform the work of the Contract. C. Inspection, Sampling and Testing is required for- 1. Densities and Proctors (for soil compaction) 2. Bacteriological Clearance 3. Concrete Strength 4. Any water quality monitoring as required by the project permits 5. Other operations specified in these specifications or as required by the Engineer or Owner. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. General Conditions of the contract: Inspections and testing required by laws, ordinances, rules, regulations, orders or approvals of public authorities. See sections GC 7 and GC 37 of the General Conditions and Terms. 1.03 QUALIFICATION OF LABORATORY A. Meet "Recommended Requirements for Independent Laboratory Qualification," published by American Council of Independent Laboratories. 01410 - 1 B. Meet basic requirements of ASTM E329, "Standards of Recommended Practice for Inspection and Testing Agencies for Concrete and Steel as Used in Construction." C. Authorized to operate in the Village, County, and State in which the Project is located. D. Submit copy of report of inspection of facilities made by Materials Reference Laboratory of National Bureau of Standards during the most recent tour of inspection, with memorandum of remedies of any deficiencies reported by the inspection. E. Testing Equipment: 1. Calibrated at reasonable intervals by devices of accuracy traceable to either: a. National Bureau of Standards b. Accepted values of national physical constants. 1.04 LABORATORY DUTIES A. Cooperate with Engineer and Contractor; provide qualified personnel after due notice. B. Perform specified inspections, sampling, and testing of materials and methods of construction- 1. Comply with specified standards 2. Ascertain compliance of materials with requirements of Contract Documents. C. Promptly notify Engineer and Contractor of observed irregularities or deficiencies of work or products. D. Promptly submit written report of each test and inspection; one copy each to Engineer, Owner, and Contractor, and one copy to Record Documents File. Each report shall include- 1. Date issued 2. Project title and number 3. Testing laboratory name, address, and telephone number 4. Name and signature of laboratory inspector 5. Date and time of sampling or inspection 6. Record of temperature and weather conditions 01410 - 2 7. Date of test 8. Identification of product and specification section 9. Location of sample or test in the Project 10. Type of inspection or test 11. Results of tests and compliance with Contract Documents 12. Interpretation of test results, when requested by Engineer E. Perform additional tests as required by Engineer or the Owner 1.05 LIMITATIONS OF AUTHORITY OF TESTING LABORATORY A. Laboratory is not authorized to- 1. Release, revoke, alter, or enlarge on requirements of Contract Documents 2. Approve or accept any portion of the work 3. Perform any duties of the Contractor 1.06 CONTRACTOR'S RESPONSIBILITIES A. Cooperate with laboratory personnel, and provide access to work and to manufacturer's facilities. B. Secure and deliver to the laboratory adequate quantities of representative samples of materials proposed to be used and which require testing. C. Provide to the laboratory the preliminary design mix proposed to be used for concrete, and other material mixes which require control by the testing laboratory. D. Provide to the laboratory a representative proctor sample of the materials to be used for backfilling throughout the project. E. Furnish copies of product test reports as required. F. Furnish incidental labor and facilities- 1. To provide access to work to be tested 2. To obtain and handle samples at the project site or at the source of the product to be tested 3. To facilitate inspections and tests 4. For storage and curing of test samples G. Notify laboratory, in advance of operations to allow for laboratory assignments of personnel and scheduling of tests. 01410 - 3 H. Pay for services of the Testing Laboratory to perform additional inspections, sampling and testing required- 1. For Contractor's convenience. 2. When initial tests indicate Work does not comply with Contract Documents. Such payment shall be made directly by the Contractor. I. Contractor will be responsible for payment for all failing tests. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01410 -4 SECTION 01510 TEMPORARY UTILITIES PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Furnish, install, and maintain temporary utilities required for construction; remove on completion of entire project. B. Provide temperature, ventilation, and lighting requirements, if applicable, as specified in each individual section. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections: 1. Section 01010: Summary of Work 1.03 REQUIREMENTS OF REGULATORY AGENCIES A. Comply with National Electric Code. B. Comply with federal, state, and local codes and regulations, and with utility company requirements. PART 2 - PRODUCTS 2.01 MATERIALS (GENERAL) A. Materials may be new or used, but must be adequate in capacity for the required usage. They MUST NOT create unsafe conditions, and MUST NOT violate requirements of applicable codes and standards. 2.02 TEMPORARY ELECTRICITY AND LIGHTING A. The Contractor must maintain power to all existing buildings, pump stations, businesses, residences, and other related areas. 01510 - 1 B. The Contractor is responsible for providing and paying for all power required for his operations. The Contractor shall make arrangements with The Owner for temporary power. C. The Contractor is responsible for arranging power for his office trailers(s), power tools, etc., at his own expense. The Contractor shall pay the costs of all power used. D. Provide Power Centers for miscellaneous tools and equipment used in the work- 1. Weatherproof distribution box with minimum of four 20-amp., 120- volt grounded outlets. 2. Locate so that power is available at any point of use with minimum 100-foot Construction-Type power cords. 3. Provide circuit breaker protection for each outlet. E. Provide adequate artificial lighting for all areas of work, when natural light is not adequate for work, and for areas accessible to persons other than Contractor's employees. F. If Contractor requires service other than specified above, he shall arrange for, provide maintenance, and pay all costs incurred. 2.03 TEMPORARY WATER A. The Contractor will be responsible for making an application to the Village of Tequesta for hydrant meters with backflow preventers. The Village of Tequesta will install necessary connections and backflow preventers at locations needed by the Contractor and approved by the Engineer. Maintenance of such is the responsibility of the Contractor. B. Construction water will be paid for by the Contractor. In an event that damage to these facilities occurs, the Contractor will be responsible for all costs associated with their replacement by the Village's standard rate. 2.04 TEMPORARY SANITARY FACILITIES A. The Contractor shall provide temporary sanitary facilities in compliance with laws and regulations. Location of such facilities will be subject to the approval of the Village of Tequesta as applicable. Existing Village facilities are not available for use by the Contractor. B. The Contractor shall provide for regular service, cleaning, and maintenance of temporary facilities and enclosures. 01510 - 2 PART 3 - EXECUTION 3.01 GENERAL A. Maintain and operate systems to ensure continuous service. 3.02 REMOVAL A. Completely remove temporary materials and equipment when their use is no longer required. B. Clean and repair damage caused by temporary installations or use of temporary facilities. C. Restore existing facilities used for temporary services to specified, or to original, condition. END OF SECTION 01510 - 3 This page intentionally left blank. 01510 -4 SECTION 01560 TEMPORARY CONTROLS PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Furnish, install, and maintain temporary control facilities required for construction; remove on completion of entire project any features not intended to remain on the project site. B. Provide noise control, dust control, water control, debris control, pollution control and erosion control as specified in the appropriate sections of these documents. 1.02 REQUIREMENTS OF REGULATORY AGENCIES A. Comply with federal, state, and local codes and regulations and utility company requirements. B. Comply with the requirements of all permits and easements issued by the FDEP, Palm Beach County Health Department, SFWMD, Village of Tequesta, Palm Beach County, and any other agencies that have issued permits for the project. 1.03 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. PART 2 - PRODUCTS 2.01 MATERIALS (GENERAL) A. Materials may be new or used, but must be adequate in capacity and quality for the required usage, MUST NOT create unsafe conditions and MUST NOT violate requirements of applicable codes and standards. 2.02 TEMPORARY NOISE CONTROL A. Mechanical equipment shall be fitted with mufflers to reduce noise from internal combustion type engines. B. Bells, sirens, alarms, etc., shall be adjusted to provide adequate warnings to personnel on the project site; however, they shall be regulated to an intensity that is amenable to the neighboring communities and within applicable limitations stated within level code of ordinance. 01560 - 1 C. Exterior construction work noises shall be kept to a minimum during evening, night, and early morning hours. D. In addition to on-site control, noise considerations shall be made to off- site vehicles and equipment (mobilization, demobilization, deliveries, etc.). 2.03 TEMPORARY DUST CONTROL A. Dust formed as a result of the construction shall be controlled by the Contractor. Cleaning of work areas and application of dust control materials are the most effective methods of dust control. Contractor shall adhere to the methods indicated in the Stormwater Pollution Prevention Plan (SWPPP) prepared by the Contractor. 2.04 TEMPORARY WATER CONTROL A. The flow of water through the construction site shall be controlled by the Contractor such that it does not damage any constructed items; however, it shall be diverted and channeled to effectively leave the site as soon as possible. Puddling and ponding on the site is not permitted. B. Water shall be controlled such that it does not enter excavated areas, nor is deposited on or against constructed features. 2.05 TEMPORARY DEBRIS CONTROL A. Provision shall be made by each Contractor to have available and adequate containers to hold any and all debris that is generated from the project. Containers should be covered to prevent wind blowing paper, plastic, and lightweight products around and off the site. B. Provide acceptable containers for deposit of debris and waste. Instructions shall be given to personnel to utilize the trash containers. Containers shall be placed in convenient places at the site. C. At least once per week, a thorough cleaning of trash and debris shall be made at the construction site. An acceptable method of disposal shall be employed. D. Maintain all areas under the Contractor's control free of extraneous debris, garbage and waste matter. E. Initiate and maintain a specific program to prevent accumulation of debris at the construction site, storage and parking areas, or along access roads and haul routes. F. Prohibit overloading of trucks to prevent spillage on access and haul roads. 01560 - 2 G. Provide periodic inspection of traffic areas to enforce requirements. 2.06 POLLUTION CONTROL A. Provide methods, means and facilities required to prevent contamination of soil, water or air by the discharge of noxious substances from construction operations. B. Immediately remove and properly dispose of all contaminated materials upon discovery of spillage of noxious substances. C. Take special precautions to prevent harmful substances from entering public waters. D. Provide systems for control of atmospheric pollutants and prevent toxic concentrations of chemicals. 2.07 EROSION CONTROL A. Abide by the Erosion Control Plan on the Drawings and described in the SWPPP submitted as part of the FDEP Notice of Intent. B. Plan and execute construction and earthwork by methods to control surface drainage from cuts and fills and from borrow and waste disposal areas to prevent erosion and sedimentation. C. Hold areas of bare soil exposed at one time to a minimum and provide temporary control measures such as berms, dikes and drains. D. Construct fills and waste areas by selective placement to eliminate surface silts and clays which erode. PART 3 - EXECUTION 3.01 GENERAL A. Comply with all applicable requirements of local building codes. B. Maintain and operate systems to assure continuous service. C. Modify and extend systems as work progress requires. D. Preserve from damage all property along the line of work or which is in the vicinity of or is in any way affected by the Work. Wherever such property is damaged due to the activities of the Contractor, it shall be immediately restored to its original condition by the Contractor at no cost to the Owner. 01560 - 3 3.02 INSPECTIONS A. Prior to placing temporary facilities into service, inspect and test each service and arrange for inspections and tests by governing authorities and obtain required certifications and permits for use thereof. 3.03 REMOVAL A. Completely remove temporary materials and equipment when their use is no longer required. B. Clean and repair damage caused by temporary installations or use of temporary facilities. C. Restore permanent facilities used for temporary services to specified conditions. END OF SECTION 01560 -4 SECTION 01561 PROTECTION OF EXISTING FACILITIES PART 1 - GENERAL 1.01 GENERAL A. The Contractor shall protect all existing utilities and improvements not designated for removal and shall restore damaged or temporarily relocated utilities and improvements to a condition equal to or better than they were prior to such damage or temporary relocation, all in accordance with requirements of the Contract Documents. B. The Contractor shall verify the exact locations and depths of all utilities shown and the Contractor shall make exploratory excavations of all utilities that may interfere with the work. All such exploratory excavations shall be performed as soon as practicable after award of the contract and, in any event, a sufficient time in advance of construction to avoid possible delays to the Contractor's Work. When such exploratory excavations show the utility location as shown to be in error, the Contractor shall so notify the Engineer. C. The number of exploratory excavations required shall be that number which is sufficient to determine the alignment and grade of the utility. 1.02 RIGHTS-OF-WAY A. The Contractor shall not do any work that would affect any oil, gas, sewer, or water pipeline; any telephone, telegraph, or electric transmission line; any fence; or any other structure, nor shall the Contractor enter upon the rights-of-way involved until notified by the Engineer that the Owner has secured authority from the proper party. After authority has been obtained, the Contractor shall give said party due notice of its intention to begin work, if required by said party, and shall remove, shore, support or otherwise protect such pipeline, transmission line, ditch, fence, or structure or replace the same. When two or more contracts are being executed at one time on the same or adjacent land in such manner that work on one contract may interfere with that on another, the Owner shall determine the sequence and order of the Work. When the territory of one contract is the necessary or convenient means of access for the execution of another contract, such privilege of access or any other reasonable privilege may be granted by the Owner to the Contractor, to the extent, amount, in the manner, and at the times permitted. No such decision as to the method or time of conducting the Work or the use of territory shall be made the basis of any claim for delay or damage, except as provided for temporary 01561-1 suspension of the Work in the General Conditions of the Contract. 1.03 PROTECTION OF STREET OR ROADWAY MARKERS A. The Contractor shall not destroy, remove, or otherwise disturb any existing survey markers or other existing street or roadway markers without proper authorization. No pavement breaking or excavation shall be started until all survey or other permanent marker points that will be disturbed by the construction operations have been properly referenced. All survey markers or points disturbed by the Contractor shall be accurately restored after all street or roadway resurfacing has been completed. 1.04 RESTORATION OF PAVEMENT/SIDEWALKS A. General: All paved areas including asphaltic concrete berms cut or damaged during construction shall be replaced with similar materials and of equal thickness to match the existing adjacent undisturbed areas, except where specific resurfacing requirements have been called for in the Contract Documents or in the requirements of the agency issuing the permit. All temporary and permanent pavement shall conform to the requirements of the affected pavement Owner. All pavements which are subject to partial removal shall be neatly saw cut in straight lines. B. Temporary Resurfacing: Wherever required by the public authorities having jurisdiction, the Contractor shall place temporary surfacing promptly after backfilling and shall maintain such surfacing for the period of time fixed by said authorities before proceeding with the final restoration of improvements. C. Permanent Resurfacing: In order to obtain a satisfactory junction with adjacent surfaces, the Contractor shall saw cut back and trim the edge so as to provide a clean, sound, vertical joint before permanent replacement of an excavated or damaged portion of pavement. Damaged edges of pavement along excavations and elsewhere shall be trimmed back by saw cutting in straight lines. All pavement restoration and other facilities restoration shall be constructed to finish grades compatible with adjacent undisturbed pavement. 1.05 EXISTING UTILITIES AND IMPROVEMENTS A. General: The Contractor shall protect all Underground Utilities and other improvements which may be impaired during construction operations. It shall be the Contractor's responsibility to ascertain the actual location of all existing utilities and other improvements that will be encountered in 01561-2 construction operations, and to see that such utilities or other improvements are adequately protected from damage due to such operations. The Contractor shall take all possible precautions for the protection of unforeseen utility lines to provide for uninterrupted service and to provide such special protection as may be necessary. B. Utilities to be Moved: In case it shall be necessary to move the property of any public utility or franchise holder, such utility company or franchise holder will, upon request of the Contractor, be notified by the Contractor to move such property within a specified reasonable time. When utility lines that are to be removed are encountered within the area of operations, the Contractor shall notify the Engineer a sufficient time in advance for the necessary measures to be taken to prevent interruption of service. C. Where the proper completion of the work requires the temporary or permanent removal and/or relocation of an existing utility or other improvement which is indicated, the Contractor shall, at the Contractor's expense, remove and, without unnecessary delay, temporarily replace or relocate such utility or improvement in a manner satisfactory to the Engineer and the Owner of the facility. In all cases of such temporary removal or relocation, restoration to former location shall be accomplished by the Contractor in a manner that will restore or replace the utility or improvement as nearly as possible to its former locations and to as good or better condition than found prior to removal. D. Owner's Right of Access: The right is reserved to the Owner and to the providers of public utilities and franchises to enter at any time upon any public street, alley, right- of-way, or easement for the purpose of making changes in their property made necessary by the work of this Contract. E. Underground Utilities Indicated: Existing utility lines that are indicated or the locations of which are made known to the Contractor prior to excavation and that are to be retained, and all utility lines that are constructed during excavation operations shall be protected from damage during excavation and backfilling and, if damaged, shall be immediately repaired or replaced by the Contractor. F. Underground Utilities Not Indicated: In the event that the Contractor damages any existing utility lines that are not indicated or the locations of which are not made known to the Contractor by Florida One Call prior to excavation, a written report thereof shall be made immediately to the Engineer. If directed by the Engineer, repairs shall be made by the Contractor under the provisions for changes and extra work contained in 01561-3 the General Conditions of the Contract. The Contractor shall be responsible for all repair or relocation costs for any failure by the Contractor to contact appropriate utilities for locations prior to digging. G. Approval of Repairs: All repairs to a damaged utility or improvement are subject to inspection and approval by an authorized representative of the utility or improvement Owner and the Engineer before being concealed by backfill or other work. H. Maintaining in Service: All oil and gasoline pipelines, power, and telephone or the communication cable ducts, gas and water mains, irrigation lines, sewer lines, storm drain lines, poles, and overhead power and communication wires and cables encountered along the line of the work shall remain continuously in service during all the operations under the Contract, unless other arrangements satisfactory to the Engineer are made with the Owner of said pipelines, duct, main, irrigation line, sewer, storm drain, pole, or wire or cable. The Contractor shall be responsible for and shall repair all damage due to its operations, and the provisions of this Section shall not be abated even in the event such damage occurs after backfilling or is not discovered until after completion of the backfilling. I. Existing Water Services: Contractor shall protect and provide temporary support for existing water services. Any water service damaged by the Contractor, shall be replaced at the Contractor's expense, with a new water service complete with new water main tap. 1.06 TREES WITHIN STREET RIGHTS-OF-WAY AND PROJECT LIMITS A. General: The Contractor shall exercise all necessary precautions so as not to damage or destroy any trees or shrubs, including those lying within street rights-of-way and project limits, and shall not trim or remove any trees unless such trees have been approved for trimming or removal by the jurisdictional agency or Owner. All existing trees and shrubs which are damaged during construction shall be trimmed or replaced by the Contractor or a certified tree company under permit from the jurisdictional agency and/or the Owner. Tree trimming and replacement shall be accomplished in accordance with the following paragraphs. All trees to remain in right-of-way shall be protected and fenced with orange barricade fencing. B. Trimming: Symmetry of the tree shall be preserved; no stubs or splits or branches left; clean cuts shall be made close to the trunk or large branch. Spikes shall not be used for climbing live trees. All cuts over 1-1/2 inches in diameter shall be coated with an asphaltic emulsion material. 01561-4 C. Replacement: The Contractor shall immediately notify the jurisdictional agency and/or the Owner if any tree is damaged by the Contractor's operations. If, in the opinion of said agency or the Owner, the damage is such that replacement is necessary, the Contractor shall replace the tree at its own expense. The tree shall be of a like size and variety as the tree damaged, or, if of a smaller size, the Contractor shall pay to the owner of said tree a compensatory payment acceptable to the tree owner, subject to the approval of the jurisdictional agency or Owner. The size of the trees shall be not less than 1-inch diameter nor less than 6-feet in height. 1.07 NOTIFICATION BY THE CONTRACTOR A. Prior to any excavation in the vicinity of any existing underground facilities, including all water, sewer, storm drain, gas, petroleum products, or other pipelines; all buried electric power, communications, or television cables; all traffic signal and street lighting facilities; and all roadway and state highway rights-of-way, the Contractor shall notify the respective authorities representing the Owners or agencies responsible for such facilities not less than 3-days nor more than 7-days prior to excavation so that a representative of said Owners or agencies can be present during such work if they so desire. The Contractor shall also contact 811 at least 2 business days, but no more than 14 days, prior to such excavation. PART 2 - PRODUCTS 2.01 MATERIALS, GENERAL A. Materials may be new or used, suitable for the intended purpose, but must not violate requirements of applicable codes and standards. 2.02 FENCING A. Materials to Contractor's option, fence height should match existing. 2.03 BARRIERS A. Materials to Contractor's option, as appropriate to serve required purpose. PART 3 - EXECUTION 3.01 GENERAL A. Install facilities of a neat and reasonable uniform appearance, structurally adequate for required purposes. B. Maintain barriers during entire construction period. 01561-5 C. Relocate barriers as required by progress of construction. 3.02 TREE AND PLANT PROTECTION A. Preserve and protect existing trees and plants adjacent to work areas. B. Consult with Owner's Representative and remove agreed-upon roots and branches which interfere with the Work: 1. Employ qualified tree surgeon to remove branches, and to treat cuts. C. Protect root zones of trees and plants: 1. Do not allow vehicular traffic and parking. 2. Do not store materials or products. 3. Prevent dumping of refuse or chemically injurious materials or liquids. 4. Prevent puddling or continuous running water. D. Carefully supervise all work to prevent damage. E. Replace trees and plants which are damaged or destroyed due to work operations under this contract. 3.03 REMOVAL A. Completely remove barricades, including foundations, when construction has progressed to the point that they are no longer needed, and when approved by Owner's representative. B. Clean and repair damage caused by installation, fill and grade areas of the site to required elevations and slopes, and clean the area. END OF SECTION 01561-6 SECTION 01570 TRAFFIC REGULATION PART 1 — GENERAL 1.01 REQUIREMENTS A. Provide, operate, and maintain equipment, services, and personnel with traffic controls and protective devices, as required to expedite vehicular traffic flow around the construction area in accordance with the Village of Tequesta, Palm Beach County and the approved traffic control plan. B. Remove temporary equipment and facilities when no longer required, restore grounds to original, or to specified conditions. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Village of Tequesta Engineering Standards 1.03 REFERENCES A. Traffic Control shall be in accordance with FDOT Roadway and Traffic Design Standards Series 600, Latest Edition, Manual on Uniform Traffic Control Devices, Latest Ed., and FDOT Standard Specifications, latest Ed. and the project permits. 1.04 TRAFFIC CONTROL PLAN A. The Contractor is to prepare a traffic control plan and/or policy statement for each phase of construction. This plan is to be presented to the Village of Tequesta and Palm Beach County, and other governing agencies, as applicable, at or before the pre-construction meeting. B. The Contractor shall prepare additional traffic control plans and/or policy statements for special events, and/or other unforeseen circumstances as needed. C. The following guidelines shall be used in developing the traffic control plans and/or policy statements- 1. The traffic control plan shall contain provisions for maintaining access to the residents and businesses throughout the project area. Roads should remain open to the greatest extent practical. 01570 - 1 Should blocks need to be closed, closure durations should be minimized and detour routes established. 1.05 SIGNS AND TRAFFIC SIGNALS A. Provide and operate traffic control and directional signals required to direct and maintain an orderly flow of traffic in all areas under Contractor's control, or affected by Contractor's operations. B. All existing traffic signs shall remain visible throughout construction activities unless superseded by required construction signing or as directed by the Owner. 1.06 FLAG PERSONS A. Provide qualified and suitably trained flag persons to regulate traffic when construction operations or traffic encroach on public traffic lanes. 1.07 FLARES, LIGHTS, AND DAY SHAPES A. Provide lights as required for implementation of the Traffic Control Plan, and- 1. To clearly delineate traffic lanes and to guide traffic as required. 2. For use by flagmen in directing traffic. B. Provide illumination of critical traffic and parking areas as required. Use flares and lights during hours of low visibility to delineate project limit. 1.08 CONSTRUCTION PARKING CONTROL A. Control vehicular parking to preclude interference with public traffic or parking, private property, business, access by emergency vehicles, or construction operations. B. Monitor parking of construction personnel's private vehicles. C. Prohibit parking on all major north-south roads, as well as those areas designated for public access. Parking is to also be prohibited adjacent to access roads or in non-designated areas such as permit only spaces and private driveways. 1.09 CONSTRUCTION VEHICLES A. All slow-moving construction vehicles shall have a slow moving sign visible from the rear of the vehicle. 01570 - 2 B. All vehicles used for construction activities shall have audible back-up warning devices. 1.10 ROAD CLOSURES A. No road shall be closed prior to receiving approval from the Village of Tequesta or Palm Beach County, depending on jurisdiction. B. At least fourteen (14) days prior to a proposed road closure, the Contractor shall submit to the applicable jurisdiction a complete traffic control plan. This plan shall include the following minimum information- 1. Sketch of work site and all area roads, streets and mark driveways. 2. Proposed detour route. 3. All necessary traffic control devices to be used. 4. Emergency Contractor contact person name and phone to be available 24 hours a day. 5. Estimated time/dates of road closure. C. The Contractor shall notify affected property owners and tenants (if applicable) at least 48 hours prior to a proposed driveway closing. PART 2 — PRODUCTS 2.01 SIGNAGE A. All traffic control devices shall meet or exceed FDOT certification standards. Post mounted traffic-control and informational signs shall conform with FDOT and MUTCD standards. B. All traffic signs shall have high intensity reflective face material. PART 3 — EXECUTION 3.01 GENERAL A. Upon notification by the Owner either verbally or in writing, the Contractor shall correct any noted MOT deficiencies within one hour. B. Inspection of all traffic control items shall be accomplished at least twice per day by the Contractor. One of these inspections shall be at the end of the workday or at night. C. Weekly updates shall be completed by the Contractor and provided to the Village of Tequesta and the Engineer. END OF SECTION 01570 - 3 This page has been intentionally left blank. 01570 -4 SECTION 01600 MATERIAL AND EQUIPMENT PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Products B. Workmanship C. Manufacturer's Instructions D. Transportation and Handling E. Storage and Protection F. Substitutions and Product Options 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections: 1. Section 01010: Summary of Work 2. Section 01090: Reference Standards 3. Section 01300: Submittals and Progress Schedules 4. Section 01740: Warranties and Bonds 1.03 PRODUCTS A. Products include materials, products, equipment and systems. B. Comply with specifications and referenced standards as minimum. C. DO NOT provide used materials and products, except as specifically allowed by notation or indication in Contract Documents. 01600 - 1 1.04 WORKMANSHIP A. Comply with industry standards except when more restrictive tolerances or specified requirements indicate more rigid standards or more precise workmanship. B. Perform work by persons qualified to produce workmanship of specified quality. C. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, and rocking. 1.05 MANUFACTURER'S INSTRUCTIONS A. When Work is specified to comply with manufacturer's printed instructions, obtain and distribute copies to persons involved, and maintain one set at job site in field office. B. Perform work in accordance with manufacturer's instructions and specified requirements. C. Should a conflict exist between Specifications and manufacturer's instructions, consult with Engineer. 1.06 TRANSPORTATION AND HANDLING A. Arrange deliveries of products in accordance with construction schedules; coordinate to avoid delay of progress, conflict with work and with conditions at the site. B. Transport products by methods to avoid product damage; deliver dry in an undamaged condition in manufacturer's unopened containers or packaging. C. Provide equipment and personnel to handle product by methods to prevent soiling or damage. D. Promptly inspect shipments to assure that products comply with requirements, quantities are correct and products are undamaged. 1.07 STORAGE AND PROTECTION A. Store products in accordance with manufacturer's instructions, with seals and labels intact and legible. 01600 - 2 B. Store sensitive products in weather-tight enclosures; maintain within temperatures and humidity ranges recommended/required by manufacturer's instructions. PVC pipe shall not be stored in a place where it can be exposed to ultraviolet light. C. For exterior storage of fabricated products, place on sloped supports above ground. Cover products subject to deterioration with impervious sheet covering; provide ventilation to avoid condensation. D. Store loose granular materials on solid surfaces in a well-drained area; prevent mixing with foreign matter. E. Arrange storage to provide access for inspection. Periodically inspect to assure products are undamaged, and are maintained under required conditions. F. After installation, provide coverings to protect products from damage of traffic and construction operations and remove when no longer needed. 1.08 PRODUCT OPTIONS A. Within 30 days after date of Contract, submit complete list of major products proposed, with name of manufacturer, trade name and model. B. Options- 1. Products specified only by reference standard: Any product meeting that standard. 2. Product specified by naming several manufacturers: Product of any named manufacturer meeting specifications. 3. Products specified by naming one or more manufacturers and "or equivalent": Submit a request for substitution for any manufacturer not specifically named. See bid documents for specific instructions regarding substitution requests. 1.09 SUBSTITUTIONS A. Substitutions will be considered during the bidding process. See the instructions to bidders for more information on how to propose a substitution. Subsequent to the bidding process, substitutions will be considered only when a product becomes unavailable due to no fault of the Contractor. B. Document each request with five sets (5) of complete data, drawings and samples as appropriate, substantiating compliance of proposed substitution with Contract Documents including: 01600 - 3 1. General information about the proposed substitution: a. For Products: 1) Product identification, including manufacturer's name and address. 2) Manufacturers' literature: a) Product description. b) Performance and test data. c) Reference standards. 3) Samples 4) Name and address of similar projects on which product was used, and date of installation. b. For construction methods: 1) Detailed description of proposed method. 2) Drawings illustrating methods. 2. Comparison of the qualities of the proposed substitution with the specified. 3. Changes required in other elements of the work because of the substitution. 4. Effect on the construction schedule. 5. Cost data comparing the proposed substitution with the product specified. 6. Any required license fees or royalties 7. Availability of maintenance service, and the source replacement materials. C. Request constitutes a representation that Contractor- 1. Has investigated proposed product and determined that it meets or exceeds, in all respects, specified product. 2. Will provide the same warranty for substitution as for specified product. 3. Will coordinate installation and make other changes which may be required for work to be complete in all respects. 4. Waives claims for additional costs which may subsequently become apparent. D. Substitutions will not be considered when they are indicated or implied on Shop Drawing or Product Data submittals without separate written request, or when acceptance will require significant revision of the Contract Documents. E. Engineer will review to determine acceptability of proposed substitution, and will notify Contractor of acceptance or rejection in writing within a reasonable time. 01600 -4 PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01600 - 5 This page intentionally left blank 01600 - 6 SECTION 01700 CONTRACT CLOSE-OUT PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01720: Project Record Drawings 2. Section 01730: Operating and Maintenance Manuals 3. Section 01740: Warranties and Bonds 1.02 SUBSTANTIAL COMPLETION A. When the Contractor considers his work is substantially complete, he shall submit to the Engineer: 1. A written notice that the Work, or designated portion thereof, is substantially complete. 2. A list of items to be completed or corrected. B. Within a reasonable time after receipt of such notice, the Engineer will review the Work to determine the status of completion. C. Should the Engineer determine that the Work is not substantially complete- 1. Engineer will promptly notify the Contractor, in writing, giving the reasons. 2. Contractor shall remedy the deficiencies in the Work, and shall send a second written notice of substantial completion to the Engineer 3. Engineer will re-review the Work D. When the Engineer concurs that the Work is substantially complete, he will- 1. Prepare a Certificate of Substantial Completion, accompanied by a list of items to be completed or corrected 01700 - 1 2. Submit the Certificate to Owner and Contractor for their written acceptance of the responsibilities assigned to them in the certificate. 1.03 FINAL INSPECTION A. When the Contractor considers the Work is complete, he shall submit written certification that: 1. Contract Documents have been reviewed 2. Work has been inspected for compliance with Contract Documents 3. Work has been completed in accordance with Contract Documents 4. Equipment and systems have been tested in the presence of the Owner's representative and are operational 5. Equipment and systems instructions to Owner's personnel have been completed in accordance with Section 01730 6. Work is completed and ready for final inspection B. The Engineer will review the Work to verify the status of completion with reasonable promptness after receipt of such certification. C. Should the Engineer consider that the Work is incomplete or defective- 1. Engineer will promptly notify the Contractor, in writing, listing the incomplete or defective work. 2. Contractor shall take immediate steps to remedy the stated deficiencies, and send a second written certification to Engineer that the work is complete. 3. Engineer will re-review the Work D. When the Engineer finds that the Work is acceptable under the Contract Documents, he shall request the Contractor to make close-out submittals. 1.04 RE-INSPECTION FEES A. Should the Engineer perform re-inspection due to failure of the Work to comply with the claims of status of completion made by the Contractor, the Contractor will compensate Engineer/Owner for such additional services. 1.05 ADDITIONAL SERVICES A. Should the Engineer be required to provide representation at the site for the administration of the Contract for Construction more than thirty days after the specified Date of Substantial Completion of the Work, the Contractor will compensate Engineer for such additional services. 01700 - 2 1.06 CONTRACTOR'S CLOSE-OUT SUBMITTALS TO ENGINEER A. Evidence of compliance with requirements of governing authorities. B. Project Record Documents: To requirements of Section 01720 and the General Conditions and Terms of the Contract. C. Warranties and Bonds: To requirements of Section 01740 and the General Conditions and Terms of the Contract. D. Evidence of Payment and Release of Liens: To requirements of the General Conditions and Terms of the Contract. E. Certificate of Insurance for Products and Completed Operations. F. One (1) Year Maintenance Bond G. Certificate of Operation from equipment manufacturers 1.07 FINAL ADJUSTMENT OF ACCOUNTS A. Submit a final statement of accounting to the Engineer. B. Statement shall reflect all adjustments to the Contract Sum- 1. The original Contract Sum 2. Additions and deductions resulting from: a. Previous change orders b. Allowances c. Unit prices d. Deductions for uncorrected work e. Deductions for liquidated damages f. Deductions for re-inspection payments g. Other adjustments 3. Total Contract sum, as adjusted 4. Previous payments 5. Sum remaining due C. The Engineer will prepare a final Change Order, reflecting approved adjustments to the Contract sum which were not previously made by Change Order. 01700 - 3 1.08 FINAL APPLICATION FOR PAYMENT A. Contractor shall submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contract. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01700 -4 SECTION 01720 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. The Contractor shall maintain at the site for the Owner one (1) record copy of the following- 1. Drawings 2. Specifications 3. Addenda 4. Change orders and other modifications to the Contract 5. Engineer field orders or written instructions 6. Approved shop drawings, product data, and samples 7. Field test records B. Drawings and general provisions of the Contract, including the General and Supplementary Conditions and Division 1 Specification sections, apply to this section. C. Village standards D. Specified in other Sections- 1. Section 01300: Submittals and Progress Schedules 2. Section 01700: Contract Close-out 1.02 MAINTENANCE OF DOCUMENTS AND SAMPLES A. The Contractor shall store documents and samples in the field office apart from documents used for construction. 1. Provide files and racks for storage of documents. 2. Provide locked cabinet or secure storage space for storage of samples. B. File documents and samples in accordance with Specifications — Table of Contents. C. Maintain documents in a clean, dry, legible condition and in good order. Do not use record documents for construction purposes. 01720 - 1 D. Make documents and samples available at all times for inspection by Engineer and Village. Record drawing information shall be maintained concurrently with Pay Requests. 1.03 MARKING DEVICES A. Provide felt tip marking pens for recording information in the color red. 1.04 RECORDING (SEE ALSO GENERAL CONDITIONS AND TERMS) A. The Contractor shall provide record drawings for all pay applications, partial releases and final release submittals. With each submittal provide survey data, signed and sealed by the Contractor's Surveyor, to support elevation information depicted on the record drawings. B. Label each document "PROJECT RECORD" in neat large printed letters. C. Record information concurrently with construction progress. DO NOT conceal or backfill any work until required information is recorded. D. Drawings-General: The Record Drawings shall correctly and accurately be drawn to record actual construction. Legibly mark to record actual construction- 1. Horizontal location of pipes and other improvements shall be provided any time the pipe passes a permanent surface reference point. Permanent surface reference points must be permanent structures manholes, catch basins, concrete sidewalk or concrete curbs. Edge of pavement and road intersections may not be used without the Engineer's approval. Any deviations from the alignment shown on the drawings must be noted. 2. Existing utilities that are not shown on the plans that are found in the field are to be noted and recorded on the record drawings. Actual locations of all utilities including water service and sanitary laterals shall be noted and recorded on the record drawings. a. Field changes of dimension and detail b. Drainage and Control Structure inverts and weir elevations. Roadway, sidewalk, planters, parking area, and site perimeter elevations C. Sanitary manhole rim and invert elevations d. Changes made by Work Change Directives or by Change Order e. Details not on original Contract Drawings f. Limits of work including temporary storage equipment area g. All information required by the Village Standards 01720 - 2 E. Drawings — General Requirements for Pressure Mains. Record Drawings shall legibly and accurately depict record of actual construction and showing the following, as a minimum: 1. Material used to construct mains 2. Location and top of pipe elevation of all fittings, including sleeves, and valves by stationing and offsets 3. Top of pipe elevation at every 50 feet and at every change of direction 4. Length of restrained pipe 5. All elevations and horizontal control of all storm sewer, gravity sewers including laterals, fittings and clean outs, electric cables, television cables, telephone cables, force mains and water mains which are crossed or exposed 6. Locations and elevations as required to define major horizontal/vertical pipe deflections/conflicts. Data shall include beginning and end of deflection/conflicts, all changes in elevations and alignment and the location and elevation of subject conflict item. 7. Location and elevation of all connections to existing systems 8. Locations and elevations as required to describe all other improvements F. Drawings — Specific Requirements for Pressure Mains 1. General - FOR ALL LAYERS: a. All references to "proposed" and "plan" are to be removed from the Final Record Drawings b. All lines, structures, and other items that are relocated will be removed and shown in the proper location (hand written notes and 'Y'ing out will not be allowed) C. All record drawings will be signed and sealed by Certified Land Surveyor or Professional Engineer licensed to practice in the State of Florida. If certified by a Surveyor, P.E. will sign off stating that the record drawings were checked by the Engineer, verifying that they inspected the work d. Clearly mark existing infrastructure which is to remain. e. Clearly mark existing infrastructure which has been abandoned, and how it was abandoned. f. Station, length, width and depth of flowable fill used. g. Record Drawings shall not be greater than 1" - 30' in scale h. All Detail sheets shall be included with each record drawing 01720 - 3 i. Location by station and elevation, width, depth and length of flowable fill used for all uses. j. Supply all surveys of the project and or property. 2. Water and Force Mains - TO BE SHOWN ON ONE LAYER: Water Utility Record Drawings shall conform with the requirements of the Village of Tequesta Utility Department. Records shall include locations (horizontal and vertical) of all pipe lines, structures, fittings, valves, and appurtenances and all water/utility crossings (including sanitary laterals) for proposed mains in accordance with Village and Palm Beach County Health Department requirements. Water main record drawings shall include at a minimum: a. Pressure class and material of proposed pipe b. Top of Pipe elevations and horizontal location every 100 feet C. Locations and elevation of all fittings including bends, tees, gate valves, double detector check valves, fire hydrants, etc. All tie-ins to existing lines shall be as-built d. Water meter locations (with stations/offsets) e. The ends of all proposed water service at the buildings or homes shall be as-built or where the water service terminates f. Limits of restrained joints on proposed and existing main g. Locations of joint deflections h. Thrust block locations and size 3. Sanitary Sewers - TO BE LOCATED ON THE SAME LAYER AS WATER AND FORCE MAINS a. Manhole rim elevation, invert elevations and directions. b. Length of run between sanitary structures, type of and size of pipe material with calculated percentage of slope for the run of pipe. C. Location of sanitary service wyes with station and offset, together with the invert elevation, station and offset, pipe diameter, lateral fittings, and material (clean-out). d. Locations and type of flexible eccentric coupling with station and offset, and adjoining pipe diameters and materials. e. Applicable lift station information should be filled out on the detail sheet for lift stations. 4. Water/Sanitary/Storm Pipe Crossings and Separations - PART OF WATER, SANITARY, AND/OR STORM LAYER 01720 -4 a. Pipe types, sizes and material b. Crossings: Top and bottom elevations of pipes crossing each other and the distance between the outside of the two lines C. Separation: Distance between the OD of the two lines 5. Conflict Storm/Water/Sanitary Structures - PART OF EACH APPLICABLE LAYER: a. Top and bottom of casing b. All info asked for in storm or sanitary manhole descriptions with the addition of top of all pipes 6. Casings - PART OF EACH APPLICABLE LAYER: a. Material and thickness b. Top of and invert of casing C. Length and station and offset of ends d. If used, station and offset for vent, including tap location, and fittings 7. Storm Sewers - TO BE LOCATED ON A SEPARATE LAYER: a. Manhole and catch basin rim elevation, outfalls and top of headwall invert elevations and direction, weir elevations, bottom of manholes and catch basins (sumps) b. Length of run between storm structures, type of and size of pipe material with calculated percentage of slope for the run of pipe C. Location of service connections (without manholes) together with the invert elevation, pipe diameter and material d. Dry retention, wet retention, dry detention, wet detention areas e. Exfiltration trenches, Station at beginning and end of system, width, depth f. Top of and toe of slope on berm elevation designed to stop flooding 8. Street Lights - TO BE LOCATED ON A SEPARATE LAYER: a. Manufacturer, model, and height of poles shall be shown on the record drawings 01720 - 5 b. Manufacturer, model, and wattage and voltage of lights shall be shown on the record drawings C. Pull boxes, station and offset d. Length of conduit runs between boxes and poles, type of, and size of pipe material. Show as laid in the ground, not as a wiring schematic, with amount, by color, type of, and size of wiring material e. Service connection, type (FP&L owned and metered) station and offset 9. Irrigation - TO BE LOCATED ON A SEPARATE LAYER: a. Backflow preventer, control stand location, control valve, zone, station and offset b. Main line piping size, material, lengths, depth C. Heads, Type (1/4, half, 3/4, full circle) zone, station and offset d. Control Stand, station and offset 10. Landscaping - TO BE LOCATED ON A SEPARATE LAYER: a. Tree type, caliper, and height b. Tree grate, size, and model C. Station, elevation, length, width, and depth of Structural Soil used d. Top of and toe of slope on berm elevation for landscaping 11. Private Construction Impacts to Right-of-Way - TO BE LOCATED ON A SEPARATE LAYER: a. Private utility or revocable easements in the Village or County's ROW or on Village property must be shown on the plan. Any improvements within the easement need to be shown and called out as private. The recording information should be on the as-built. b. Privately owned lighting, irrigation and landscaping in the Village or County right-of-way needs to be called out as private and identified. C. All aerial and underground footer easements (in ROW) G. Specifications and Addenda: Legibly mark each section to record- 1. Manufacturer, trade name, catalog number and supplier of each product and item of equipment actually installed 2. Changes made by field order or by Change Order 01720 - 6 H. Photographs- 1. Manufacturer, trade name, catalog number and supplier of each product and item of equipment actually installed 2. Changes made by field order or by Change Order 1.05 SUBMITTAL A. Record drawings shall be submitted to the Engineer with pay applications, and partial and final releases per Village standards. If no Village standards exist, utilize the following formats- 1. All incoming as-built survey AutoCAD drawing files shall be received on CD-ROM in a jewel case and in state plane coordinates. The disk label shall include the following: a. Engineering and/or Survey Company Name with prepared by statement b. Project Name C. Village of Tequesta Project Number d. Date the data is burned onto disk e. Designate "Record Drawings", "Preliminary Record Drawings", or "Final Record Drawings" 2. Four (4) - 24" by 36" hard copies, signed and sealed 3. An electronic PDF of the record drawing 4. AutoCAD Files must be submitted in DWG format, latest AutoCAD version 5. Each file should be for one section of development and one layer as described in 1.04. Multiple sections will not be accepted in one file. 6. Tie into section corners in the Florida State Plane Coordinate System to insure proper orientation at each end of baseline. Section corner tie sheets can be obtained from the Palm Beach County Surveyor's web page. B. At Contract close-out, deliver Record Documents to Engineer for the Owner. C. Accompany submittal with transmittal letter in duplicate, containing- 1. Date 2. Project title and number 3. Contractor's name and address 4. Title and number of each Record Document 5. Signature of Contractor or his authorized representative 01720 - 7 1.06 AS-BUILT SURVEYS A. CONTROL INFORMATION FOR AS-BUILT UTILITY SURVEY WORK 1. All as-built drawings shall state in 1" lettering "AS-BUILT RECORD SURVEY' located in the bottom right hand side of the drawing original and/or copies, along with the as-built date 2. All as-built surveys shall meet the minimum requirements of the Chapter 61G17, Florida Administrative Code Pursuant to Section 472 of the Florida Statutes. All surveys shall be based on a minimum horizontal control Third Order, "Class 2." 3. All state plane coordinates shall be based on the Florida State Plane Horizontal Data (East Zone); Florida High Precision Geodetic Network (Superstation) and NAD 83/1990 — final adjustment. 4. State plane coordinates shall be physically tied to a minimum of two known state plane coordinate benchmarks that utilize number 3 above. State plane coordinates shall be shown on survey at benchmarks used. 5. The Contractor shall provide the Engineer and Owner with record drawings in NAVD 1988 6. All record data shall be digitally positioned on the design drawings prepared by the engineer of record. Said design drawings shall be complete and include both plan and profile views of the infrastructure. 7. All as-builts shall clearly depict as-built utility lines that were constructed along with all easements 8. All as-builts shall include the information required by the Village Standards PART 2 — PRODUCTS NOT USED PART 3 — EXECUTION NOT USED END OF SECTION 01720 - 8 SECTION 01730 OPERATION AND MAINTENANCE MANUALS PART 1 — GENERAL 1.01 RELATED INFORMATION A. Compile product data and related information appropriate for Owner's maintenance and operation of products furnished under the Contract. 1. Prepare operating and maintenance data as specified in this Section and as referenced in other pertinent sections of Specifications. B. Instruct Owner's personnel in the maintenance of products and in the operation of equipment and systems. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01300: Submittals and Progress Schedules 2. Section 01720: Project Record Drawings 1.03 FORM OF SUBMITTALS A. Prepare data in the form of an instructional manual and electronic format for use by Owner's personnel. B. Hard-Copy Format- 1. Size: 8-1/2 in. x 11 in. 2. Text: Manufacturer's printed data, or neatly typewritten. 3. Drawings: a. Provide reinforced punch binder tab, bind in with text. b. Fold larger drawings to the size of the text pages. 4. Provide fly-leaf for each separate product, or each piece of operating equipment. 01730-1 a. Provide typed description of product, and major component parts of equipment. 5. Cover: Identify each volume with typed or printed title "OPERATING AND MAINTENANCE INSTRUCTIONS". List: a. Title of Project. b. Identity of separate structure as applicable. C. Identity of general subject matter covered in the manual. C. Binders- 1. Commercial quality expandable catalog binders with durable and cleanable plastic covers. 2. When multiple binders are used, correlate the data into related consistent groupings. D. Electronic format shall be in .pdf file format. Copies of specific manuals shall either be scanned or converted to .pdf format and submitted on CD disc to Owner. Submit after approval of hard copies. 1.04 CONTENT OF MANUAL A. Neatly typewritten table of contents for each volume, arranged in a systematic order. 1. Contractor, name of responsible principal, address and telephone number. 2. A list of each product required to be included, indexed to the content of the volume. 3. List, with each product, the name, address and telephone number of: a. Subcontractor or installer. b. Maintenance contractor, as appropriate. C. Identify the area of responsibility of each. d. Local source of supply for parts and replacement. 4. Identify each product by product name and other identifying symbols as set forth in Contract Documents. B. Product Data- 1. Include only those sheets which are pertinent to the specific product. 2. Annotate each sheet to: a. Clearly identify the specific product or part installed. 01730-2 b. Clearly identify the data applicable to the installation. C. Delete references to inapplicable information. C. Drawings- 1. Supplement product data with drawings as necessary to clearly illustrate relations of component parts of equipment and systems. 2. Coordinate drawings with information in Project Record Documents to assure correct illustration of completed installation. 3. Do not use Project Record Documents as maintenance drawings. D. Written text, as required to supplement product data for the particular installation- 1. Organize in a consistent format under separate headings for different procedures. 2. Provide a logical sequence of instructions for each procedure. E. Copy of each warranty issued. 1. Provide information sheet for Owner's personnel, give: a. Proper procedures in the event of failure. b. Instances which might effect the validity of warranties. 1.05 MANUAL FOR EQUIPMENT AND SYSTEMS A. Submit three (3) complete copies of manual in final form. B. Content, for each unit of equipment and system, as appropriate- 1. Description of unit and component parts. a. Function, normal operating characteristics, and limiting conditions. b. Performance curves, engineering data and tests. C. Complete nomenclature and commercial number of all replaceable parts. 2. Operating procedures: a. Start-up, break-in, routine and normal operating instructions. b. Regulation, control, stopping, shut-down and emergency instructions. C. Summer and winter operating instructions. 01730-3 d. Alignment, adjusting and checking. 3. Servicing and lubrication schedule: a. List of lubricants required for each piece of equipment. b. Schedule for manufacturer recommended maintenance. 4. Manufacturer's printed operating and maintenance instructions. 5. Original manufacturer's parts list, illustrations, assembly drawings and diagrams required for maintenance. 6. Manufacturer's written warranties for parts and labor. 7. Other data as required under pertinent sections of specifications. 1.06 SUBMITTAL SCHEDULE A. Submit one copy of completed data in final form fifteen days prior to final inspection or acceptance. 1. Copy will be returned after final inspection or acceptance, with comments. B. Submit specified number of copies of approved data in final form 10 days after final inspection or acceptance. 1.07 INSTRUCTION OF OWNER'S PERSONNEL A. Prior to final inspection or acceptance, fully instruct Owner's designated operating and maintenance personnel in the operation, adjustment and maintenance of all products, equipment and systems. B. Operating and maintenance manual shall constitute the basis of instruction. 1. Review contents of manual with personnel in full detail to explain all aspects of operations and maintenance. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01730-4 SECTION 01740 WARRANTIES AND BONDS PART 1 - GENERAL 1.01 REQUIREMENTS INCLUDED A. Compile specified warranties and bonds. B. Compile specified service and maintenance contracts. C. Co-execute submittal when so specified. D. Review submittals to verify compliance with Contract Documents. E. Submit to Engineer for review and transmittal to Owner. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01700: Contract Close-Out C. Each respective section of Specifications shall have Warranties and Bonds required for specific products. D. Provisions of Warranties and Bonds, Duration: The respective section of specification which specifies the product. 1.03 SUBMITTAL REQUIREMENTS A. Assemble warranties, bonds and service and maintenance contracts, executed by each of the respective manufacturers, suppliers and subcontractors. B. Table of Contents: Neatly typed, in orderly sequence. Provide complete information for each item. 1. Product or work item. 2. Firm, with name of principal, address, and telephone number. 3. Scope. 01740 - 1 4. Date of beginning of warranty, bond or service and maintenance contract. 5. Duration of warranty, bond or service maintenance contract. 6. Provide information for Owner's personnel: a. Proper procedure in case of failure b. Instances which might affect the validity of warranty bonds. 7. Contractor, name of responsible principal, address and telephone number. 1.04 FORM OF SUBMITTALS A. Prepare in duplicate packets. B. Format- 1. Size 8-1/2" X 11" punched sheets for 3-ring binder a. Fold larger sheets to fit into binders 2. Cover: Identify each packet with typed or printed title "WARRANTIES AND BONDS." List: a. Title of project b. Name of Contractor C. Binders: Commercial quality, three-ring, with durable and cleanable plastic cover. D. Provide one electronic copy of warranties, bonds, and service maintenance contract on CD-ROM as PDF files. 1.05 TIME OF SUBMITTALS A. Make submittals within ten days after Date of Substantial Completion, prior to final request for payment. B. For items of work, where acceptance is delayed materially beyond the Date of Substantial Completion, provide updated submittal within ten days after acceptance, listing the date of acceptance as the start of the warranty period. 01740 - 2 1.06 SUBMITTALS REQUIRED A. Submit warranties, bonds, and service and maintenance contracts as specified in the respective sections of Specifications, as appropriate. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 01740 - 3 This page intentionally left blank 01740 - 4 SECTION 02016 EXISTING UTILITIES AND UNDERGROUND STRUCTURES PART 1 — GENERAL 1.01 GENERAL A. The plans depict the approximate location of the existing utilities. The locations of those facilities (horizontal and vertical) were obtained from survey information, Utility Atlas and Record Drawings provided by the applicable Utility Owners, and a limited amount of utility soft dig information (Appendix C). B. Existing utilities shown are located according to the information available to the Engineer at the time of the topographic survey. Guarantee is not made that all existing underground utilities are shown or that the location of those shown are entirely accurate. Finding the actual location of any existing utilities is the Contractor's responsibility and shall be done before he commences Work in the vicinity. Furthermore, the Contractor shall be fully responsible for any and all damages due to the Contractor's failure to exactly locate and preserve any and all underground utilities. 1.02 CONTRACTOR'S RESPONSIBILITIES A. Contractor shall notify the Sunshine State One Call of Florida (SSOCF) service at 811, 48-hours prior to digging for direct bury, as required by Florida Statues Chapter 556 throughout the duration of the construction project. B. Locate the cables, ducts, conduit, pipeline, etc. in advance of the proposed construction. C. Notify the Engineer of any substantial changes and/or conflicts that would require a deviation in the plans. Late discovery of existing underground utilities does not constitute "required" deviations should early discovery prevent them. D. Repair any damage done to existing utilities at no additional expense to the Owner. E. Remove or modify those utilities scheduled to be removed or modified on the plans. F. All asbestos cement pipe that is not abandoned in place shall be removed and disposed of off-site in a legal manner. 02016-1 G. Provide support of existing utilities that are to remain and be protected while uncovered during installation of the new improvements or removal of existing items required to be removed. 1.03 PRECONSTRUCTION VIDEO A. At least one (1) week prior to the start of construction, the Contractor shall have video recordings taken of the entire project area. This area includes but is not limited to, the entire length of the utility work, and all locations where work may occur on or near private property, including for residences where meter relocations are to occur. Such recordings shall be provided to the Owner and Engineer before the commencement of construction. These recordings shall serve as record of the conditions as they existed priorto the start of the work. They will be used in the event of a dispute that arises from restoration or damage claims from property owners along the project corridor. The Contractor shall pay particular attention to existing damage on public and private property near the work area and ensure that these items are documented on the video. B. Video shall be limited to one video per street or a maximum of 2,000 linear feet of roadway per file. C. Label and catalog by street name and beginning and ending intersections. D. Video files are to be submitted to the Owner and Engineer on a DVD in a standard video format that is able to be viewed on a Windows operating system. All video files shall become the property of the Owner. PART 2 — PRODUCTS NOT USED PART 3 — EXECUTION NOT USED END OF SECTION 02016-2 SECTION 02065 DEMOLITION PART 1 - GENERAL 1.01 SCOPE OF WORK A. ON — SITE DEMOLITION 1. The Contractor shall furnish all supervised labor, materials, equipment, and incidentals required for the removal of all items necessary to be removed in order to construct the project as shown on and in accordance with the plans and specifications. B. REMOVAL PROCEDURES 1. Perform complete or partial removal and disposal of specified existing debris, vegetation, asphalt, concrete, piping, structures, landscaping, mechanical equipment, electrical equipment and miscellaneous items and appurtenances encountered during construction operations. 2. Perform temporary modification of structures, equipment, appurtenances and utilities as necessary to allow for operation of the facilities during construction. 3. Perform demolition, partial removal and cutting of existing asphalt, concrete, piping, structures, and appurtenances as required for the new construction. 4. Handle existing equipment to be reinstalled or salvageable as specified. 5. Perform off-site disposal of excess and unacceptable materials including but not limited to asphalt, concrete, concrete blocks, bricks, steel, PVC, AC pipe, DI pipe, Cl pipe, fuel, waste oil, metal, debris, etc. All materials shall be disposed of off-site in a legal manner. 6. This section may not cover all of the activities necessary to perform the Work. The Contractor shall exercise due concern for the utility system operation and shall diligently direct all of the Contractor's activities toward maintaining continuous operation of the existing facilities and minimizing operation impacts. 02065-1 1.02 RULES AND REGULATIONS A. The Building Code of the State of Florida shall control the demolition, modification or alteration of the existing site. B. No blasting shall be done on-site. C. Refer to the Village of Tequesta Code of Ordinances and the project permits for additional requirements. 1.03 ACCESS A. Conduct demolition and modification operations, and the removal of equipment and debris to ensure minimum interference with roads and walks both on-site and off-site and to ensure minimum interference with occupied or used facilities. B. Special attention is directed towards maintaining safe and convenient access to the existing facilities. C. Do not close or obstruct streets, walks or other occupied or used facilities without permission from the Owner. Provide alternate routes around closed or obstructed traffic in access ways. 1.04 PROTECTION A. The Contractor shall conduct construction activities to minimize damage to adjacent buildings, structures, roadways, utilities, storm drainage, and other facilities, including persons. B. Provide support to existing utilities and other improvements as required to install the new improvements. 1.05 DAMAGE A. The Contractor shall immediately report damage caused to adjacent facilities by demolition operations. The Contractor shall promptly make all required repairs as directed by the Engineer and at no cost to the Owner. 1.06 UTILITIES A. It shall be the Contractor's responsibility to maintain existing utilities in service and protect against damage during demolition operations 02065-2 1.07 POLLUTION CONTROL A. For pollution control, use sprinkling, temporary enclosures, and other suitable methods as necessary to limit the amount of dust and dirt rising and scattering in the air to the lowest level of air pollution practical for the conditions of work. Comply with the governing regulations. B. Clean adjacent structures and improvements of all dust, dirt, and debris caused by demolition operations. Return areas to conditions existing prior to the start of work. C. Pollution control measures outlined in the Stormwater Pollution Prevention Plan shall be implemented during the entire construction timeline to control turbidity and sediment discharges to the stormwater system. D. The Contractor shall provide for any required water quality monitoring programs as may be outlined in the SFWMD Dewatering Permit. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED END OF SECTION 02065-3 This page intentionally left blank. 02065-4 SECTION 02110 CLEARING AND GRUBBING PART 1 -GENERAL 1.01 SCOPE A. The Work to be performed under this item shall consist of either the clearing of or the clearing and grubbing of the area of construction as designated on the drawings. B. Clearing - Where clearing only is required, it shall consist of the cutting and removal of all trees, stumps, brush, logs, hedges, and the removal of all fences, concrete, debris, asphalt, and other loose or projecting material from the designated area. The grubbing of stumps and roots will be required. C. Clearing and Grubbing - Clearing and grubbing shall consist of clearing the surface of the ground of the designated areas of all trees, stumps, down timber, logs, snags, brush, undergrowth, hedges, heavy growth of grass or weeds, fences, structures, debris, and rubbish of any nature, natural obstructions or such material which, in the opinion of the Engineer, is unsuitable, including grubbing of stumps, roots, matter roots, foundations and disposal from the project of all spoil materials resulting from clearing and grubbing by burning or otherwise. 1.02 REFERENCES A. Florida Department of Transportation Standard Specifications for Road and Bridge construction (FDOT), latest edition. PART 2 - MATERIALS 2.01 MATERIALS FOR REPLACEMENT A. All materials required to be brought on to the site for filling of holes caused by grubbing or otherwise shall be as specified in Section 02200 — Earthwork, Excavation and Backfill. 02110-1 PART 3 - EXECUTION 3.01 SCHEDULE A. The Contractor shall schedule the clearing or clearing and grubbing work at a satisfactory time in advance of the project improvement construction operation. 3.02 SPOIL MATERIALS REMOVAL A. All materials to be disposed of by removal from the site shall be disposed of off-site in a legal manner by the Contractor at the Contractor's expense. The manner and location of disposal of materials shall be subject to review by the Engineer and shall not create an unsightly or objectionable view. 3.03 CLEARING A. Clear the area of all objectionable materials. Trees and other debris unavoidably falling outside the specified limits must be cut up, removed, and disposed of in a satisfactory manner. Preserve and protect from injury all trees not to be removed. The trees, stumps, and brush shall be cut to a height of not more than 12-inches above the ground. The grubbing of stumps and roots will be required. B. On-site burning of debris will not be allowed. 3.04 CLEARING AND GRUBBING A. In areas designated to be cleared and grubbed, all stumps, roots, buried logs, brush, grass and other unsatisfactory materials shall be removed. B. All holes remaining after the grubbing operation in embankment areas shall have the sides broken down to flatten out the slopes, and shall be filled with acceptable material, moistened and properly compacted in layers to the density required in Section 02200. The same construction procedure shall be applied to all holes remaining after grubbing in excavation areas where the depth of holes exceeds the depth of the proposed excavation. END OF SECTION 02110-2 SECTION 02150 DEWATERING PART 1 — GENERAL 1.01 SECTION INCLUDES A. The Work covered by this Section consists of furnishing all permits, labor, equipment, appliance and materials, and performing all operations required for dewatering all excavations, if required, complete. 1.02 RELATED SECTIONS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01060: Regulatory Requirements and Notifications 2. Section 02200: Earthwork, Excavation, and Backfill. PART 2 - PRODUCTS 2.01 TEMPORARY FACILITIES A. All materials and equipment shall be suitable and adequate to function continuously as a dewatering system. B. All material and equipment used in the dewatering system remain the property of the Contractor and shall be removed off-site when dewatering is completed. C. All dewatering equipment shall conform with the noise standards set forth in the Village of Tequesta Code of Ordinances. 2.02 SUBMITTALS A. Submit the dewatering method or plan in accordance with Submittal specifications prior to commencing dewatering if it is determined by the Contractor that dewatering beyond that allowed by a no-notice dewatering permit is required to construct the project. 02150-1 B. The Contractor shall prepare and submit the necessary permit applications and supporting documents for the purposes of obtaining a dewatering permit from the SFWMD and any other required agencies. PART 3 - EXECUTION 3.01 METHODS A. The method of dewatering is to be selected by the Contractor and may include- 1. Wellpoints 2. Sump pumps 3. Bedding rock 4. Dewatering wells 5. Other approved items 3.02 DISCHARGE A. The Contractor shall provide all labor, materials, tools and equipment necessary to properly control the quality of the discharge from his dewatering operations as described herein. The Contractor shall comply with all applicable laws, rules and regulations governing the discharge of water from his dewatering operations. B. The Contractor shall not discharge water in any manner that will- 1. Adversely affect water quality of nearby water bodies 2. Violate Federal, State or local laws or regulations 3. Allow discharge to flow onto private property 4. Deter movement of traffic 5. Damage portions of the work previously constructed 6. Damage portions of existing facilities or structures 7. Violate the conditions of the SFWMD Dewatering Permit 8. Violate the conditions of the Stormwater Pollution Prevention Plan C. The Contractor shall obtain and pay for any permits required to discharge the dewatering waters. D. The Contractor shall coordinate and pay for any water quality monitoring program that may be required by the applicable dewatering permit(s). END OF SECTION 02150-2 SECTION 02200 EARTHWORK, EXCAVATION, AND BACKFILL PART 1 - GENERAL 1.01 SECTION INCLUDES The Work covered by this section consists of furnishing all labor, equipment, and materials, and performing all earthwork operations to include: A. Excavation and backfill of structures, foundations, and pavements B. Surface preparation for structures, foundations, and pavements C. Excavation and backfill of pipe trenches D. Roadway area grading E. Soil compaction and stabilization requirements for pipe trenches and roadway areas F. Soil testing for pipe trenches and parking areas 1.02 REFERENCES A. Florida Department of Transportation Standard Specifications for Road and Bridge Construction, Latest Edition. B. American Society for Testing and Materials (ASTM) D698 Moisture-Density Relationship of Soils D1556 Standard Method of Test for Density of Soil in Place by Sand Cone Method D1557 Method for Test for Moisture-Density Relations of Soils Using a 10-Pound Rammer and 18-Inch Drop D2487 Classification of Soils for Engineering Purposes D6938 Density of Soil and Soil-Aggregate in Place by Nuclear Methods 02200 - 1 1.03 RELATED SECTIONS SPECIFIED ELSEWHERE A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01410: Testing Laboratory Services 2. Section 02016: Existing Utilities and Underground Structures 3. Section 02150: Dewatering 4. Section 02660: Pressure Pipe Systems C. Village of Tequesta Engineering Standards 1.04 FIELD MEASUREMENTS AND COORDINATION A. Verify that survey benchmark, control point, and intended elevations for the work are as shown on the Drawings. B. Verify that work associated with lower elevation utilities is complete before placing higher elevation utilities. 1.05 SUBSURFACE SOILS DATA A. The Owner and Engineer make no representations or statements as to site or soil conditions, and therefore do not assume any responsibility for actual site or soil conditions. PART 2 - PRODUCTS 2.01 EXCAVATION A. All excavation is unclassified. Complete all excavation regardless of the type, nature, or condition of the materials encountered. 2.02 SOURCE QUALITY CONTROL A. If tests fora material type fail three times, the Engineer may reject the source supplier and require the Contractor to submit a new source for approval, at no additional cost to the Owner. The in-situ material is considered acceptable material and may be used, provided it meets the specified requirements. 02200 - 2 B. Quality control of the work shall be the Contractor's responsibility and the Contractor shall make every effort to produce the best quality work as specified on the Drawings and in these Specifications. 2.03 STRUCTURAL FILL AND BACKFILL A. Fill and backfill under and around all structures shall be suitable on-site excavated material or approved imported material. Material shall be free of organic material, shall not have more than 10 percent by dry weight passing the U.S. Standard No. 200 sieve, and shall have no rocks larger than 3- inches in size. On-site Fine Sand (SP), without roots or other deleterious materials, is suitable material. Imported material may be provided by the Contractor at no additional cost to the Owner. B. On-site soils with more than 10% by dry weight passing the U.S. Standard No. 200 sieve and/or particle sizes larger than 3-inches are not suitable for use as fill under pavements or structures. C. Backfill behind walls shall be as specified above except that they shall not have more than 4% by dry weight passing the U.S. Standard No. 200 sieve. 2.04 EARTHFILL A. On-site excavated material free from roots, trash, and rocks larger than 3- inches. 2.05 FLOWABLE FILL A. Provide and place flowable fill in accordance with the requirements of Section 121 of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, Latest Edition. 2.06 WATER FOR COMPACTION A. The Contractor shall furnish potable water, as required. The Contractor may coordinate with the Village of Tequesta Engineering Department to arrange for a hydrant meter for water during construction. Costs associated with the hydrant meter shall be paid for by the Contractor. Water trucks shall be used as required. 2.07 EQUIPMENT A. All equipment shall be suitable and adequate to perform the Work specified. Compaction equipment shall be vibratory type. It is recommended that the Contractor perform a pre-construction assessment of existing adjacent 02200 - 3 structures and monitor those structures for settlement during the construction period. Contractor shall notify Owner of any settlements that occur at existing adjacent structures. PART 3 — EXECUTION 3.01 PREPARATION A. Identify required lines, levels, contours, and datum locations. Protect bench marks, survey control points, sidewalks, paving, and curbs from excavating equipment and vehicular traffic. B. Locate, identify, and protect utilities that remain from damage. 3.02 STRIPPING TOPSOIL A. See Section 02110, Clearing and Grubbing. Stripping of topsoil shall be performed prior to any cutting, excavation, removal and/or replacement or fill materials. B. Strip topsoil from designated areas within boundaries of proposed construction lines to a depth of approximately 6-inches to 8.5-inches. The top materials stripped shall be removed and disposed of off site, unless authorized for use on the site landscaping areas by the Engineer or Owner. Top materials shall not be used under roadway or parking areas. C. Stripping of topsoil shall ensure the entire site is stripped and scraped clean of all brush, weeds, grass, roots, vegetation, etc. 3.03 CUTTING A. Except as otherwise specified, after stripping of topsoil all site areas which are above elevation required shall be cut to subgrades required by drawings. 3.04 FILLING A. Except as otherwise specified, after stripping of topsoil all site areas which are below elevation required shall be compacted as specified and then over such areas clean granular fill placed and compacted in layers not exceeding 6-inches in un-compacted thickness. Each layer of fill shall be compacted to at least 95% of the modified proctor maximum dry density required on the construction drawings (ASTM D1557 or AASHTO T-180). Filling and compaction shall continue until subgrades required for various areas are reached. All holes and depressions caused from removal of trees, stumps, 02200 - 4 etc. shall be filled and compacted. Fill shall be good clean material as previously specified. 3.05 EXCAVATION UNDER STRUCTURES AND PAVEMENT AREAS A. Excavation shall be performed to elevations and dimensions required by drawings with suitable allowance made for construction operations and inspections. Excavation carried to depths below required elevations shall be replaced in loose layers a maximum of 6-inches in depth and compacted in a manner to achieve a minimum density of 98% as determined by and in accordance with the modified proctor required on the construction drawings (ASTM D-1557 or AASHTO T-180). The Contractor may place additional concrete in lieu of replacing and compacting excess excavation as specified above to fill excess cut. Correction of excess cut shall be responsibility of the Contractor at no additional cost to the Owner. B. Compact disturbed load bearing soil in direct contact with foundations to achieve a minimum density of 98% as determined by and in accordance with modified proctor required on the construction drawings (ASTM D-1557 or AASHTO T-180). C. Verify that the specified density extends to 2-feet below the bottom of the structure or pavement base course to be installed. D. Slope banks with machine to angle of repose or provide necessary shoring. E. Do not interfere with 45 degree bearing splay of existing foundations without providing adequate means of shoring protection. F. Grade top perimeter of excavating to prevent surface water from draining into excavation. G. Notify the Engineer of unexpected subsurface conditions and discontinue affected work in area until notified to resume work. H. Correct areas over excavated in accordance with this section. I. Remove excavated material unsuitable for backfill from site. J. When muck or other deleterious materials is encountered in the excavation, it shall be completely removed within the area of the structure or pavement and to a depth where acceptable material is encountered. After removal of all muck or other deleterious material, the area shall be backfilled with approved fill material to the specified grade. 02200 - 5 3.06 TRENCH EXCAVATION AND PREPARATION A. Excavation: Excavate as required for the installation of all piping, utilities, conduits, and appurtenances. B. Trench Width: Cut trenches sufficiently wide to enable installation, compaction and inspection. The maximum width will not be limited except where excessive trench width would cause damage to adjacent structures or piping. C. Grade: Excavate the bottom of the trench to the line and grade shown, or as established by the Engineer with proper allowance for pipe bedding. D. All trench work shall comply with OSHA Standards and the Trench Safety Act of 1990, with latest revisions. E. Piping shall be installed in a dry trench. F. When acceptable material is encountered in the trench, the bottom shall be excavated and graded to the depth required so as to provide a uniform and continuous bearing and support for the pipe on solid and undisturbed ground at every point between bell holes. G. Bell holes shall be provided at each joint to permit the joint to be made properly. At no time shall the bells support the pipe when in the trench. H. When muck or other deleterious materials is encountered in the trench, it shall be completely removed for the width of the trench at the pipe and to a depth where acceptable material is encountered. After removal of all muck or other deleterious material, the trench shall be backfilled with bedding material to the bottom of pipe grade. I. See the Village of Tequesta for additional requirements. 3.07 MAINTENANCE OF EXCAVATION A. The excavation shall be maintained at a dry condition at all times. B. All side slopes shall be such that material will not slide into the bottom of the excavation and any material doing so shall be immediately removed. Trench side slopes shall be in accordance with local codes, OSHA requirements, and the Trench Safety Act. C. All excavated material shall be piled in a manner that will not endanger the work and that will avoid obstructing sidewalks and driveways. Hydrants under pressure, valve pit covers, valve boxes, curb stop boxes, fire and police call boxes, or other utility controls shall be left unobstructed and 02200 - 6 accessible until the work is completed. D. Trees, shrubbery, fences, poles, bollards and all other property and surface structures shall be protected unless their removal is shown on the drawings or authorized by the Engineer. When it is necessary to cut roots and tree branches, such cutting shall be done under the supervision and direction of the Engineer. E. The attention of the Contractor is drawn to the fact that during excavation at the project site, the possibility exists of the Contractor encountering various utilities (water, chemical, electrical, gas, or other) not shown on the drawings. The Contractor shall exercise extreme care before and during excavation to locate and flag these lines so as to avoid damage to the existing lines. Should damage occur to an existing line, the Contractor shall repair the line at no cost to the Owner. F. It is the responsibility of the Contractor to ensure that all utility or other poles, the stability of which may be endangered by the close proximity of excavation, are temporarily stayed in position while the Work proceeds in the vicinity of the pole and that the utility or other companies concerned be given reasonable advance notice of any such excavation by the Contractor. 3.08 BACKFILL UNDER STRUCTURES AND PAVEMENT AREAS A. Backfilling of excavated areas under, around or over building and structural appurtenances and pavement, concrete or pavers shall be performed with clean fill materials which are free of debris, organics, trash or other deleterious substances. Suitable compaction equipment shall be used to obtain density described previously for the entire depth of backfilling. Each layer of backfill under structures, pavements, and pavers shall be compacted to a minimum of 98%as determined by and in accordance with the modified proctor required on the construction drawings (ASTM D-1557 or AASHTO T-180). Each layer of compacted backfill shall not exceed 6-inches in thickness. The completed, compacted surface shall be at the proper final subgrade elevation. B. Verify that the specified density extends to 18-inches below the bottom of the structure or pavement base course to be installed. 3.09 TRENCH BACKFILLING A. Haunch Backfill: Carefully place pipe bedding material so as not to damage the pipe in maximum 6-inch loose lifts and compact to the pipe centerline. Use hand-held compaction equipment. B. Pipe Zone: Backfill with pipe bedding material in maximum 6-inch loose lifts and 02200 - 7 compact to a point at a minimum of 12-inches above the pipe crown or in accordance with Palm Beach County standard detail, whichever is greater. C. Under Pavement/Concrete/Paver Areas, and Structures: In areas where backfill settlement must be held to a minimum, backfill above the pipe zone with pipe bedding material in maximum 6-inch loose lifts and compact to a minimum 98% maximum dry density as determined by and in accordance with the modified proctor required on the construction drawings (ASTM D-1557 orAASHTO T- 180) up to the subgrade elevation. Backfilling and compaction within the MOT Rights of Way shall be in accordance with the MOT Standard Specifications for Road and Bridge Construction, latest edition. D. Outside Pavement/Concrete/PaverAreas- In areas where backfill settlement is not critical, backfill above the pipe zone with earthfill material to a density equal to or greater than the soil adjacent to the pipe trench, but not less than 95% of the maximum dry density as determined by and in accordance with the modified proctor required on the construction drawings (ASTM D-1557 or AASHTO T-180), to final grade. E. No material shall be used for backfill which contains muck or other deleterious material or material with an excessive void content. All backfill shall be composed of select clean granular material. F. All trenches and excavation shall be backfilled immediately after all pipe and joints have been investigated and approved by the Engineer or the Village, subject to satisfactory pressure and leakage test results, as required. G. Backfill, in general, shall be kept up with the rate of pipe laying. No more than 100 feet of pipe trench shall be open at one time at any one project location. H. See the Village of Tequesta Standards for additional requirements. 3.10 BACKFILL AROUND STRUCTURES A. Obtain the Engineer's acceptance of concrete work and attained concrete strength prior to backfilling. B. Backfill with structural backfill material placed in maximum 6-inch loose lifts and compacted to a minimum 98% of maximum dry density as determined by and in accordance with the modified proctor required on the construction drawings (ASTM D-1557 or AASHTO T-180). C. Compact backfill adjacent to structures with equipment that will not damage the structure. 02200 - 8 D. Backfill with flowable fill or other material only if reviewed and approved by the Engineer. 3.11 SITE GRADING A. Fill and contour site areas with earthfill material to elevations shown and as required to prepare the site for landscape grading and sodding. B. Place materials in maximum 6-inch loose lifts and compact as required to limit subsequent settlement. 3.12 COMPACTION TESTING A. In-situ compaction testing shall be performed by a certified laboratory. B. Compaction testing shall be done by nuclear density equipment or other approved methods. (ASTM D-2937, D-1557, D-6938, AASHTO T-180, AASHTO T-90). C. Density testing shall be performed as follows- 1. Pipe Trenches: 1 test per lift per 100-feet of pipe. 2. Fill Under/Around Structures: 1 test per lift under each structure or 1 backfill test per lift per drainage or sanitary structure installed. 3. Fill Under Pavement Areas: 1 test per lift per 2,000 square feet of compacted surface area. D. Test results in a specific location are only representative of a larger area if the Contractor has used consistent compaction means and methods and the soils are practically uniform throughout. If it is determined by the Owner/Engineer that there are variations in the compaction methods and/or soil uniformity, additional testing may be required. 3.13 FINAL AND FINISH GRADING A. Using clean topsoil, perform all final and finish grading in all yard and planting areas indicated on drawings. Topsoil shall be placed to a minimum of 4-inch thickness, rototilled to a minimum depth of 8-inch, leveled and finish graded in all areas. No pavement base course material or broken asphalt will be allowed as topsoil materials in landscaping areas. B. Final grading shall be performed and grades shaped to finished elevations indicated. Finish grades(top of the soil)shall be approximately 1-1/2 inch below edges of pathways, curbs and other paved or concrete slabs. After sod installation, the top of the sod shall not be more than '/2-inch below or shall be flush with the grade established by any adjacent paved or curbed surface. 02200 - 9 C. The Contractor shall verify that all finish subgrades are correct prior to beginning installation of sod and planting materials. Upon completion of the project work, the Contractor shall prepare"record drawings"verifying that all finish grades are in accordance with the contract documents and shall submit same to the Engineer for review and acceptance prior to requesting final inspection of the project. The"record drawings"shall be prepared by a surveyor registered in the State of Florida. D. Upon project completion, all areas of the site within immediate construction and adjacent areas shall be completely cleaned of all debris occasioned by this construction. Particular attention is called to any cement, mortar, masonry drippings and plaster which shall be completely removed from planting and lawn areas and shall be disposed of off-site. E. All areas adjacent to the site and all areas not within contract construction areas shall be left in reasonably the same condition as they were found prior to commencement of construction. F. Any damage to the existing adjacent facilities including adjacent lakes or roads, and related areas such as, but not limited to, finish grades, slopes, grass sod, structures, pipe, etc. shall be repaired and restored to a proper and appropriate condition acceptable to the Owner and Engineer. 3.14 EXCESS MATERIAL A. Remove all excess suitable material from the site and dispose of at the Contractor's expense. B. Unsuitable materials shall also be removed and disposed of off-site at the Contractor's expense. END OF SECTION 02200 - 10 SECTION 02270 EROSION AND SEDIMENTATION CONTROL PART 1 - GENERAL 1.01 DESCRIPTION A. The Work specified in this Section consists of measures required to control erosion on the project and in areas outside the project area where Work is accomplished in conjunction with the project, so as to prevent pollution of water, detrimental effects of public or private property adjacent to the project area and damage to Work on the project. These measures will consist of construction and maintenance of temporary erosion control features or, where practical, the construction and maintenance of permanent erosion control features. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 01060: Regulatory Requirements and Notifications 2. Section 02485: Grassing 1.03 START OF WORK A. Do not start work until erosion control measures are in place. PART 2 - PRODUCTS 2.01 GENERAL A. No testing of materials used in construction of temporary erosion control features will be required. B. Materials used for the construction of the temporary erosion and sedimentation control measures not to be incorporated into the completed project may be new or used. 02270 - 1 PART 3 - EXECUTION 3.01 GENERAL A. Construct temporary and permanent erosion and sediment control measures to prevent the pollution of adjacent water ways in conformance with the laws, rules and regulations of Federal, State and local agencies and the conditions. B. Temporary erosion control features shall consist of, but are not limited to, temporary grassing, temporary sodding, temporary mulching, spoil containment pits, sandbagging, slope drains, sediment basins, artificial coverings, berms, baled hay or straw, floating silt barriers, staked silt barriers and staked silt fences. Design details for some of these items may be found in the Village of Tequesta Engineering Standard Details, Chapter 6 of the Florida Land Development Manual: A Guide to Sound Land Water Management (Department of Environmental Regulation) or the Water Quality Section of the applicable edition of the FDOT Roadway and Traffic Design Standards. C. Incorporate permanent erosion control features into the project within seven (7) days of any construction activity. Correct conditions, using temporary measures, that develop during construction to control erosion prior to the time it is practical to construct permanent control features. D. The Contractor will be required to prepare, submit, and obtain a Notice of Intent (NOI) to use Generic Permit for Stormwater Discharge from the Florida Department of Environmental Protection which will include a Stormwater Pollution Prevention Plan (SWPPP) prepared by the Contractor as required by F.A.C. 62-621.300(4) and the Environmental Protection Agency (EPA) as part of the National Pollutant Discharge Elimination System (NPDES) prior to beginning work. 3.02 INSTALLATION A. Temporary Grassing: This Work shall consist of furnishing and placing grass seed in accordance with Section 02485, Grassing. B. Baled Hay or Straw- 1. This Work shall consist of construction of baled hay or straw dams to protect against downstream accumulations of silt. The baled hay or straw dams shall be constructed in accordance with the details shown in FDOT's Roadway and Traffic Design Standards. 02270 - 2 2. The dam shall be placed so as to effectively control silt dispersion under conditions present on this project. Alternate solutions and usage of materials may be used if approved. C. Temporary Silt Fences and Staked Silt Barriers: This Work shall consist of furnishing, installing, maintaining and removing staked turbidity barriers in accordance with the manufacturer's directions, these specifications, conditions of the project permits, and the details as shown in FDOT's Roadway and Traffic Design Standards. 3.03 REMOVAL OF TEMPORARY EROSION CONTROL FEATURES A. In general, remove or incorporate into the soil any temporary erosion control features existing at the time of construction of the permanent erosion control features in such a manner that there will be no detrimental effect. 3.04 MAINTENANCE OF EROSION CONTROL FEATURES A. General: Provide routine maintenance of permanent and temporary erosion control features until the project is completed and accepted. B. Maintenance of erosion control measures shall be in strict accordance with condition of the applicable NPDES, and the Village of Tequesta requirements. 3.05 PROTECTION DURING SUSPENSION OF CONTRACT TIME A. In the event that it is necessary that the construction operations be suspended for any appreciable length of time, shape the top of the earthwork in such a manner as to permit runoff of rainwater and construct earth berms along the top edges of embankments to intercept runoff water. Should such preventive measures fail, immediately take such other action as necessary to effectively prevent erosion and siltation. END OF SECTION 02270 - 3 This page intentionally left blank. 02270 -4 SECTION 02310 SITE GRADING PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. All applicable provisions of the Bidding and Contract Requirements, and Division 1 - General Requirements shall govern the Work under this section. 1.02 WORK INCLUDED A. The Work covered by this section shall include all labor, equipment, services and materials necessary for bringing the site to elevations shown in the plans. This section shall include all necessary excavations for streets. It shall include the construction of embankments and fills by the loading, movement, deposition and compaction of suitable fill materials resulting from above listed excavations. It shall include stockpiling of any excess material to an on-site location as specified by the Owner. B. It shall include rough grading within the roadways and driveways to the elevations or cross-section details shown on the drawings. C. It shall include the erection and maintenance of any barricades that are required for accident prevention and property protection. D. It shall include removal and disposal of muck, rock boulders or any foreign material interfering with construction. 1.03 RELATED WORK A. Section 02110 — Clearing and Grubbing B. Section 02200 — Earthwork, Excavation, and Backfill PART 2 - PRODUCTS NOT USED. 02310-1 PART 3 — EXECUTION 3.01 GENERAL A. The Contractor shall acquaint himself with all Work to be performed as specified and shown on the Drawings. He shall ascertain where all excavation will be required and shall be solely responsible for all excavating to complete the Contract. 3.02 PAYMENT A. No extra payment will be allowed for type or classification of material in excavation. 3.03 MATCHING EXISTING GRADES A. Where existing roadbed surfaces are not at the elevation required prior to subgrade compaction, the Contractor shall perform any such excavation, filling, earthmoving and grading as may be necessary to attain the proper compacted subgrade elevation before proceeding with base course construction. 3.04 UNSUITABLE MATERIAL A. All muck, large rocks and boulders encountered during the Work under this Contract shall be removed and disposed of in a manner approved by the Engineer. 3.05 EXCAVATION A. All excavation shall be unclassified regardless of material encountered. B. The Contractor shall make probings or sounding for subsurface rock to ascertain its location and depth. C. It shall be the Contractor's responsibility to be familiar with soil conditions on the site. Borings, in addition to those provided by others, if any, shall be acquired by the Contractor, at the Contractor's expense. D. Any wet excavated materials shall be drained before hauling or moving. 3.06 EMBANKMENT (FILL) A. Embankment shall be constructed from suitable materials resulting from roadway or site excavation or approved materials furnished from off-site 02310-2 borrow areas. B. Embankments shall be placed in successive layers of not more than 8- inches in thickness, measured loose, for the full width of the embankment. C. Each layer of the material used in the formation of roadbed embankments shall be compacted at optimum moisture content to a density of at least 98% of the Maximum Density as determined by Moisture-Density Tests AASHTO T-180 test results. D. The existing material on the site may vary as to stability. The Contractor shall satisfy himself by site inspection borings, probings, etc., prior to bidding, as to the subsurface character of the material. E. All unstable soil shall be removed and shall be replaced by material approved by the Engineer. 3.07 GRADING A. Due to the minimal longitudinal slope of the roadways, the Contractor shall be required to demonstrate (through finish rock and first lift of asphalt as-builts) a positive flow from high points to low points along the edge of pavement and road crown as indicated on the Contract Drawings. B. Deviations from the proposed grades and drainage patterns as indicated on drawings will be reviewed at the discretion of the Engineer. C. The disposal of large rocks in excess of 8-inches, within roadways and parking areas is prohibited. Where allowable, the disposal of large rocks by burial in areas designated by the Engineer shall have a minimum 30-inches of cover below finished grade elevation. 3.08 SURVEYS A. All initial surveys, including detail construction stakes, will be furnished by the Contractor. B. The Contractor will carefully maintain benchmarks, monuments, stakes, and other reference points, and if disturbed or destroyed, be replaced as directed at the Contractor's expense. C. The Contractor shall provide roadway/sidewalk grades for record drawings for review by the Village and Engineer. 02310-3 END OF SECTION 02310-4 SECTION 02485 GRASSING PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. The Contractor shall furnish all labor, equipment, and materials necessary for grassing all areas disturbed by his operations and any other areas on the plans indicated to receive grassing. It is the intent of this specification that damaged areas are to be replaced in kind, with sod to be used for all maintained yard areas. The Contractor shall take all steps practical to minimize the area required to be sodded. All grassing shall be in accordance with Section 570-1 through 570-5 of the FDOT Standard Specifications for Road and Bridge Construction, except as modified herein. 1.02 STORAGE OF MATERIALS A. The Contractor shall provide space for storage of sod prior to placement in a manner that will not endanger or restrict pedestrian or vehicular traffic or interfere with other aspects of the Work. 1.03 RELATED REQUIREMENTS SPECIFIED ELSEWHERE A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. PART 2 - PRODUCTS 2.01 SOD A. Types: Sod shall be St. Augustine Floratam, Argentine Bahia, Centipede, or Bermuda, depending on type of existing sod in adjacent area to be matched. Sod shall be well matted with roots. Where sodding will adjoin, or be in sufficiently close proximity to private lawns, types of sod other than those listed above may be used if desired by the affected property owners and approved by the Engineer. Sod shall be delivered in commercial-size rectangles, preferably 12-inch by 24-inch or larger. B. Condition: The sod shall be sufficiently thick to secure a dense stand of live grass. The sod shall be live, fresh, and uninjured at the time of planting. It shall have a soil mat of sufficient thickness adhering firmly to the roots to withstand all necessary handling. It shall be reasonably free 02485 - 1 of weeds and other grasses. It shall be planted as soon as possible after being dug and shall be kept moist from the time it is planted. 2.02 GRASSING EQUIPMENT A. Rollers: A cultipacker, traffic roller, or other suitable equipment will be required for rolling the grassed areas. PART 3 - EXECUTION 3.01 GENERAL CONSTRUCTION METHODS A. No grassing shall be done when the ground is unduly wet or otherwise not in a suitable condition. Whenever a suitable length of right-of-way, disturbed area, or other area has been graded, it shall be made ready, when directed by the Owner/Engineer, and grassed in accordance with these specifications. Grassing shall be incorporated into the project at the earliest practical time in the lift of the Contract. 3.02 SODDING A. Preparation of Area to be Sodded: The ground which is to receive sod shall have been graded to proper elevations (2-inch below sodded grade) to match pre-construction conditions or proposed grades. All disturbed swales and ditches shall have been restored to their pre-construction condition or better. The pre-construction grade shall be maintained and the prepared soil shall be loose and reasonably smooth. It shall be reasonably free of large clods, roots, patches of existing grass, and other material which will interfere with the sod-laying operations or subsequent mowing and maintenance operations. B. Laying of Sod: Sod shall be installed in all areas so designated by the Owner/Engineer. Sod shall be carefully placed so that each piece abuts flush to all surrounding sod, regardless of whether surrounding sod is new or existing. All sod joints shall be staggered. Where new sod is to be placed adjacent to existing sod, the new sod must be cut in to match the elevation of the existing sod. Uneven sod which might cause mowing problems will be rejected. New sod laid on top of existing sod will also be rejected. All sod placed on steep slopes (greater than 1.1) shall be pinned with a wooden pin to keep it in place. C. Rolling: Immediately after completion of the sod laying, the entire sodded area shall be rolled thoroughly with the equipment specified. At least two trips over the entire area will be required. 02485 - 2 D. Watering: Newly-sodded areas are to be watered by the Contractor as necessary to keep sod alive until the Contractor is closed out. Dead sod shall be replaced by the Contractor prior to contract closeout. END OF SECTION 02485 - 3 This page left intentionally blank. 02485 -4 SECTION 02580 PAVEMENT MARKINGS AND SIGNAGE PART 1 -GENERAL 1.01 SECTION INCLUDES A. The Work included in this section consists of applying pavement markings as required for new pavement areas and to restore disturbed pavement areas and signage. Work shall adhere to all Village of Tequesta, Florida Department of Transportation (FDOT) and Palm Beach County standards. 1.02 RELATED REFERENCES A. All markings shall conform to the requirements of the MUTCD, and FDOT Roadway and Traffic Design Standards. B. Thermoplastic shall conform to the requirements of the FDOT Standard Specifications for Road and Bridge Construction (Section 711) latest edition. C. Paint shall conform to the requirements of the FDOT Standard Specifications for Road and Bridge Construction (Section 710) latest edition. 1.03 RELATED REQUIREMENTS SPECIFIED ELSEWHERE A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. PART 2 - PRODUCTS 2.01 THERMOPLASTIC A. Stop bars, centerlines, crosswalk striping, directional arrows and any other markings within the right of way to be Alkyd thermoplastic only. B. All other markings, including striping designating parking and loading spaces, to be paint type as shown on the plans. 02580 - 1 2.02 TEMPORARY MARKINGS A. Temporary markings on final asphalt shall be only backed construction tape. Lower asphalt lifts may be marked with paint or any other approved marking material. 2.03 REFLECTIVE PAVEMENT MARKERS (RPM-S) A. RPM'S shall meet FDOT Class B Specifications. B. One blue RPM shall be installed in the center of any roadway adjacent to a fire hydrant. 2.04 SIGN PANELS A. Aluminum or galvanized steel in accordance with the applicable requirements of Section 700 "Highway Signing" of the FDOT Standard Specifications. B. Size, shape and color as indicated on the drawings or as directed by the Engineer. 2.05 SIGN SUPPORT POSTS A. Aluminum or galvanized steel in accordance with the applicable requirements of Section 700 "Highway Signing" of the FDOT Standard Specifications. B. Size, shape and color as indicated on the drawings or as directed by the Engineer. PART 3 - EXECUTION 3.01 APPLICATION A. Sweep dust and loose material from the sealed surface. B. Thermoplastic shall not be installed on a roadway until thirty (30) calendar days after final lift of asphalt has been completed. C. If existing marking material is not compatible with Alkyd thermoplastic, it shall be removed prior to installation of new markings. END OF SECTION 02580 - 2 SECTION 02660 PRESSURE PIPE SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION OF WORK A. The Work covered by this section consists of providing all labor, material and equipment, and performing all construction required to install water main, fittings, valves, fire hydrants, water services and accessories as specified and shown on the drawings. 1.02 SUBMITTALS A. Reports on pressure tests, leakage tests and bacteriological tests will be prepared and submitted by the Contractor. B. Record drawings must be submitted in accordance with the Village of Tequesta Standards. C. Submit product data for all pipe, service connections, fittings, valves, accessories and other appurtenances in accordance with Division 1 specifications. 1.03 REFERENCE STANDARDS A. Water system components which come into contact with drinking water must conform with ANSI/NSF Standard 61-1991, Drinking Water Components. B. All potable water system components shall be supplied and installed per the applicable FDEP and the Village of Tequesta Standards. Refer to the Village of Tequesta for a list of approved products and submittal procedures. C. ANSI/ASTM D2466 - Poly (Vinyl Chloride) (PVC) Plastic Pipe Fittings, Schedule 40. D. ANSI/AWWA C104 — Standard for Cement-Mortar Lining for Ductile-Iron Pipe and Fittings for Water. E. ANSI/AWWA C105—Standard for Polyethylene Encasement for Ductile-Iron Pipe Systems. 02660 - 1 F. ANSI/AWWA C110 — Standard for Ductile-Iron and Gray-Iron Fittings, 3 in. through 48 in. for Water and Other Liquids. G. ANSI/AWWA C111 — Standard for Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings. H. ANSI/AWWA C115 — Standard for Flanged Ductile-Iron Pipe with Ductile- Iron or Gray Iron Treaded Flanges. I. ANSI/AWWA C150 — Standard for the Thickness Design of Ductile-Iron Pipe. J. ANSI/AWWA C151 — Standard for Ductile-Iron Pipe, Centrifugally Cast, for Water or Other Liquids. K. ANSI/AWWA C153 — Standard for Ductile-Iron Compact Fittings, 3 in. through 24 in. and 54 in. through 64 in. for Water Service. L. AWWA C210 — Standard for Liquid-Epoxy Coating Systems for the Interior and Exterior of Steel Water Pipelines. M. AWWA C220 — Standard for Stainless-Steel Pipe, 4 in. and Larger. N. AWWA C504 — Standard for Rubber-Seated Butterfly Valves. O. AWWA C508—Standard for Swing-Check Valves for Waterworks Service, 2 in. through 24 in. P. AWWA C509—Standard for Resilient-Seated Gate Valves for Water Supply Service. Q. AWWA C511 — Standard for Reduced-Pressure Principle Backflow- Prevention Assembly. R. AWWA C512—Standard for Air-Release, Air/Vacuum, and Combination Air Valves for Waterworks Service. S. AWWA C600 — Standards for Installation of Ductile-Iron Water Mains and Their Appurtenances. T. AWWA C605—Standard for Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe and Fittings for Water. U. AWWA C606 — Standard for Grooved and Shouldered Joints. 02660 - 2 V. AWWA C900 — Standard for Polyvinyl Chloride (PVC) Pressure Pipe, 4 in. through 12 in. for Water Distribution. W. AWWA C901 — Standard for Polyethylene (PE) Pressure Pipe and Tubing, '/2 in. through 3 in. for Water Services. X. ASTM D1785 - Poly (Vinyl Chloride) (PVC) Plastic Pipe, Schedules 40, 80, and 120. Y. ASTM D2855 - Making Solvent-Cemented Joints with Poly (Vinyl Chloride) (PVC) Pipe and Fittings. Z. ASTM D2922 -Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth). AA. ASTM D3139 - Joints for Plastic Pressure Pipes using Flexible Elastomeric Seals. BB. ASTM F437-82 - Threaded Chlorinated Poly Vinyl Chloride (CPVC) Plastic Pipe Fittings, Schedule 80. CC. ASTM F439-87 - Standard Specification for Socket - Type Chlorinated Poly Vinyl Chloride (CPVC) Plastic Pipe Fittings, Schedule 80. DD. ASTM 493-85 -Solvent Cements for Chlorinated Poly Vinyl Chloride(CPVC) Plastic Pipe and Fittings. EE. ASME/ANSI B16.5 —1996 — Pipe Flanges and Flanged Fittings. FF. ASME/ANSI B 31.3 — 1996 —ASME Code for Pressure Piping. GG. ASME/ANSI B 16.9 — Pipe Fittings. 1.04 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. The Village of Tequesta Standards and approved product list. C. Specified in other Sections 1. Section 02065: Demolition 2. Section 02150: Dewatering 02660 - 3 3. Section 02200: Earthwork, Excavation and Backfill 4. Section 02670: Flushing, Testing, and Disinfection 1.05 SUBMITTALS A. Submit under provisions of Section 01300. B. Product Data: Provide data on pipes, casings, pipe fittings, valves, thrust collars and accessories. C. Manufacturer's Certificate: Certify that pipe, fittings, and valves meet or exceed respective ANSI, AWWA, and/or NSF Standards. PART 2 - PRODUCTS 2.01 GENERAL A. Although they may not be specifically shown on the drawings or called for elsewhere in the Technical Provisions, the Contractor shall include the cost of all fittings, piping supports, and miscellaneous appurtenances needed to provide a secure, working pipe and valve system. Piping shall be supported by thrust restraints and tie rods as necessary to ensure a stable installation. Adjustable pipe supports or piers shall be arranged to relieve attached equipment of all strain due to the weight of the pipe, fittings, valves, and the contents of the pipe. All tie rods, nuts, bolts, fasteners, and other similar appurtenances shall be 316 stainless steel throughout project to protect against corrosive environment. 2.02 APPROVED PRODUCTS A. All products that come into contact with potable water shall be as specified by the Village of Tequesta Standards and Village of Tequesta approved products list. B. DUCTILE IRON PIPE Ductile iron pipe and fittings shall conform to AWWA/ANSI C151/A21.52, Class 51 (minimum) Pressure Class 350, unless heavier class is required for conditions. Sizes 3" to 12" diameter shall be class 52. Sizes 14" and above shall be class 51. All ductile iron pipe shall be polyethylene encased in accordance with ANSI/AWWA C105/A21.5. If no standard exists, the following shall be used: 02660 - 4 1. Joints: All buried pipe at fittings must be restrained, mechanical joints. "Push on" and mechanical joints shall be in accordance with AWWA/ANSI C111/C21.11. Restraine joint assemblies with mechanical joint pipe shall be by approved restraining devices. Exposed joints shall be AWWA approved flanged joint pipe, in accordance with ANSI/AWWA C115, or as detailed on the drawings. Flanges shall be threaded unless otherwise noted. All above ground flanges shall be flat faced unless they are mating up to existing raised flanges. All gaskets shall be full faced 1/8" Toruseal, or approved equal. 2. Fittings: Buried fittings shall be AWWA approved mechanical joint fittings. Exposed fittings shall be flanged fitting or as detailed on the drawings. Conform to AWWA C153 with a minimum pressure rating of 350 psi. 3. The internal surface of all piping and fittings in contact with potable water shall be cement mortar lined and seal coated in accordance with AWWA C104, A21, unless other noted. 4. External surfaces of all buried ductile iron pipe and fittings shall be coated with a bituminous coating approximately one mil thick in accordance with AWWA C151/A21.51 latest revision. DIP water main shall have a line of blue paint or blue tape the full length of the new run on top of the pipe and on both sides. 5. Restrained joint fittings for 24-inch and smaller diameter pipe shall be ductile iron, "Flex-Ring" as manufactured by America Cast Iron Pipe Company, "TR Flex" and manufactured by US pipe Company, "Super- lock" as manufactured by Clow corporations, or an approved equal. Restrained joint fittings for 30-inch and larger pipe shall be ductile iron, American Cast Iron Pipe Co., Lok-Fast or approved equal. Restrained joint pipe shall be constructed on all new water mains adjacent to all bends, crosses, tees, etc., where a change in direction occurs. Refer to the table on the drawings for restrained pipe lengths. C. DUCTILE IRON FITTINGS All products that come into contact with potable water shall be as specified by the Village of Tequesta Standards. All ductile iron fittings shall be polyethylene encased in accordance with ANSI/AWWA C105/A21.5. If no standard exists, the following shall be used- 1. Potable Water: Ductile iron fittings shall conform to ANSI/AWWA Standard C110 A21.10 latest revision. Fittings 4-inch and larger shall 02660 - 5 be cement lined and seal coated in accordance with ANSI/AWWA Standard C104 A21.4 latest revision. D. POLYVINYL CHLORIDE (PVC): AWWA C-900 & C-905 All products that come into contact with potable water shall be as specified by the Village of Tequesta Standards. If no standard exists, the following shall be used: 1. PVC will be acceptable for water mains up to and including 30-inch diameter pipe. 2. PVC must meet requirements as set forth in AWWA C900 and C905 and bear the National Sanitation Foundation seal for potable water pipe. Provisions must be made for contraction and expansion at each join with a rubber ring and integral thickened bell as part of each joint. Pipe and fitting must be assembled with nontoxic lubricant. 3. Water mains shall be blue in color. 4. Design working pressure for water mains shall be C900, DR-18 (Pressure Class 150) 4" to 12", C905, DR-18 (Pressure Rating 235) 14" to 30". 5. Connections for pipe 2-inches of greater in diameter shall be rubber compression ring-type. Pipe shall be extruded with integral thickened wall bells without increase in dimension ration (DR). Rubber ring gaskets shall consist of synthetic compounds meeting the requirements of ASTM Designation F477 and suitable for the designated service. 6. Fittings: Ductile iron fittings shall be used on all PVC C900 & C905 mains. Fittings shall conform to AWWA/ANSI C110/A21.10 with a minimum pressure rating of 350 psi. All ductile iron fittings shall be polyethylene encased in accordance with ANSI/AWWA C105/A21.5. E. POLYETHYLENE TUBING All products that come into contact with potable water shall be as specified by the Village of Tequesta Standards. If no standard exists, the following shall be used: 02660 - 6 1. Polyethylene tubing shall conform to AWWA C901 subject to the Standard Code Designation PE4710, Pipe Class 200, and Dimension Ratio (DR) 9. 2. Tubing shall bear identification markings, which shall remain legible during normal handling, storage, and installation, and which have been applied in a manner than will not reduce the strength of the product or otherwise damage the tubing. Marking on the tubing shall include the following and shall be applied at intervals of not more than 5 feet. Nominal size, material code designation, dimension ratio, pressure class, manufacturer's name or trademark and production record code, and seal (mark) of the testing agency that certified the suitability of the tubing material for potable water products is required. 3. Joints for polyethylene tubing shall be of the compression type utilizing a totally confined grip seal and coupling nut. Stainless steel tube stiffener insert shall also be used for tubing services. 4. All fittings and stops to be high quality water works brass. No PVC fittings or adapters will be permitted. Fittings shall be brass equipped with compression-type connectors. F. FIRE HYDRANTS See specification section 02660, Section 2.02A. If no standard exists, the following shall be used: 1. All fire hydrants shall comply with AWWA Standard C-502 latest revisions thereof and the following design standards. 2. Fire hydrants shall be of the compression type, opening against the pressure and closing with the line pressure with a 5-1/4-inch minimum valve opening. The hydrant shall be equipped with two 2-1/2-inch hose and one 4-1/2-inch steamer nozzles to meet the American National Standard hose thread. 3. Hydrants shall be furnished with a sealed oil or grease reservoir location in the bonnet so that all threaded and bearing surfaces are automatically lubricated when the hydrant is operated. The hydrant will be designed for disassembly by use of a short disassembly wrench or the hydrant shoe having integral cast tieback lugs on the main valve to permit the main valve assembly and valve seat to be removed without digging earth or disassembling the hydrant barrel. 02660 - 7 4. Hydrants shall be furnished with a breakable feature that will break cleanly upon impact. This shall consist of a two part breakable safety flange with a breakable stem coupling. The upper and lower barrels shall be fluted and ribbed above and below the safety flange or have an extra strength lower barrel. 5. The hydrant internal valve shall be 5-1/4-inch minimum. The pentagonal operating nuts and the cap nuts shall be 1-1/2-inch point to flat. Drain valve outlets shall be plugged or omitted. The hydrants shall open counter-clockwise and the direction of opening shall be case on top. 6. Fire hydrant color shall be yellow to match the existing hydrants. Paint shall be reflective type with glass beads all in accordance with N.F.P.A. #291. 7. Installation. Hydrants shall be installed plumb with the larger nozzle facing the street or access area. Where possible, the tee on the main shall be an anchor tee to which the gate valve is attached and installed onto. A Grade Lock long sweep device with anchor fittings shall then be attached to the gate valve and the hydrant shall be attached to the Grade Lock device. Where anchor fitting cannot be used, the components shall be tied together with %-inch stainless, galvanized or bituminous coated steel rods. G. THRUST RESTRAINT See specification section 02660, Section 2.02A. If no standard exists, the following shall be used- 1. All bends, tees, crosses, reducers and dead ends shall be restrained through an approved means of joint restraint unless an alternate restraint method is shown on the drawings. All branch valves shall be restrained with joint restraints or approved equal or anchor tees, or anchor couplings. Any line terminated during the construction phase that is a known future extension shall have a plugged valve placed at the end and be restrained. Thrust restraints shall be placed in accordance with the restraint table shown in the construction plans. If installed cover is less than the depth referenced in the table, increase restrained length per manufacturer's recommendation. Existing pressure pipes that are modified by the construction or connected to new piping systems shall be restrained by bell restraints, split-ring restraints, or thrust blocks as appropriate. 02660 - 8 2. All restraints shall be EBAA 1900 and 2000 style for PVC installations and EBAA 1100 style for ductile iron MJ connections. H. LOCATOR FOR WATER MAIN PIPE See specification section 02660, Section 2.02A. If no standard exists, the following shall be used- 1. On all pipe construction, 10 gauge, THHN insulated, solid copperwire shall be laid and secured on top of pipe. Wire shall be continuous from valve box to valve box, wrapped two times around each joint of pipe and extended inside each valve box to enable location devices to be attached without digging up the valve box. Locator wire shall be routed to ARV boxes at the request of the Village. 2. Service wire shall be laid in the trench with all services, connected to the main wire and wrapped around the service piping or tubing. Wire for water mains shall be blue in color. 3. All wire connections shall be made with Dri-Splice wire connectors, Imperial Snip-Snap fittings filled with waterproof silicone sealant or approved equal. All splices shall be inspected and tested before burial. 4. Blue warning tape, as applicable to water main, shall also be provided 18-inches above pipe. I. VALVE BOXES See specification section 02660, Section 2.02A. If no standard exists, the following shall be used- 1. All valve boxes shall be cast iron construction with 5-inch shafts, equal to Tyler pipe 6850 series or Bingham Taylor equivalent. Valve box lids shall have a 1-inch deep skirt and shall have the words "WATER", where appropriate, cast in the top. Valve operating nuts shall be brought to within 30-inch of the surface using valve extension rods if required. J. WATER SERVICES All water service material and fittings shall be main products in conformance with the Village of Tequesta Utility Standards. Joints in PE service piping shall not be allowed. 02660 - 9 PART 3 - EXECUTION 3.01 SALVAGEABLE MATERIAL A. Any existing equipment or material which is removed or replaced as a result of construction under this project may be designated as salvageable by the Village of Tequesta and if so, shall be removed, cleaned, and delivered to a protected location specified by the Village. Any equipment or material not worthy of salvaging, as directed by the Village, shall be disposed of in a legal manner by the Contractor at an off-site location. Upon request of the Engineer, the Contractor shall submit evidence of proper disposal. 3.02 POTABLE WATER SYSTEM A. Potable Water system components shall be installed perthe requirements of the Village of Tequesta Standards. 3.03 IDENTIFICATION AND COLOR CODING OF PIPE & FITTINGS A. POTABLE WATER MAINS 1. All water main pipe and fittings shall be color coded or marked using safety blue as a predominant color to differentiate drinking waterfrom reclaimed or other water. Underground plastic pipe shall be solid-wall Blue pipe, shall have a co-extruded blue external skin, or shall be white or black pipe with blue stripes incorporated into, or applied to, the external pipe wall. 2. Underground metal or concrete pipe shall have safety blue stripes applied to the pipe wall. Pipe striped during manufacturing of the pipe shall have continuous stripes that run parallel to the axis of the pipe, that are located at no greater than 90-degree intervals around the pipe, and that will remain intact during and after installation of the pipe. If tape or paint is used to stripe pipe during installation of the pipe, the tape or paint shall be applied in a continuous line that runs parallel to the axis of the pipe and that is located along the top of the pipe. For pipes with an internal diameter of 24-inches or greater, tape or paint shall be applied in continuous lines along each side of the pipe as well as along the top of the pipe. 3. Aboveground pipe at drinking water treatment plants shall be color coded and labeled in accordance with subsection 62-555.320(10), F.A.C. 4. All aboveground potable water pipe shall be painted solid blue. 02660 - 10 5. Blue Warning tape with "WATER" printed on the tape shall be placed in the trench during backfill of the water pipe, a vertical distance of 18-inch above the crown of the pipe. 3.04 MARKING BY MANUFACTURER A. Special markings shall be plainly marked on the applicable pipe indicating the weight, class of pipe, casting period, manufacturer's mark and year pipe was produced. 3.05 EXISTING UTILITIES A. The plans depict the approximate location of the known existing subsurface water, sanitary sewer, electric, telephone, gas, cable, and storm water utilities. B. The Contractor will arrange for underground utilities to be located by appropriate utility owners in advance of the Contractor's operations. The Contractor shall pothole all locations where the proposed pipe crosses an existing underground facility to verify that a conflict does not exist. C. Notify the Engineer of any substantial changes thatwould require a deviation in the plans. D. Repair any damage done to existing utilities and private property at no additional expense to the Owner. 3.06 PREPARATION A. Where applicable, ream pipe and tube ends and remove burrs. B. Remove scale and dirt, on inside and outside, before assembly. C. Prepare pipe connections to equipment with flanges or unions. 3.07 BEDDING A. Excavate trench and install pipe bedding as specified in Section 02200, Earthwork, Excavation and Backfill. 3.08 SURFACE CONDITIONS A. Inspection 02660 - 11 1. Prior to all Work of this section, carefully inspect the installed work of all other trades and verify that all such work is complete to the point where this work may properly commence. 2. Verify that all equipment may be installed in accordance with all pertinent codes and regulations, the original design, shop drawings, and the reference standards. B. Discrepancies 1. In the event of discrepancy, immediately notify the Engineer. 2. Do not proceed with installation in area of discrepancy until all such discrepancies have been fully resolved. 3.09 PIPE INSTALLATION GENERAL A. Verify that building service connection(s) and size, location and invert of municipal utility water mains are as indicated. B. Take all precautions necessary to ensure that pipe, valves, fittings, and other accessories are not damaged in unloading, handling, and installation. Examine each piece of material just prior to installation to determine that no damage has occurred. Remove any damaged material from the site and replace with undamaged material. C. Exercise care to keep foreign material and dirt from entering pipe during storage handling and installation. Close ends of in-place piping at the end of any work period to preclude the entry of animals and foreign material. D. Use only those tools specifically intended for cutting the size, material and type pipe involved. Make cut to prevent damage to pipe or lining and to leave a smooth end at right angles to the axis of the pipe. E. Pipe deflection at joints shall be limited to 75% of the manufacturer's maximum deflection tolerance. F. All piping shall be laid to line in a clean, dry trench on line and grade with all valves and appurtenances plum. G. No wet taps, line stops, or connections to active water lines shall be performed on a Friday without prior permission from the Village. H. Underground pressure piping systems shal be securely anchored by acceptable means at all tees, plugs, caps, bends and valves, and at all other 02660 - 12 locations where unbalanced forces exist or as directed by the Utilty or Engineer. Restrained joints shall be used in accordance with manufacturer's recommendations. I. Black bags (fabric or geotextile only) shall be placed over hydrants not in service. No plastic garbage bags. J. All coupons shall be kept and provided to the Village. K. Special Exterior Protection for Corrosion: When specifically required, extra protection shall be provided for underground cast or ductile iron pipe and fittings within areas of severe corrosive conditions. This shall be accomplished by the installation of encasement or outside protection, AWWA C105, through the area of concern. Soil-test evaluation to determine the necessity for extra protection in suspect areas shall be as set forth in ANSI Standard A21.5. L. In case of conflict between various installation requirements, the more stringent requirement shall apply. 3.10 PIPE/SLEEVE INSTALLATION — DIRECTIONAL BORE (PLUMBING CONNECTION) A. This work shall include all services, equipment, materials, and labor for the complete and proper installation, testing, restoration of underground utilities and environmental protection and restoration. B. The proposed plan installation locations are approximate; the intent is to construct the water service in the general area shown and to avoid existing utilities and obstructions. The general horizontal location are shown on the plans, but the entry and exit locations, and minimum clearances are not shown on the plans. The Contractor may utilize an alternative drill path than is shown on the drawings with the approval of the Owner at no additional cost to the Owner. C. Submittals: a. Specifications on material to be used shall be submitted to Engineer. Material shall include the pipe, fittings and any other item which is to be an installed component of the project. D. Contactor shall notify all companies with underground utilities in the work area via the state or local "one-call" to obtain utility locates. Once the utilities have been located Contractor shall physically identify the exact location of the utilities by vacuum or hand excavation, when possible, in order to determine the actual location and path of any underground utilities which 02660 - 13 might be within 20 feet of the bore path. Contractor shall not commence boring operations until the location of all underground utilities within the work area have been verified. E. The Contractor is required to bring to the attention of the Engineer any known design discrepancies with these specifications and the actual drilling methods that the Contractor will be performing. This shall be stated in writing to the Engineer no later than the pre-construction meeting. F. No joints in HDPE sleeves shall be allowed. G. Horizontal directional drilling shall consist of the drilling of a small diameter pilot hole from one end of the alignment to the other, followed by enlarging the hole diameter for the pipeline insertion. The exact method and techniques for completing the directionally drilled installation will be determined by the Contractor, subject to the requirements of these Specifications. H. The elevation of the sleeve and/or carrier pipe at the location of the connection point of the directional bore shall be 36" below the natural grade and shall be in a horizontal location for ease of connection to continuing lateral or mainline. Should this not be possible due to the acute angle of the bore, the contractor shall furnish and install appropriate fittings to provide for a horizontal continuation. I. The required piping shall be assembled in a manner that does not obstruct adjacent roadways, driveways, or public activities. The Contractor shall erect temporary fencing and submit Maintenance of Traffic plans for approval by Palm Beach County and the Village. J. During the drilling, reaming, or pullback operations, the Contractor shall make adequate provisions for handling the drilling fluids, or cuttings at the entry and exit pits. To the extent practical, the Contractor shall maintain a closed loop drilling fluid system. When the Contractor's provisions for storage of the fluids or cuttings on site are exceeded, these materials shall be hauled away to a suitable legal disposal site. After completion of the directional drilling work, the entry and exit pit locations shall be restored in accordance with the project specifications. K. Following service operations, the Contractor will de-mobilize equipment and restore the work-site to original condition. All excavations will be restored in accordance with the project specifications. 3.11 VALVES AND VALVE BOXES 02660 - 14 A. Unless a beveled gear valve is specified, for valves 2-inch through 12-inch, install valves for with operator stems in the vertical plane through the pipe axis and out of the plane of flow. Locate valves where shown on Drawings. Thoroughly clean valves before installation. Check valves for satisfactory operation. B. Equip all underground valves with gearing or operator switch valve boxes. Set box in alignment with valve stem centered on valve nut. Set the valve box to prevent transmitting shock or stress to the valve. Set the box cover flush with the finished ground surface or pavement. 3.12 PIPE PENETRATIONS A. Use sleeves where pipes, valve stem extensions, or equipment parts pass through poured in place concrete or masonry walls or slabs. Sleeves shall be either cast iron or fabricated steel wall pipe with intermediate flange seep ring of sufficient size to allow sealing around pipe and clearance for valve stems or equipment. Extend vertical sleeves through slabs 1-inch above top surface. B. Where new pipe must penetrate concrete wall on non-water bearing concrete structures, drill penetration in neat, workmanlike manner, install pipe, grout in place with non-shrink grout, and refinish surface to match adjacent. 3.13 THRUST RESTRAINT A. Provide reaction anchors of concrete blocking, metal harness, retainer gland type or restrained joint type at all changes in direction of pressure pipelines and as shown on drawings. B. Concrete reaction anchors shall bear against undisturbed earth and shall be of the size and shape necessary to resist service conditions of the pipe. C. Use metal harness restraints as shown on drawings to restrain existing pipe segments. D. Where retainer glands are used, extreme care shall be taken so that each set screw is tightened as recommended by the manufacturer before the pipe is backfilled and tested. E. Existing piping shall be restrained with bell restraints as required by the thrust restraint table shown on the plans. 02660 - 15 F. Anchor tees shall be used for fire hydrants attached to new water mains. Anchor couplings shall be used for fire hydrants attached to existing water mains. 3.14 FIELD QUALITY CONTROL A. Compaction testing shall be performed in accordance with Section 02200. B. If tests indicate Work does not meet specified requirements, remove Work, replace, and retest at no cost to Owner. 3.15 CONSTRUCTION CONSTRAINTS The Contractor shall give special considerations to accommodate the business owners and residents in minimizing downtime and disruption of water and sewer services during the entire construction period. A. The Contractor will be required to submit as-builts including laboratory results to the Village of Tequesta after the completion of each phase for preparation of Request for Partial Release and submission to the Palm Beach County Health Department. The Contractor shall coordinate with the Village of Tequesta when service shut downs are required for performance of the Work. The Village will be required to deliver (Village's standard) Boil Water Notices in notifying affected customers of a service interruption and delivering those notices to affected customers at least 48 hours prior to any service interruption. The Contractor shall comply with the following limitations- 1. Each service interruption required for transferring (relocating) an existing water service will be limited to a maximum of two hours; 2. Each service interruption required for connecting newwaterserviceto water meter will be limited to a maximum of one hour; 3. Each service interruption required for tie-in of new main to existing distribution system will be limited to a maximum of four hours. B. The Contractor shall coordinate with the Village of Tequesta on their preferred method of transferring existing water services to proposed water mains. END OF SECTION 02660 - 16 SECTION 02670 FLUSHING, TESTING AND DISINFECTION PART 1 - GENERAL 1.01 WORK INCLUDED A. Flushing, Pressure Testing, and Disinfection of systems including, but not limited to, the potable water mains shown to be relocated on the Plans. B. The Contractor shall furnish all necessary pumps, hoses, piping, fittings, meters, gauges, chemicals and labor to conduct specified testing. C. Testing shall be repeated at the Contractor's expense until satisfactory results are achieved. 1.02 RELATED REQUIREMENTS A. Drawings and general provisions of the Contract, including the General Conditions and Terms and Division 1 Specification sections, apply to this section. B. Specified in other Sections- 1. Section 02660: Pressure Pipe Systems 1.03 REFERENCES A. ANSI/AWWA C651 - Standard for Disinfecting Water Mains. 1.04 SUBMITTALS A. Test Reports: Indicate results comparative to specified requirements. Submit two (2) copies of test results to Engineer in accordance with Submittal specifications. B. Final approval of the bacteriological samples shall be received from the Florida Department of Environmental Protection (Palm Beach County Health Department) prior to the time that the system is placed into operation. Sampling procedures shall be done in accordance with FDEP requirements. C. Bacteriological sampling locations shall meet FDEP requirements and be taken where shown on the drawings and as directed by the Engineer at no 02670 - 1 additional cost to Owner. Costs for all bacteriological testing shall be borne by the Contractor. 1.05 QUALITY ASSURANCE A. Perform Work in accordance with ANSI/AWWA C651. 1.06 REGULATORY REQUIREMENTS A. Conform to applicable FDEP requirements for performing the work of this Section. B. Work shall conform to Village of Tequesta Standards. PART 2 - PRODUCTS 2.01 DISINFECTION CHEMICALS A. Chemicals shall be in accordance with the Village of Tequesta Standards. If no standards exist, the below chemicals shall be used. B. Chemicals: The disinfecting agent shall be sodium hypochlorite solution ANSI/AWWA B303 or liquid chlorine ANSI/AWWA B301. Dry hypochlorite, similar to "HTH" or equal may also be used as the disinfecting agent. Bleach or Clorox is not acceptable. PART 3 - EXECUTION 3.01 EXAMINATION A. Verify that the installed potable water systems have been cleaned, inspected, and tested. B. Coordinate scheduling and disinfection activity with the Engineer and the Village of Tequesta. 3.02 FLUSHING AND PRESSURE TESTING - PIPING The Contractor shall furnish and install suitable temporary testing plugs or caps for the water lines, all necessary pressure pumps, hose, pipe connections, meters, gauges and other similar equipment, and all labor required, all without additional compensation for conducting pressure and leakage tests and flushing of the new water lines and force mains. Flushing and pressure testing shall be in accordance with the Village of Tequesta Standards. If no standards exist,flushing and pressure testing shall be conducted in the following order. 02670 - 2 A. After all piping lines have been installed and before pressure testing and final connections to equipment, each run of pipe shall be thoroughly flushed so as to remove all debris and foreign matter from the piping and equipment. Clean and flush all piping using potable water. Cleaning and flushing shall be achieved by pigging or cannon flushing if approved by the Village of Tequesta Standards. Each section of pressured main will be thoroughly cleaned with two (2) polyurethane foam pigs as manufactured by Girard Poly-Pig Inc. or an approved equal. Each pig will run through the line prior to running the second pig. Contractor shall furnish and install required pig launch and exit assemblies or temporary piping required for cannon flushing. Non-abrasive pigs shall be employed. Flushed water may be discharged to the onsite catch basins or water bodies and be coordinated with Owner. The Contractor to provide means of discharging water to catch basins at the Contractor's expense. B. Pressure and leakage tests shall be conducted in the presence of the Engineer, or his representative. All pressure mains, fittings, water services, and appurtenances shall undergo pressure and leakage tests. The Contractor will provide all necessary apparatus including a suitable pressure gage, pump, measuring device, piping connections and fittings and the necessary labor to conduct the test. Leakage is defined as the quantity of water added to the pipe being tested during the test period. The Contractor shall submit to the Engineer the testing pattern he proposes to follow priorto testing for the Engineer's approval. The Contractor shall not test more than 1,500 feet of pipe in a single test without approval from the Engineer. C. Pressure testing ductile iron and PVC piping systems- 1. The test pressure for the water piping constructed of ductile iron and PVC pipe shall be 150 psi. The test pressure for force main piping shall be 100 psi. These pressures shall be maintained for a period of not less than two hours. Tests shall be made between valves and as far as practicable and as approved by the Engineer. Potable water from the distribution system shall be used. Pressure shall not vary more than five (5) psi for piping during the test periods or as approved by the Engineer. Additionally, allowable leakage shall be computed on the basis of AWWA C-600, C-605 where practical. 2. All leaks evident at the surface shall be uncovered and repaired regardless of the total leakage as indicated by the test, and all pipes, valves and fittings and other materials found defective under the test shall be removed and replaced at the Contractor's expense. Tests shall be repeated until leakage has been reduced below the allowable amount. 02670 - 3 3. Should, in the judgment of the Engineer, it not be practical to follow the foregoing procedures exactly for any reason, modifications in the procedure shall be made as approved by the Engineer and the Village of Tequesta. In any event, the Contractor shall be responsible for the ultimate water tightness of the plant piping within the preceding requirements. 3.03 DISINFECTION A. The Contractor shall furnish and install suitable temporary connections to the piping, all necessary pressure pumps, hose, pipe connections, meters, gauges and other similar equipment, and all labor required, all without additional compensation for the disinfection of all required potable water piping systems. Disinfection shall be in accordance with the Village of Tequesta Standards. If no standards exist, disinfection shall be conducted on the following systems in the following manner- 1. All relocated and new potable water and private fire line piping. B. Conform to AWWA Standards and as modified herein. C. Maintain disinfectant for a minimum of 8 hours in such a manner that the entire system will be filled with water containing a minimum chlorine concentration of 50 ppm at any point. At the Village and/or the Engineer's request and at no additional cost to the Owner, this step may be required to be performed immediately before pressure testing. D. After the disinfecting agents have been permitted to remain for the specified contact periods, the water lines, and valves shall be thoroughly flushed with water until the residual chlorine tests are less than 4 ppm in each instance. The determination of the amount of residual chlorine in the system shall be made at such points and in accord with standard tests by means of a standard orthotolodine test set. E. Replace permanent system devices removed for disinfection. 3.04 BACTERIOLOGICAL SAMPLING A. It shall be the responsibility of the Contractor under this Contract to perform the bacteriological testing required by the Florida Department of Environmental Protection (Palm Beach County Health Department) and the Village of Tequesta to obtain clearance of all piping. The Contractor shall be responsible to disinfect and repeat testing as needed until clearance is obtained for all required systems. The Contractor shall be responsible to 02670 - 4 pay for additional water needed if the bacteriological testing must be repeated. B. The piping requires two (2) passing consecutive daily samples taken from the locations called out on the plans or as determined by the Engineer. The samples shall be taken concurrently at all the respective sample point locations. C. Sampling must be coordinated with the Engineer and other construction activities so as to minimize re-sampling. D. The Contractor shall submit schedule for bacteriological testing and pressure tests. E. The Contractor shall incur all costs needed to provide bacteriological clearance of the piping systems. F. If repeated tests of such samples show the presence of coliform organisms, the disinfection shall be repeated until tests indicate an absence of contamination. 3.05 QUALITY CONTROL A. The laboratory and personnel collecting bacteriological samples shall be Florida state certified in accordance with FDEP requirements. 3.06 CONNECTIONS TO EXISTING MAINS A. The Contractor shall make connections to existing mains as shown on the drawings. The connections of new water main to existing main shall be made only after the new mains have passed their pressure and leakage test and completed the disinfection and bacteriological clearance procedures as mandated by the Palm Beach County Health Department, and shall be under the Owner's immediate supervision. END OF SECTION 02670 - 5 This page has been intentionally left blank. 02670 - 6 SECTION 02741 ASPHALTIC SURFACES PART 1 — GENERAL 1.01 RELATED DOCUMENTS A. All applicable provisions of the bidding and Contract Requirements, and Division 1 — General Requirements shall govern the Work under this section. 1.02 WORK INCLUDED A. This section of the specifications covers the control and general conduct of asphalt paving construction for roads, parking, walks and court areas. B. All Work within the right-of-way shall be constructed using materials and methods in accordance with the Contract drawings, Palm Beach County Standards and Florida Department of Transportation Standard Specifications for Road and Bridge Construction. 1. Grade deviations from Contract and Drawings shall conform to Section 02310, Site Grading. C. Provide all labor, materials, necessary equipment and services to complete the Asphaltic Surfaces work, as indicated on the drawings, as specified herein or both, except as for items specifically indicated as "NIC ITEMS". D. Including, but not necessarily limited to the following: 1. Preparation of subgrade 2. Installation and compaction of base course 3. Spreading of asphalt surface course 1.03 RELATED WORK A. Section 02200 — Earthwork, Excavation, and Backfill B. Section 02310 — Site Grading C. Section 02751 — Portland Cement Concrete Paving 02741-1 1.04 REFERENCE STANDARDS A. American Association of State Highway and Transportation Officials (AASHTO) 1. M140 - Standard Specification for Emulsified Asphalt Nineteenth Edition; Revised Per Interim Specifications — Specifications - 1999 R (1998) 2. M276 - Standard Specification for Viscosity Graded Asphalt Cement Nineteenth Edition R (1996) 3. T245 - Standard Method of Test for Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus Nineteenth Edition; ASTM D1559-76 B. American Society for Testing and Materials (ASTM) 1. D1559 - Test Method for Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus 2. D2041 - Standard Test Method for Theoretical Maximum Specific Gravity and Density of Bituminous Paving Mixtures 3. D2171 - Standard Test Method for Viscosity of Asphalts by Vacuum Capillary Viscometer (RAP Asphalt Mixes) C. Asphalt Institute (AI) 1. MS-2- Mix Design Method for Asphalt Concrete and Other Hot Mix Types 2. MS-22- Principles of Construction of Hot-Mix Asphalt Pavement, Addendum 1.05 TRAFFIC CONTROL A. The Contractor shall provide and maintain access to and from all properties along the line of Work. The Contractor shall also provide temporary by- passes and maintain them in a safe and usable condition whenever detouring of traffic to parallel routes cannot be done without hardship or excessive increases in travel by the public. 02741-2 1.06 SPECIAL SUBGRADE CONDITIONS A. When special subgrade conditions are encountered for which these "Asphaltic Surfaces Specifications" are not applicable, portions of these specifications shall be deleted or revised to provide a properly finished paved surface. A requested revision or deletion of the specifications shall be accompanied with reports and laboratory tests on existing field conditions. Any change from these "Asphaltic Surfaces Specifications" shall be approved by the Engineer and shall be in effect only for a specified area or paving project. 1.07 QUALITY ASSURANCE A. DOT Standard Specifications. 1. Work and materials shall conform to all applicable requirements of Florida Department of Transportation "Standard Specifications for Road and Bridge Construction — Current Edition" (referred to herein as DOT). B. American Society for Testing and Materials. 1. ASTM 3515-80 "Standard Specification for Hot-Mixed, Job Laid, Bituminous Paving Mixtures." 1.08 SUBMITTALS A. Job Mix Designs: The Contractor shall submit a mix design for each pavement course proposed for construction for the Owner's review and approval 45 days prior to schedule production and lay down of the mix. The design mix submittal shall be formatted as indicated in Asphalt Institute Manual MS-2, the "Marshall Stability Method"; and shall include type/name of mix, gradation analysis, grade of asphalt cement, Marshall Stability in pounds flow, effective asphalt content in percent (%), and corresponding copies of governing State Department of Transportation (DOT) material specifications or regulatory authorities having jurisdiction for each proposed material. B. The Contractor may submit to the Owner a superpave asphalt mix design for review and approval, in lieu of a Marshall Mix Design asphalt, meeting the specifications of the governing State Department of Transportation or regulatory authorities having jurisdiction. C. Material Certificates: The Contractor shall submit certificates stating that asphalt mix to be supplied complies with the specifications of the 02741-3 governing State Department of Transportation (DOT) or regulatory authority having jurisdiction, as well as copies the regulatory specifications corresponding to the asphalt mix formula and material. The certificates shall be signed by the asphalt mix producer and the Contractor. 1.09 JOB CONDITIONS A. Apply prime and tack coats when ambient temperature is above 50 degrees, and when temperature has not been below 35 degrees for 12 hours immediately prior to application. Do not apply when base is wet or contains an excess of moisture. B. Construct asphalt concrete surface course only when atmospheric temperature is above 40 degrees, and when base is dry. Base course may be placed when air temperature is above 30 degrees, and rising. 1.10 LOCATIONS, LAYOUT AND GRADES A. Locate and layout paved areas and rights-of-way with reference to benchmarks, property lines or buildings according to the Contract drawings and accepted by the Engineer. The Contractor shall not utilize electronic files from the Engineer for layout. B. Determine locations of paved edges and right-of-way lines from surveyor's permanent reference monuments and information on the Horizontal Control drawings. C. Where permanent reference monuments are not available, obtain proper line locations from authorities having jurisdiction. D. Establish and maintain required lines and elevations. E. Furnished rock as-builts shall demonstrate a positive flow along the edge of pavement and road crown from the high point to the low point (catch basin/inlet) as indicated on the Contract drawings. PART 2 — PRODUCTS 2.01 FILL A. All fill shall be clean rock and sand (maximum rock size = 1-inch). B. Fill shall be compacted thoroughly as per Section 02300 — Earthwork. 02741-4 2.02 LIMEROCK A. Limerock shall be obtained from pits for which all overburden has been removed previous to blasting and shall show no tendency to air slake and must undergo the following chemical requirements. 1. Carbonates of Calcium Min. 70.0% (Miami Limerock) and Magnesium. (24- foot roadway). Min 60.0 (Miami Limerock) and Magnesium. (22-foot roadway) 95.0 (Ocala Limerock) 2. Oxides of Iron and Max. 2.0% Aluminum 3. Organic Matter Max 5.0% 4. Any constituents of other than the above shall be silica or inert material. 5. The material shall be crushed to such size that not less than 97% shall pass a 3-1/2-inch sieve and it shall be graded uniformly down to dust. All fine material shall consist entirely of duct of fracture. 6. Limerock from on-site may be used if the material meets the requirements of this section of the specifications. B. All limerock shall comply with requirements set forth under DOT Section 911. C. Limerock Bearing Requirements — Limerock material used in construction of limerock base shall have an average LBR vales of not less than 100. The average LBR value of materials produced at a particular source shall be determined in accordance with an approved quality control procedure. D. Equipment: The equipment for constructing the rock base shall be in first class working condition and shall include- 1. Vibratory compactor weighing not more than three tons. If approved in writing by the Engineer, larger vibratory compaction equipment may be allowed if operated in static mode only. 2. Self-propelled blade grader weighing not less than three tons. The wheel base shall be not less than 15-feet and 02741-5 blade length not less than 10-feet. 3. Scarifiers shall have teeth space not to exceed 4-1/2-inches. 4. Provision for furnishing water at the construction site by tank or hose at a rate not less than 50 gallons per minute. 2.03 PRIME COAT A. Prime coat shall be Grade RC-70, cut-back asphalt, DOT Section 916-2. B. Prime coat shall have full compatibility with surface treatment asphalt. C. The bituminous material shall conform to the requirements of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, Section 300-2. D. The sand for cover shall be clean dry sand. 2.04 TACK COAT A. The bituminous material to be used for the tack coat shall conform to the requirements of the Florida Department of Transportation Standard Specifications for Road and Bridge Construction, Section 300-2. 2.05 ASPHALT A. GENERAL- 1. The asphaltic concrete surface course shall be in accordance with Palm Beach County, Florida Department of Transportation Standard Specifications for type S-III asphaltic concrete wearing surface, 1 -1/2 inches in compacted thickness or as indicated on the Drawings, in accordance with Sections 330-10 Compacting Mixture and 331 Type S-III Asphaltic Concrete of aforesaid DOT standard specification. 2. Final lift of asphaltic concretes shall be virgin material only and shall be placed at the end of the project. (First lift may be RAP, reclaimed asphaltic paving, in accordance with DOT standards). 02741-6 2.06 SEAL COATING A. Homogeneous mixture of emulsified coal tar pitch, asbestos, sand and other inert fillers. It shall be easily remixed if settlement occurs in storage (except in the case of freezing). It shall be capable of application and complete coverage by rubber squeegee, brush, or approved mechanical method, to the surface of bituminous pavements at the spreading rate of 0.2 to 0.3 gallons per square yard in two coats. B. Approved product: "TARFEV manufactured by Bitucote Products Co. or approved equal. PART 3 — EXECUTION 3.01 COLD MILLING A. Milling of existing asphalt pavement shall be at the depth and location as indicated on the Construction Drawings or as directed by the Owner. B. The milled surface shall be reasonably smooth and free of excessive scarification marks, gouges, ridges, continuous grooves, or other damage. The milled pavement surface shall be thoroughly cleaned of all loose aggregate particles, dust, and other objectionable material by the use of power brooms, power blowers, power vacuums or other means. C. The Contractor shall coordinate the adjustment of manhole, meter boxes, drainage inlets, and valve boxes with the milling operation. D. All milled material shall become the property of the Contractor and shall be disposed of off-site or used in conformance with Section 02300 or for utilization as Reclaimed Asphalt Pavement, in conformance with the specification provided above, as approved by the Owner. 3.02 PATCHING A. Hot-Mix Asphalt Pavement: Saw cut perimeter patch and excavate existing pavement section to sound base. Excavate rectangular or trapezoidal patches, extending 12-inches into adjacent sound pavement, unless otherwise indicated or directed by the Owner. Re- 02741-7 compact existing unbound-aggregate base course to form new subgrade. B. Tack Coat: Apply uniformly to vertical surfaces abutting or projecting into new, hot-mix asphalt paving at a rate of 0.05 gallons per square yard. C. Patching: Fill excavated pavements with hot-mix asphalt base mix, and while it is still hot, compact flush with adjacent surface. 3.03 BARRICADES A. Provide substantial temporary barricades around all areas of operation and maintain until Work under this section is completed and approved. B. Install temporary traffic markers, signals, and signs as per Palm Beach County Highway Construction & Engineering Services Division Standard Specification to- 1. Eliminate potentially hazardous conditions. 2. Maintain adequate traffic patterns free of conflict with work under this Contract. 3.04 PREPARATION OF SUBGRADE A. This Work consists of bringing the bottom of excavations and top of embankments of the roadway between the outer limits of the shoulders or base course to a surface conforming to the grades, lines, and cross sections shown on the plans. The subgrade shall be of uniform density ready to receive the rock base of the paving course. B. All soft and yielding material and other portions of the subgrade which will not compact readily shall be removed and replaced with suitable material and the entire subgrade brought to line and grade to provide a foundation of uniform compaction and supporting power. C. Stumps, roots, and other deleterious organic matter encountered in the preparation of the subgrade shall be removed. D. Where fills are required on areas covered or partly covered by existing paving, the entire area of such existing paving shall be scarified to a depth of at least six inches, and the scarified material spread evenly over the area to be filled to a width not less than that of the proposed paving. 02741-8 E. Material for fills shall consist of sand or other suitable material approved by the Engineer free from stumps, roots, brushes, and other deleterious organic matter. F. Where fill is more than 1-foot in depth, the backfill material above the ground water table shall be compacted in 8-inch depth lifts or as noted on the plans, whichever is less. Each individual layer of fill under the rock base shall have a density of 98% of the maximum density as determined by the AASHTO T-180 unless shown otherwise on the plans. Each individual layer of fill under the shoulder area shall have a density of 98% of the maximum density as determined by AASHTO T- 180, unless shown otherwise on the plans. G. The bottom of all excavated areas and the top of all fills where rock base is to be constructed shall be thoroughly compacted by rolling. Water shall be used to insure thorough compaction. The stability of the top 12- inch thickness of the subgrade immediately under the base, for the full base width plus 1-foot on each side, shall be minimum LBR 40. H. Bring subgrade which has been properly filled and shaped to a firm unyielding surface, by rolling an entire area with an approved power roller: 1. Thoroughly compact area inaccessible to the roller with approved hand tamper. 2. Apply water sufficiently to compact the subgrade where the subgrade is of a dry, sandy nature and cannot be rolled. I. The subgrade shall be maintained free from ruts, depressions or other irregularities until rock base material is spread. J. For all roads, streets and paved areas other than State Highway, the stabilized subgrade shall have a minimum Limerock Bearing Ratio (LBR) of 40, unless otherwise noted on the plans. K. Where the bearing value of the existing subgrade is adequate without addition of stabilizing material, the subgrade shall be scarified and disked, harrowed, bladed or tilled for removal of boulders, roots, etc. to assure uniformity and thorough mixing of material to the full width and depth of required stabilization. The compacted subgrade shall conform to the lines, grades and cross-section shown on the plans. L. Test subgrade for crown and elevation after preparation and immediately before base of paving course is laid: 02741-9 1. Remove or add material and compact to bring to a correct elevation and uniform bearing if the subgrade is found not to be at the specified elevation at all points. 2. Adjust the manhole rims, catch basin frames and valve boxes where necessary to match proposed finish grade. 3.05 CONSTRUCTION OF BASE COURSE A. This Work consists of construction of lime rock base course for the asphaltic concrete wearing surface. The base course shall be constructed on the prepared subgrade in an 8-inch thick limerock bases constructed in two 4-inch lifts as shown on the drawings. Twelve (12) inch thick limerock bases shall be constructed in two six-inch lifts. The limerock base shall be a minimum LBR of 100. B. Spreading Rock: The rock shall be transported to the points where it is to be used over rock previously placed, and dumped on the end of the preceding spread. It shall then be spread uniformly with hand tools, or mechanical equipment. In no case shall rock be dumped directly on the subgrade. No hauling shall be done over the subgrade. C. Compacting Rock: 1. Following spreading, the rock shall be rolled with a three wheel roller weighing not less than ten tons, water being added as required, until the entire depth of base is compacted into a dense unyielding mass. 2. No greater are of rock base shall be placed during any one day than that which can be rolled and compacted on the same day. D. Finishing Base- l. After watering and rolling, the entire surface shall be thoroughly scarified to a depth not less than 4-inches and shaped to exact crown and cross section, re-watered and again thoroughly rolled. Rolling shall continue until the entire depth of base is bonded and compacted into a dense, unyielding mass, true to grade and cross section. a. Any irregularities which may develop in the surface during such finishing shall be corrected by the removal or addition of 02741-10 rock as the case may be. b. If at any time the subgrade material becomes churned up and mixed with the base rock, the Contractor shall dig out and remove the mixture, reshape and compact the subgrade and replace the materials removed with clean rock which shall be watered and rolled until satisfactorily compacted. c. Where cracks or checks appear in the base either before or after priming, which in the opinion of the Engineer would impair the structural efficiency of the base course, the Contractor shall remove such cracks or checks by re- scarifying, reshaping, watering, rolling and adding rock where necessary. d. During final compacting operations, if grading of any areas are necessary to obtain the true grade and cross section, the compacting operations for such areas shall be completed prior to making the density tests on the finished base. E. Inferior Rock: If in the opinion of the Engineer at any time during the progress of the Work, rock of inferior quality is being delivered to the construction site, a laboratory analysis of the rock shall be made. Should the results of such tests indicate that the rock does not conform to specifications, the Contractor shall, at his own expense, remove such inferior material from the area indicated and deliver and spread satisfactory rock on said area. F. Testing Surface: The finished surface of the rock base shall be true to the required cross section. Any irregularities in the grade greater than 1/4-inch, as determined by placing a 10-foot straight edge parallel with the centerline and use of full width crown board, shall be corrected by scarifying to a depth of 3-inches, removing or adding rock as may be required and again watering, rolling, and compacting the scarified area. In testing the surface for irregularities, the measurements under the straight edge shall not be taken in small holes caused by individual pieces of rock having been pulled out by the road grader. The finished rock base shall provide positive flow from the high point to the low point (catch basin/inlet) as indicated on the Contract Drawings. G. Thickness Determination: Thickness of the base shall be measured by intervals as required by the Engineer. Measurements shall be taken at various points on the cross section. The measurements shall be taken in holes through the base of not less than 3-inches in diameter. Where the base is more than 1/2-inch less than the required compacted thickness, the Contractor shall correct such areas by scarifying and 02741-11 adding rock. The affected areas shall then be watered, rolled and brought to a satisfactory state of completion, and of required thickness and cross section. H. Density: Density determinations shall be made by the Contractor or at intervals required by the Engineer. An average required density shall be 98% of maximum density obtainable under AASHTO Method T-180. No section of base shall be accepted when more than 10% of tests fall below 98% of maximum density and in no case shall a density of less than 96% of maximum be accepted. I. Testing: The Contractor shall coordinate with the Engineer for all testing. One test shall be made in accordance with AASHTO, T-180 for each class of material in the subgrade and base: 1. In place density tests in accordance with AASHTO T-147 shall be made in the locations shown on the plans. Two copies of the test reports will be sent directly to the Engineer for evaluation. 2. Any material which fails to meet these specifications shall be removed, replaced, and retested, all at the Contractor's expense. 3. Tests shall be taken at least every 1,000 square yards and taken at locations and lifts as directed by the Engineer. 3.06 PRIME COAT FOR BASE COURSE A. Cleaning for prepared base- 1. Before any bituminous material is applied, all loose material (dust, dirt, caked clay and foreign matter) which might prevent proper bond with the existing surface shall be moved to the shoulders, to the full width of the treatment, by means of revolving brooms or approved mechanical sweepers and by mechanical blowers, of approved types, supplemented by hand sweeping. Dust and other loose materials not removed by mechanical means shall be removed with hand brooms. Particular care shall be taken to clean the outer edges of the strip to be treated in order to ensure that the prime coat will adhere. Sweeping and blowing shall be continued until all the loose dust and dirt is removed from the surfaces. 2. Application of bituminous material shall be made during the same day surface has been swept and as soon as practical thereafter. B. Application for prime coat: 02741-12 1. The bituminous material shall be applied to the clean dry surface of the rock base at such temperature as will ensure uniform distribution. The amount applied will be at the rate of approximately 0.10 to 0.20 gallons per square yard of base area. The application shall be made by means of self-propelled pressure distributor operating under a pressure not less than 20 pounds per square inch. Application of bituminous material shall be made on only one-half of the width of base at one time. 2. The primed base shall then be covered with a uniform layer of clean sand, and kept thoroughly and uniformly covered by additional sand or sweeping until it shows no signs of picking up under traffic. For a period of one week after priming, the Contractor shall again broom any area where insufficient cover sand or excess of bituminous material causes "bleeding" and, if necessary, spread additional sand on such area. C. Prime coat finish: After prime has cured or sat and been sanded, the shoulder shall be shaped to conform to all grade lines and cross sections and the entire area shall be rolled and compacted with a rubber tired roller or a power roller before asphalt surface is laid on the finished base. 3.06 BITUMINOUS TACK COAT A. Before applying any bituminous material, all loose material: dust, dirt and foreign material, which might prevent proper bond with the existing surface, shall be removed for the full width of the application. B. Application for tack coat- 1. The surface to receive the tack coat shall be clean and dry. The tack coat shall be clean and dry. The tack coat shall be applied with a pressure distributor except that on small jobs, if approved by the Engineer, the application may be made by other approved mechanical methods or by hand methods. The pressure distributor shall operate at a pressure not less than 20 pounds per square inch and at a consistency such that it can be properly pumped and sprayed uniformly over the surface. 2. The bituminous material shall be applied in a thin uniform layer. The rate of application shall be between 0.02 and 0.10 gallon per square yard. The tack coat shall be applied sufficiently in advance of the laying of the wearing surface to permit drying, but shall not be applied so far in advance that it might lose adhesiveness as a result of being covered with dust or other foreign material. The tack coat surface shall be 02741-13 kept free from traffic until the wearing surface is laid. 3.07 ASPHALTIC CONCRETE WEARING SURFACE COURSE A. Cleaning and preparing base- 1. Prior to the laying of the asphaltic concrete, the base of pavement to be covered shall be cleaned of all loose deleterious material by the use of power brooms or blowers. A tack coat shall be applied on all pavement. The tack coat shall not be applied so far in advance of laying operations as to allow shifting and sand or weather conditions to nullify its effectiveness. 2. After the surface has been thoroughly cleaned, all holes shall be filled with asphaltic concrete, if necessary, and thoroughly compacted to conform to the existing surface and to form a smooth surface. B. Placing asphaltic concrete: The asphaltic concrete surface course applied after the tack coat and be permitted a reasonable time for drying, but not to an extent that the tack coat is allowed to lose its adhesiveness: 1. Machine spreading: Upon arrival the mixture shall be dumped into the approved mechanical spreader and immediately spread and struck off to the full width required and to such appropriate loose depth for each successive course that when the work is completed the required weight of the mixture per square yard or the specified thickness will be secured. An excessive amount of mixture shall be carried ahead of the screen at all times. Hand raking shall be done behind the machine as required. 2. Hand spreading: In limited areas, where, on account of irregularities or unavoidable obstacles, the use of mechanical spreading and finishing equipment is impractical, the mixture may be spread by hand, when so authorized by the Engineer. 3. The mixture shall be laid only when the surface to be covered is dry and only when weather conditions are suitable. 4. All structures which will be in actual contact with asphaltic mixture, including the face or surface of curbs or gutters and their vertical faces of existing pavements, shall be painted with a uniform coating of asphalt material to provide a closely bonded, watertight joint. 02741-14 5. Where necessary, due to the traffic requirements, the mixture shall be laid in strips in such manner as to provide for the passage of traffic. 6. Any mixtures caught in transit by a sudden rain may be laid at the Contractor's risk. In no case shall the mixture be laid while rain is falling or when there is water on the surface to be covered. 7. The depth of the layer being spread shall be gauged as directed, and where the thickness fails to average the specified thickness, immediate steps shall be taken to correct the depth. 8. Before any rolling is started, the course surface shall be checked, any inequalities adjusted, and all drippings, fat sand accumulations from the screed and fat spots from any source shall be removed and replaced with satisfactory material. 9. Straight-edging and back-patching shall be done after initial completion has been obtained and while the material is still hot. Any irregularity greater than 1/4-inch either longitudinally or traversely shall be corrected at this time. 10. No skin patching shall be done. When a depression is to be corrected while the mixture is hot, the surface shall be well scarified before the addition of fresh mixture. If irregularities occur and are not corrected while the mixture is still hot, the irregularities shall be cut out the full depth of the layer and replaced with fresh mixture. C. Compacting mixture: After the spreading, the mixture shall be rolled when it has set sufficiently or come to the proper condition to be rolled, and when the rolling does not cause undue displacement or shoving- 1. The motion of the roller shall at all times be slow enough to avoid displacement and shall at once be corrected by the use of rakes and fresh mixture where required. The rolling shall include all transverse, longitudinal, and diagonal rolling, as may be necessary to obtain the maximum density. 2. The seal rolling with tandem steel rollers weighing from five to eight tons shall follow as close behind the spreader as is possible without picking up, or displacing or blistering the material. 3. Rolling with the self-propelled pneumatic-tired rollers shall follow as soon as possible and as close behind the seal rolling 02741-15 as the heat of the mixture will permit. The rolling shall be done while pavement temperature is between 1750 and 2400 F, and to such an extent that the self-propelled traffic roller shall cover every area of the surface with at least ten passes. Final rolling with tandem steel rollers shall be done after the rolling with self-propelled pneumatic tired rollers is completed. This final rolling shall be done before the pavement temperature is lower than 175°F, and shall be continued until all roller marks or tire marks are eliminated. 4. Self-propelled pneumatic rollers shall be used for the rolling of patching and leveling courses. At the option of the Contractor, a steel-wheeled roller may be used to supplement the self-propelled pneumatic-tired rollers but not more than one steel-wheeled roller may be used in conjunction with the necessary number of self-propelled pneumatic-tired rollers. After final completion, the finished pavement shall at no point have a density less than 95% of the laboratory compacted density. 5. Rolling with the self-propelled pneumatic-tired roller shall proceed at a speed from six to twelve miles per hour and the rate of rolling shall not exceed 3,000 square yards per hour per roller. A sufficient number of self-propelled pneumatic- tired rollers shall be used so that the rolling of the surface for the required number of 10 passes within this maximum rolling rate shall not delay any other phase of the placing operation and not result in excessive cooling of the mixture before the rolling is complete. In the event that the rolling is not properly maintained to schedule as outlined above, the laying operation shall be discontinued until the rolling operations are sufficiently caught up. 6. In all places inaccessible to a roller, such as adjacent to curbs, headers, gutters, bridges, manhole, etc., the required compaction shall be secured with tamps. Depressions which may develop before the completion of the rolling shall be remedied by loosening the mixture laid and adding new material to bring such depressions to a true surface. 7. Should any depressions remain after final compaction has been obtained, the mixture shall be removed sufficiently and new material added to form a true and even surface. All high spots, high joints and honeycombs shall be adjusted as directed by the Engineer. 02741-16 8. The mixture, after compaction, shall be of the thickness shown on the plans. After compaction, the surface shall not show an excess of asphalt. Any area showing such excess or other defect shall be cut out and replaced with fresh mixture and immediately compacted to conform with the surrounding area. Any mixture which becomes loose or broken, mixed with dirt in the wearing course shall be removed and replaced with fresh mixture which shall be immediately compacted to conform with surrounding areas. 9. Gasoline or oil from rollers shall not be allowed to deposit on the pavement and any pavement damaged by such deposits shall be removed and replaced as directed by the Engineer. 10. Any mixture remaining unbonded after rolling shall be removed and replaced. D. Protection of pavement: After the completion of the pavement, no vehicular traffic of any kind shall be permitted on the pavement until it has set sufficiently as approved by the Engineer. 3.08 ASPHALT OVERLAY A. Clean existing asphalt and clear of loose aggregate. Mill roadway as required to maintain plan grades and provide a smooth transition between all overlay sections adjacent to milled or existing roadway sections. B. Risers shall be installed to bring existing manhole rims, valves, basins, etc to grade. C. Structural patching necessary to seal existing cracks or pot holes shall be done prior to tack coat. Tack coat shall be applied to ensure proper adhesion between the old surface and new asphalt. D. Hot mix asphalt shall be applied at the depth specified on the plans. All edges and ends shall be sloped to create a smooth seam between old and new pavement surfaces. 3.09 ABUTTING EXISTING PAVING A. Meet elevation of existing paving and structures, facilities and utilities where applicable by feathering the thickness of the new surface course for not more than 1-foot in the periphery of the structure, facility or utility. Do not cover access covers, manhole tops, water meters or other similar devices. 02741-17 3.10 PAVEMENT EDGES A. Make edges of paved area conform to details and sections as shown on drawings. 3.11 SEAL COATING A. Preparation of surface: Pavement to be sealed must be sound and free of loose dust, dirt, stones, or other foreign matter: 1. Repair any breaks or holes. 2. Scrape off accumulations of oil or fuel drippings and scrub with detergent and water. Remove all traces of detergent. 3. Soft or damaged spots must be repaired. 4. Flush entire area with clean water. 5. Pavement should be damp (no puddles or excess water) when seal coating is applied. B. Mixing: Stir seal coating to a uniform consistency, use no solvents for thinning. Dilute seal coating with 10% to 20% clean water, stirring to uniform consistency. C. Application- 1. Seal coat may be applied to dampened surface with a rubber squeegee, soft bristled push broom, or approved mechanized equipment. 2. Seal coating may be poured directly onto pavement in a ribbon or windrow. Squeegee is placed on pavement at a slight angle to edge line of pavement and pulled in a window along pavement in parallel lines, always working excess material toward bottom edge of squeegee. 3. Seal coating should be applied in two (2)thin coats. After first coat is completely dry to touch, a second coat may be applied at right angles to the first. Rate of application will depend on porosity of surface. 4. Allow to cure for 24 hours before opening to traffic. 5. Do not apply seal coating when temperature is below 50°F, or falling, before sealer is dry, or rain appears imminent or forecast. 02741-18 6. Apply in strict accord with manufacturers published instructions. 3.12 FIELD QUALITY CONTROL A. Test in place asphalt concrete course for compliance with requirements for thickness and surface smoothness. Repair or remove and replace unacceptable paving as directed by Engineer: 1. In-place compacted thickness will not be acceptable if exceeding following allowable variation from required thickness: a. Base Course: Not greater than '/2-inch of specified thickness. b. Wearing Course: Not greater than '/4-inch of specified thickness. 2. Test finished surface of each asphalt concrete course for smoothness, using 10-foot straight edge applied parallel with, and at right angles to centerline of paved area. Surfaces will not be acceptable if exceeding the following tolerances for smoothness. a. Base Course Surface: 1/4-inch. b. Wearing Course Surface: 1/8-inch. B. Check surface area at intervals as directed by the Engineer. C. Finish grade of asphaltic concrete wearing course shall be within ±0.04 feet of the grades indicated on the plans. 3.13 CLEANUP A. Remove all debris and excess material immediately from project site. B. Take down all barricades and temporary traffic markers, signals and signs only after all work included in this section is finished and inspected, and only after so directed by the Engineer. C. Leave project area clean, orderly and free of any hazardous conditions. END OF SECTION 02741-19 This page has been intentionally left blank. 02741-20 SECTION 02751 PORTLAND CEMENT CONCRETE PAVING PART 1 — GENERAL 1.01 RELATED DOCUMENTS A. All applicable provisions of the Bidding and Contract Requirements, and Division 1 - General Requirements shall govern the Work under this section. 1.02 SUMMARY A. This section includes all portland concrete pavement, including but not limited to- 1. Driveways 2. Parking lots 3. Curbs and gutters 4. Sidewalks 5. Drainage Aprons 1.03 WORK INCLUDED A. Provide all labor, materials, necessary equipment and services to complete the Portland Cement Concrete Paving work, as indicated on the drawings, as specified herein or both. B. Including, but not necessarily limited to the following- 1. Fill, subgrade, and limerock base 2. Concrete formwork 3. Concrete reinforcement 4. Isolation and contraction joints 5. Concrete paving 1.04 RELATED WORK A. Section 02300 — Earthwork 02751-1 B. Section 02741 - Asphaltic Concrete Paving - General 1.05 REFERENCE STANDARDS A. American Society of Testing Materials (ASTM) 1. A82 - Standard Specification for Steel Wire, Plain, for Concrete Reinforcement 2. A185 - Standard Specification for Steel Welded Wire Fabric, Plain, for Concrete Reinforcement 3. A615/A615M - Standard Specification for Deformed and Plain Billet-Steel Bars for Concrete Reinforcement 4. C33 - Standard Specification for Concrete Aggregates 5. C94 - Standard Specification for Ready-Mixed Concrete 6. C150 - Standard Specification for Portland Cement 7. C171 - Standard Specification for Sheet Materials for Curing Concrete 8. C260 - Standard Specification for Air-Entraining Admixtures for Concrete 9. C309 - Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete 10. C494/C494M - Standard Specification for Chemical Admixtures for Concrete 11. C979 - Standard Specification for Pigments for Integrally Colored Concrete 12. C1116 - Standard Specification for Fiber-Reinforced Concrete and Shotcrete 13. D1751 - Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types) 14. D1752 - Standard Specification for Preformed Sponge Rubber and Cork Expansion Joint Fillers for Concrete Paving and Structural Construction 15. D3405 - Standard Specification for Joint Sealants, Hot-Applied, 02751-2 for Concrete and Asphalt Pavements 16. D5249 - Standard Specification for Backer Material for Use with Cold- and Hot- Applied Joint Sealants in Portland-Cement Concrete and Asphalt Joints 17. D5893 - Standard Specification for Cold Applied, Single Component, Chemically Curing Silicone Joint Sealant for Portland Cement Concrete Pavements B. American Concrete Institute (ACI) 1. 301 R-99- Specifications for Structural Concrete 2. 304R- Placing and Handling Concrete, etc. 3. 309R-96- Guide for Consolidating of Concrete 4. 330.1 - Standard Specifications for Plain Concrete Parking Lots 5. 330R-92- Guide for Design & Construction of Concrete Parking Lots 6. 211.1 R-91 -Standard Practice for Selecting Proportions for Normal, Heavyweight and Mass Concrete C. American Association of State Highway and Transportation Officials (AASHTO) 1. M182 - Standard Specifications for Burlap Cloth made from Jute for Kenaf 2. M 153 - Standard Specifications for Preformed Sponge Rubber and Cork Expansion Joint Filler 1.06 QUALITY ASSURANCE A. Requirements of Regulatory Agencies: Perform work in accordance with local building and other applicable codes. B. Installation: Performed only by skilled workmen with satisfactory record of performance on completed projects of comparable size and quality. C. Inspection and Testing: Performed in accordance with Sections 01330, and 01410 unless otherwise specified: 1. Test cylinders- as per ASTM C-39. a. Minimum of three (3) concrete test cylinders shall be taken 02751-3 for every 75 or less cubic yards of concrete placed. b. Minimum of one (1) additional test cylinder shall be taken during any cold weather concreting, and be cured on job site under same conditions as the concrete it represents. 2. Slump test- as per ASTM C-143: a. Minimum of one (1) slump test shall be taken for each set of test cylinders taken. 1.07 SUBMITTALS A. Test Reports: Reports of concrete compression, yield, air content, and slump tests. B. Certificates: 1. Manufacturer's certification that materials meet specification requirements. 2. Material content on a cubic yard basis of each class of concrete furnished. a. Dry weights of cement. b. Saturated surface-dried weights of fine and coarse aggregate. c. Quantities, type and name of admixtures. d. Weight of water. 3. Ready-mix delivery tickets, ASTM C-94. C. Shop Drawings- 1. Show sizes and dimensions for fabrication and placing of reinforcing steel and bar supports. 2. Indicate bar schedules, stirrup spacing, and diagrams of bend bars. 1.08 DELIVERY, STORAGE AND HANDLING A. Deliver reinforcement to project site in bundles marked with metal tags indicating bar size and length. 02751-4 B. Handle and store materials to prevent contamination. 1.09 JOB CONDITIONS A. Allowable concrete temperatures- 1. Hot weather: Maximum 90°F as per ASTM C-94. B. Do not place concrete during rain, unless protection is provided. PART 2 -PRODUCTS 2.01 FILL A. As specified in Section 02741- Asphaltic Concrete Paving - General 2.02 SUBGRADE A. As specified in Section 02741 -Asphaltic Concrete Paving-General 2.03 LIMEROCK BASE A. As specified in Section 02741 -Asphaltic Concrete Paving- General 2.04 READY-MIXED CONCRETE A. Cement: ASTM C-150, normal Type 1. B. Aggregate: ASTM C 33, uniformly graded, from a single source. C. Water/Ready Mix Concrete: ASTM C 94. D. Admixtures: Certified by manufacturer to contain not more than 0.1 % water-soluble chloride ions by mass of cement and to be compatible with other admixtures, as follows: 1. Air-Entraining Admixture: ASTM C 260; 2. Water-Reducing Admixture: ASTM C 494, Type A; 3. Water-Reducing and High-Range Admixture: ASTM C 494, Type F; 4. Water-Reducing and Accelerating Admixture: ASTM C 494, Type E; and, 5. Water-Reducing and Retarding Admixture: ASTM C 494, Type D. 6. Fly ash and pozzolans: ASTM C-618. 02751-5 E. Coarse aggregate: Not less than 50% clean, hard, croshed stone conforming to requirements of Table 2, size number 467 ASTM C-33. F. Slump Range: 2-4 inches tested according to ASTM designation C- 143 (AASHTO- T119). G. Air content: 5% ± 1%. H. Mix proportioning: 1. 28-day compressive strength of cured laboratory samples 3,000 psi. 2. Minimum cement content 5 sacks/cubic yard. I. Calcium Chloride: The use of calcium chloride or admixtures containing more than 0.05% chloride ions is prohibited. J. Curing Materials: 1. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. dry; 2. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap- polyethylene sheet; 3. Water: Potable; 4. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete; 5. Clear Solvent-Borne Liquid-Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B; 6. Clear Waterborne Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B; 7. White Waterborne Membrane-Forming CuringCompound; ASTM C 309, Type 2, Class B. K. Mixes- 1. ASTM C-94. 2. Mix concrete only in quantities for immediate use. 3. Do not retemper or use set concrete. 02751-6 2.05 CONCRETE MIXES AND MIXING A. Concrete Mixes: Prepare design mixes, proportioned according to ACI 211.1 R-91 and ACI 304, with the following properties: 1. Compressive Strength (28 Days): 3,000 psi; (curb/sidewalk) B. Coloring Agent: When required, add coloring agent to mix according to manufacturer's written instructions. 1. Expansion and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt- saturated cellulosic fiber, or ASTM D 1752, cork or self-expanding cork; and, 2. Coloring Agent: ASTM C 979, synthetic mineral-oxide pigments or colored water-reducing admixtures; color stable, nonfading, and resistant to lime and other alkalis. C. Ready-Mixed Concrete: Comply with requirements and with ASTM C 94 and ASTM C 1116. D. Project-Site Mixing: On-site mixing must be approved by the Owner. Comply with requirements and measure, batch, and mix concrete materials and concrete according to ASTM C 94. Mix concrete materials in appropriate drum-type batch machine mixer. 2.06 REINFORCEMENT A. Reinforcing Steel Bars: 60 ksi yield strength; deformed billet steel bars; ASTM A-615, plain finish. B. Welded Steel Wire Fabric: Plain type, ASTM A-185, hot dip galvanized, plain finish. C. Tie Wire: FS QQ-W-461-G, annealed steel, black, 16 ga. minimum. D. Bar Supports: Conform to "Bar Support Specifications," CRSI Manual of Standard Practice. 2.07 FORMWORK AND ACCESSORIES A. Formwork: Matched, tight fitting and adequately stiffened to support weight of concrete without deflection detrimental to tolerances and appearance of concrete, conform with ACU 347, Chapter 3, Material and Form Work. 02751-7 B. Lumber- 1. Softwood framing lumber: Kiln dried, PS-20. 2. Boards less than 1-1/2-inch thick and 2-inches wide, used for basic forms and form liners: Kiln dried. 3. Grade marked by grading rules agency approved by American Lumber Standards Committee. 4. Light framing or studs for board or plywood forms, 2-inches to 4- inches width and thickness, construction standard grade. 5. Boards for basic forms, construction standard grade. 6. Board surface: Smooth. C. Plywood- 1. Exterior type softwood plywood, PS 1-66. 2. Each panel stamped or branded indicating veneer grades, species, type and identification. 3. Wood faced plywood for Architectural concrete surfaces. a. Panel veneer grades: B-C b. Mill-oiled sides and mill-sealed edges of panels. D. Ties 1. Material: Steel 2. Type: Snap tiles 3. Depth of break back: 1-inch E. Max. diameter: 1/4-inch F. Form coatings: 1. Non-staining type. 2. Agent: Pine oil derivative. 02751-8 2.08 ISOLATION AND CONTRACTION JOINTS A. Minimum 3/4-inch thick asphaltic impregnated fiberboard as per ASTM D- 1751. 2.09 JOINTS, FILLERS, AND SEALANTS A. Joint-Sealant Backer Materials: ASTM D5249, Non-Staining, compatible with joint substrates, sealants, primers, and otherjoint fillers; and approved for applications indicated by joint sealant manufacturer based on field experience and laboratory testing. B. Joint Sealant: Non-priming, pourable self-leveling silicone sealant for concrete and asphalt. 1. Cold-Applied Joint Sealant ASTM D5893, self leveling silicone sealant. Crafco Inc. "Roadwaver Silicone-SL"; Dow Coming "888, or 890- SL"; Sonneborn "Sonomeric 1 Sealant"; Tremco Wulkem 45"; or approved equal and, 2. Hot-Applied Joint Sealant: ASTM D3405, Polymeric sealant. Crafco Inc. "ROADSAVER 22"; W.R. Meadows, Inc. "SEALTIGHT HI-SPEC', or approved equal. C. Joint Fillers: Resilient pre-molded bituminous impregnated fiberboard units complying with ASTM D 1751, asphalt-saturated cellulosic fiber, ASSHTO M 153, Type I: or ASTM D 1752, cork or self-expanding cork. D. Exterior Concrete Sealant: Sonneborn "Kure-N-Sea130" exterior acrylic sealer, or Euclid "Super Rez-Seal", or approved equal. PART 3-EXECUTION 3.01 BARRICADES A. Provide substantial temporary barricades around all areas of operation and maintain until work under this section is completed and approved. B. Install temporary traffic markers, signals, and signs as per D.O.T. Standard Specifications to- 1. Eliminate potentially hazardous conditions. 2. Maintain adequate traffic patterns free of conflict with work under this Contract. 3.02 PREPARATION OF SUBGRADE A. Ensure rough grading has brought subgrade to required elevations. 02751-9 B. Fill soft spots and hollows with additional fill. C. Level and compact subgrade, to receive limerock base for concrete walks, curbs and gutters, to 98% compaction as per AASHTO T-180. 3.03 FORMWORK A. The Contractor is responsible for the design, construction, removal and complete safety of formwork and shoring. B. Form construction shall be provided to shape, lines dimensions of members shown: substantial, tight enough to prevent leakage, and properly braced or tied to maintain position and size, form sides and bottoms of members unless specifically excepted. C. Fill voids of plywood joints with sealant and tool smooth. D. Form vertical surfaces to full depth and securely position to required lines and levels. Ensure form ties are not placed so as to pass through concrete. E. Arrange and assemble formwork to permit easy dismantling and stripping, and to prevent damage to concrete during formwork removal. F. Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for pavement to required lines, grades, and elevations. 1. Maintain sufficient quantity of forms to allow continuance of work so that forms remain in place a minimum of 24 hours after concrete placement; 2. Forms shall be cleaned and casted with form release agent thoroughly after each use and before concrete is placed; and, 3. Flexible or curved forms shall be used on curves. Forms shall be of full depth of the concrete and of a strength when staked, sufficient to resist the presence of the concrete and the loads resulting from the finish operations without springing, setting or losing their shape. 3.04 REINFORCING A. Reinforce concrete curbs and gutters. Allow for minimum 1-1/2-inch concrete cover. 02751-10 B. Do not extend reinforcing through expansion and contraction ofjoints. Provide dowelled joints through expansion and contraction joints, with one end of dowels fitted with capping sleeve to allow free movement. 3.05 FORMING EXPANSION AND CONTRACTION JOINTS A. Construct pre-molded expansion and contraction joints, tied construction joints, thickened edge expansion joints, isolation joints, and construction joints, straight with face perpendicular to concrete surface. Construct transverse joints perpendicular to centerline unless otherwise detailed. 1. Expansion joints and contraction joints, pre-molded as indicated on the drawings: a. Provide joint filler for the entire depth of the slab section and not less than 1-inch below finished surface so as to allow for joint sealer. b. Provide thickened edge expansion joint as indicated on the drawings. C. Provide 1/2-inch contraction joints for curb and gutter at 10-feet on center. d. Provide 1/2-inch expansion joints for curb and gutter and sidewalk at 100-feet on center. 2. Tied construction joints: As indicated on drawings; 3. Control joints: Depth shall be equal to of the concrete thickness or 1-inch, whichever is deeper. For sidewalks, control joint spacing shall be equal to the sidewalk width. For concrete pavement, control joint spacing shall be placed as shown on the drawings, no greater than 15-feet on center either way; a. Form tooled joints in fresh concrete by grooving top portion with recommended tool and finishing edges with jointer. b. Form sawed joints using powered saws equipped with shatterproof abrasive or diamond-rimmed blades. Cut joints into hardened concrete within 24 hours of the concrete placement and as soon as surface will not be tom, abraded, or otherwise damaged by cutting action. 4. Construction Joints: Place construction joints at end of placements and at locations where placement operations are stopped for period of more than 1 h hour, except where such placements terminate at expansion joints. Construct joints using standard metal keyway-section forms or as shown on the drawings; 02751-11 5. Isolation Joints: Locate isolation joints as indicated on the drawings. Provide premolded joint filler for isolation joints abutting site lighting poles, concrete curbs, catch basins, maintenance access structures, inlets, structures, walks and other fixed objects; 6. Joint Fillers: Extend joint fillers full-width and depth of joint, and not less than 1-inch or more than 1-inch below finished surface where joint sealer is indicated. Furnish joint fillers in one-piece lengths for full width being placed, wherever possible. Where more than one length is required, lace or clip joint filler sections together; and, 7. Joint Sealants: All joints shall be sealed with approved exterior pavement joint sealants and shall be installed per manufacturer's recommendations. 3.06 INSPECTION A. Assure that excavation and formwork are completed, and excess water is removed. B. Check that reinforcement is secured in place. C. Verify that expansion joint material, anchors, and other embedded items are secured in position. 3.07 PREPARATION FOR PLACEMENT A. Notify the Engineer and other inspectors at least 36 hours prior to inspection. B. Equipment forms, and reinforcing shall be clean and wet down, reinforcing firmly secured in place, runways set up and not resting on or displacing reinforcing. 3.08 PLACING CONCRETE A. Concrete Placement Comply with recommendations in ACI 304R for measuring, mixing, transporting, and placing concrete. Place concrete in a continuous operation within planned joints or sections. 1. Moisten subbase to provide a uniform dampened condition at time concrete is placed; 2. Consolidate concrete by mechanical vibrating equipment supplemented by hand-spading, rodding, or tamping according to recommendations in ACI 309R; 02751-12 3. Screed and initial-float concrete surfaces with darby or bull float before excess moisture or bleed water appears on the surface; 4. Protect concrete from cold or hot weather during mixing, placing, and curing; and, 5. All concrete walks and aprons shall be a minimum of 4-inches thick as shown on the drawings, with a turned down edge as detailed. B. Evaporation Retarder: Apply to concrete surfaces if hot, dry, or windy conditions exist. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing. C. Pavement Tolerances: Comply with tolerances in ACI 330.1, Specification for Plain Concrete Parking Lots. D. Place concrete, screed and wood float surfaces to a smooth and uniform finish, free of open texturing and exposed aggregate. E. Avoid working mortar to surface. F. Round all edges, including edges of expansion and contraction joints, with '/2- inch of radius edging tool. G. Where concrete curbs are adjacent to pavement slabs, make concrete curbs and gutters integral with slabs. Make expansion and contraction joints of curbs coincide with slab joints. H. Ensure finished surfaces do not vary from true lines, levels or grade by more than 1/8-inch in 10-feet when measured with straightedge. I. Apply curing compound on finished surfaces immediately after finishing. Apply in accordancewith manufacturer's recommendations. 3.09 FINISHES AND CURING A. All exterior concrete shall receive a medium broom finish. B. Curing: Begin curing after finishing concrete, but not before free water has disappeared from concrete surface. Cure concrete by one or a combination of the following methods- 1. Moisture cure concrete by water, continuous fog spray, continuously wet 02751-13 absorptive cover, or by moisture-retaining-cover curing. Keep surfaces continuously moist for at least 22 hours; and, 2. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating and repair damage during curing period. 3. Contractor shall protect against graffiti and other damages to finish, prior to curing and acceptance. 4. No sidewalk installed by the Contractor with visible cracks will be accepted by the Owner. Cracked sidewalk shall be removed, disposed of and replaced by the Contractor at no cost to the Owner. Cracked sidewalk replacement shall consist of a minimum of one flat (5-feet) of sidewalk. C. All exterior concrete surface shall receive one coat of exterior sealer. 3.10 ADA DETECTABLE WARNINGS A. Detectable warnings shall be installed at all locations where required, compliant with ADA guidelines and FDOT Index 304. 3.11 REPAIRS AND PROTECTION A. Remove and replace concrete pavement that is broken, damaged, or defective, or does not meet requirements in this section. B. Protect concrete from damage. Provide adequate traffic control to prevent traffic from pavement for at least 14 days after placement. C. Maintain concrete pavement free of stains, discoloration, dirt, and other foreign material. Sweep concrete pavement not more than 2 days before date scheduled for substantial completion inspections. D. Protection of Completed Work: During curing period, protect concrete from damaging mechanical disturbances, water flow, loading, shock, and vibration. 3.12 QUALITY ASSURANCE A. Manufacturer Qualifications: Manufacturer of ready-mixed concrete products complying with ASTM C 94 requirements for production facilities and equipment. 02751-14 B. ACI Publications: Comply with ACI 301 R-99 and AC1330R-92, unless modified by the requirements of the Contract Documents. C. The Owner shall provide and pay for testing services. A slump test and air test shall be performed for each load delivered. Four standard test cylinders shall be taken for each 55 cubic yards of concrete or each days' pour, whichever is more frequent. Two cylinders shall be broken at 7 days and two cylinders shall be broken at 28 days. 3.13 CLEAN UP A. Remove all debris and excess material immediately from project site. B. Take down all barricades and temporary traffic markers, signals and signs only after all work included in this section is finished and inspected, and only after so directed by Owner or Engineer. C. Leave project area neat, orderly and free of any hazardous conditions. END OF SECTION 02751-15 This sheet has been intentionally left blank. 02751-16 APPENDIX A - OWNER ACQUIRED PERMITS Ron DeSantis Mission: Governor To prated,promote&improve the health of all people in Florida through integrated ed� Ua1 �,r� Scott A. Rivkees,MD state,county&community efforts. State Surgeon General WWII Vision:To be the Healthiest State in the Nation Notification of Acceptance of Use of a General Permit Permitee: Permit Number: 138296-044-DSGP Matthew Hammond, Utility Director Issue Date: 05/06/2020 Village of Tequesta Expiration Date: 05/05/2025 345 Tequesta Drive County: Palm Beach Tequesta, FL 33469 Project: Beach Road Water Main Replacement Water Supplier: Village of Tequesta PWS ID: 450 1438 Dear Mr. Hammond: On April 20, 2020 the Florida Department of Health-Palm Beach County, as an approved local program of the Florida Department of Environmental Protection, received a "Notice of Intent to Use the General Permit for Construction of Water Main Extensions for PWSs" [DEP Form No. 6 - , under the provisions of Rule 62 4„,530 and Chapter 5 .1655, Florida Administrative Code (F.A.C.). The proposed project includes Replacement of approximately 3,200 LF of 8"Asbestos Cement water main with 10" PVC water main to provide potable water located between 400 S. Beach Road and 19670 S. Beach Road in the Village of Tequesta, Florida. Based upon the submitted Notice and accompanying documentation, this correspondence is being sent to advise that the Department does not object to the use of such general permit at this time. Please be advised that the permittee is required to abide by Rule 62 555.405 F. A.., all applicable rules in Chapters 6 4, 62...550, 62 555, F.A.C., and the General Conditions for All General Drinking Water Permits (found in 62��4.540„ F.A,C.). When any existing asbestos cement(AC) pipes are replaced under this permit, the permittee shall do so in accordance with the applicable rules of the Federal Asbestos Regulation and Florida DEP requirements. For specific requirements applicable to AC pipes, the permittee should contact the Air and Waste Management section managers prior to commencing any such activities at (561) 837- 5900#3. Please be aware that a notification is required to be submitted to the Department for a regulated project. Florida Department of Health Palm Beach County,Division of Environmental Public Health P.O.Box 29,800 Clematis Street,West Palm Beach,FL 33402 a w rIIC Healttll :reditors �, .IY r6 PHONE:561-837-5900-FAX: 561-837-5294 FloridaHealth.gov, Flhealthpaimbeach.org PERMITTEE:Village of Tequesta Perm it/Certification No.: 138296-044-DSGP Matthew Hammond, Utility Director The permittee shall comply with all sampling requirements specific to this project. These requirements are attached for review and implementation. Pursuant to Rule 0 -5 .3 F.A.C., the permittee shall submit a certification of construction completion (DEP Form No. 0� .g00 g' to the Department and obtain approval, or clearance, from the Department before placing any water main extension constructed under this general permit into operation for any purpose other than disinfection or testing for leaks. Within 30 days after the sale or legal transfer of ownership of the permitted project that has not been cleared for service in total by the Department, both the permittee and the proposed permittee shall sign and submit an application for transfer of the permit using Form -,55a00 with the appropriate fee. The permitted construction is not authorized past the 30-day period unless the permit has been transferred. This permit will expire five years from the date of issuance. If the project has been started and not completed by that time, a new permit must be obtained before the expiration date in order to continue work on the project, per Rule L62 4,030, F.A.Q. Sincerely, For t e Division irec JorgeqRno, P.E., Environmental Administrator Division of Environmental Public Health JH/JP c: Project Engineer: Samantha Graybill, P.E. Utility: Same PERMITTEE:Village of Tequesta Permit/Certification No.: 138296-044-DSGP Matthew Hammond, Utility Director Civil Penalty May Be Incurred if this Proiect is placed into operation before obtaining a clearance from this office. Requirements for clearance upon completion of projects are as follows: 1) Clearance Form Submission of a fully completed Department of Environmental Protection (DEP) Form 2-555, Certification of Construction Completion and Request for Clearance to Place Permitted PWS Components into Operation. 2) Record Drawings Submission of the portion of record drawings showing deviations from the DEP construction permit, including preliminary design report or drawings an specifications, if there are any deviations from said permit(Note that it is necessary to submit a copy of only the portion of record drawings showing deviations and not a complete set of record drawings.). 3) Bacteriological Results Copies of satisfactory bacteriological analysis (a.k.a. Main Clearance), taken within sixty (60) days of completion of construction, from locations within the distribution system or water main extension to be cleared, Water Works Association with 62-555,315 % on (AWWA) Standard 651 92, as L-665,2�LQ, anfollows: J=' F.A.C. and • Connection to an existing system • The end point of the proposed addition • Any water lines branching off a main extension • Every 1,200 feet on straight runs of pipe Each location shall be sampled on two consecutive days, with sample points and chlorine residual readings clearly indicated on the report. A sketch or description of all bacteriological sampling locations must also be provided. All samples shall be collected by an employee of a state certified laboratory or a certified operator and be reported on DEP Reporting Format 62- 650.730. For further clarification contact: Jay Hardman, P.E. Florida Department of Health Palm Beach Plan Review& Permit Section 800 Clematis Street, 4th Floor West Palm Beach, FL 33401 561-837-5900#5 NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs INSTRUCTIONS:This notice shall be completed and submitted by persons proposing to construct projects permitted under the "General Permit for Construction of Water Main Extensions for Public Water Systems"in Rule 62-555.405,F.A.C. AT LEAST 30 DAYS BEFORE BEGINNING CONSTRUCTION OF A WATER MAIN EXTENSION PROJECT,complete and submit one copy of this notice to the appropriate Department of Environmental Protection(DEP)District Office or Approved County Health Department (ACHD)along with payment of the proper permit processing fee. (When completed,Part II of this notice serves as the preliminary design report for a water main extension project,and thus,it is unnecessary to submit a separate preliminary design report or drawings, specifications,and design data with this notice.) All information provided in this notice shall be typed or printed in ink. The DEP permit processing fee for projects requiring the services of a professional engineer during design is$650,and the DEP permit processing fee for projects not requiring the services of a professional engineer during design is$500.* Some ACHDs charge a county permit processing fee in addition to the DEP permit processing fee. Checks for permit processing fees shall be made payable to the Department of Environmental Protection or the appropriate ACHD. NOTE THAT A SEPARATE NOTIFICATION AND A SEPARATE PERMIT PROCESSING FEE ARE REQUIRED FOR EACH NON-CONTIGUOUS PROJECT.t * Except as noted in paragraphs 62-555.520(3)(a)and(b), F.A.C.,projects shall be designed under the responsible charge of one or more professional engineers licensed in Florida. t Non-contiguous projects are projects that are neither interconnected nor located nearby one another(i.e., on the same site, on adjacent streets, or in the same neighborhood). � � Y �Rd A. Name°fPr°ject- Beach Watermain Replacement B. Description of Project and Its Purpose: Replacing 3,200 LF of 8"AC watermain with a 10" PVC watermain. The existing AC pipe will be abandoned in place or removed and properly disposed of according to PBCHD regulations. El C. Location of Projecti 1. Poo Palm Beach County 2. Description f Project Location: on: Review West side of Beach Rd in Tequesta, FL between 400 S Beach Rd and Q196�S each Rd. D. Estimate of Cost to Construct Project:$700,000 E. Estimate of Dates for Starting and Completing Construc tion of Project: May 2020-September 2020 F. Permittee PWS/Com an Name village ofTe uesta on-Transient Non Communft Tr' _LPWS Identification No.:*45 �; ..".. ._ 01438 �._...w anstent Non Communta> Consecutive Contact Person:Matthew Hammond,Pe Non T " ContactmPerson's Mailm2 Address 345 Te Contact Person's Title:utuay Director _. _..._ ._...--- quests Drive _........ . .,� c. —City:villa a of T quests _....... State FL Code 33469 Contact Person's E-Mail Address:mhammond to uest _ � � .". " Contact P 's Telephone Number 56t 766 045sm Contact Person's Fax Number: _ @ q a.org — �..ma. G. Public Water q y f p ... m...te ....... Thisinformation em PWS Su �l�tnl Water to ee is a public water system(PWS). TW ) l Project is required only a the permit tee FP Te uesta water Treatment Plant Villageq .... — .m ...... .438 PWS Owner: r" _ PWS Identification No 4501 ,� •_ Communtt w� Non Transt � � _ onsecutive of Tequesta _ ent Non Commumt Transient Non Commtuut C mm ...... _ ..�— Contact Persons Mailing Address:E -^_""°'"' _ Contact Person's Title:Utility Director Contact Person Matthew Ha tP _ ��.. ' 345 Tequesta Drive Ctt Village of Teque 11 sta CpritaFL — State FL D one Contact Person s Eontact Person's eMah Address:ss bmnammonde�equest Person's Fax _. 59 'APR " mharnmond@tequesta.org DEP Form 62555.900(7)Altemate Page 1 � 1��� ...... _.. Effective August 28,2003 (Updated September8,2015) Florida Department of Health-PBC Plan Review NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs P,rOleCt Nlirlt Beach Rd Waterrnain Replacement Permittee:Village of Tequesta _H Public Water ,stern -� Own a _ After ItIs Placed into Permanent OpPeWratSi on PWS Name:Vi Village of Tequesta staWater TreatmentmePlant Id e�nhficahon No.:*4501_43e — PWS T e:* ■ i Communilw Non-Transient Non�-Communm.mi..ly Transient Non--C_.ommuml ......ne .. .. secut_ive PWS Owner:Village of Tequesta Contact Person:Matthew Hammond,PE y _ Contact Person s Title utult Director Contact Person's Mailin Address 345 Tequesta Drive _. State FIL �- 1 Code 33469 Number: Cit),,.Village of Tequesta Z Contact Persons Telephone Number:561-768-0459 Contact Persons Fax Num — Contact Person's E-Mail Address:mhammond@tequesta.org * This information is required only if the owner/operator is an existing PWS. 1. Professional Engineer(s)or Other Persons in Responsible Charge of Designing Project* Com an"J Name:Kimley-Horn&Associates Designer(s): Title(s)of Designer(s): Samantha C. raybill, PE Project Engineer...........- Qualifications of Designer(s): Professional Engineer(s)Licensed in Florida—License Number(s): 81326 Public Officer(s)Employed by State,County,Municipal,or Other Governmental Unit of Stater' n Plumbing Contractor(s)Licensed in Florida—License Number(s):^ Mailing Address of De g);1920 Wekiva Way,Suite 200 .._ si raer( ... �. _ City West Palm Beach i Code:33411 Telephone Number of Designer(s'):561290-095s _ .. .„ _ _._------___.._..... Fax Number of Designer(s,): State: E-MailAddress(es)ofDesigner(s):Samantha.graybill@kimIey-I' orn.com ­..n._. .....—........—...................... .........._........�.. ......... ..........—..m............_ —....�.............................-............................ .....�.. * Except as noted in paragraphs 62-555.520(3)(a)and(b),F.A.C.,projects shall be designed under the responsible charge of one or more professional engineers licensed in Florida. t Attach a.d tailed construction cost estimate showing that the cost to construct this project is$10,000 or less. Attach do mentation showing.At._this project will be installed by the plumbing contractor(s)designing this project, documentation showing that this project involves a public water system serving a single property and fewer than 250 fixture units, and a detailed construction cost estimate showing that the cost to construct this project is$50,000 or less. ASice Area; ater Use;anPRe ':I ress!re %:nation 1. Design Type and IiTumber of Sery Connec ,and Average Daily Water Demands and Maximum-Day Water Demands,in the Entire Area to Be Served by the Water Mains Being Constructed Under this Proi ct: D=Total Average C=Average Daily Daily Water Demanda, Water Demand Per gpd(Columns BxC for E=Total Maximum- B=Number of Service Service Connection, Residential Service Day Water Demandb, A=-TITS of Serviee Connection - Connections k*A Connections N g;d Sm;lleFamily Home 0 Mobile Home c Apartment c ... Commercial,Institutional,or Industrial Facili a _ ttli .........._- a_w - 4...............................i- ° a. Description of Commercial,Institutional,or Industrial Facilities and Explanation of Method(s)Used to Estimate Average Daily Water Demand for These Facilities: N/A b. Explanation of Peaking Factor(s)or Method(s)Used to Estimate Maximum-Day Water Demand: N/A DEP Forth 62-555.900(7)Altemale Page 2 Effective August 28,2003 jUpdated iidpteMber 8,;201'5), - NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN DEu._ — N R PWSs ..�.. � _._..EXTENSIONS FOR 1eCt Name B Watermarn Replacement Permtttee village of Tequesta 2. Explanation of Peaking Factor(s)or Method(s)Use each Rd ...—...,—... Teq _ d to Estimate Design Peak-Hour�..mm...�m Water Demand and for � �Small Water Systems that Use Hydropneumatic Tanks or that Are Not Designed to Provide Fire Protection,Peak Instantaneous Water Demand: N/A 3. Design Fire-Flow Rate and Duration: N/A 4. Design Service Pressure Range: �� B. Project Site Information """' — ~-- 1. ATTACH A SITE PLAN OR SKETCH SHOWING THE SIZE AND APPROXIMATE LOCATION OF NEW OR ALTERED w WATER MAINS SHOWING THE APPROXIMATE LOCATION OF HYDRANTS,VALVES,METERS,AND BLOW- OFFS IN SAID MAINS,AND SHOWING HOW SAID MAINS CONNECT TO THE PUBLIC WATER SYSTEM SUPPLYING WATER FOR THE PROJECT. 2. Description of Any Areas Where New or Altered Water Mains Will Cross Above or Under Surface Water or Be Located in Soil that Is Known to Be Aggressive: N/A C. Information About Compliance with Design and Construction Requirements 1. If this project is being designed to comply with the following requirements,initial in ink before the requirements. If any of the following requirements do not apply to this project or if this project includes exceptions to any of the following requirements as allowed by rule,mark"X"before the requirements and complete Part II.C.2 below. RSWW=Recommended Standards for Water Works as incorporated into Rule 62-555.330,F.A.C. z:;,Z7A'- a. This project is being designed to keep existing water mains and service lines in operation during construction or to minimize interruption of water service during construction. [RSWW 1.3.a;exceptions allowed under FAC 62- 555.3301 b. All pipe,pipe fittings,pipe joint packing and jointing materials,valves,fire hydrants,and meters installed under this project will conform to applicable American Water Works Association(AWWA)standards. [FAC 62-555.320(21)(b),RSWW 8.0,and AWWA standards as incorporated into FAC 62-555.330;exceptions allowed under FAC 62- 555.320(21)(c)] c. All public water system components,excluding fire hydrants,that will be installed under this project and that will come into contact with drinking water will conform to NSF International Standard 61 as adopted in Rule 62-555.335,F.A.C.,or other applicable standards,regulations,or requirements referenced in paragraph 62- 555.320 3 F.A.C. ( )( )]O(b), [FAC 62-555.320(3)(b);exceptions allowed under FAC 62-555.320 3 d d. All pipe and pipe fittings installed under this project will contain no more than 8.0%lead,and any solder or C flux used in this project will contain no more than 0.2%lead. [FAC 62-555.322] U e. All pipe and pipe fittings installed under this project will be color coded or marked in accordance with subparagraph 62-555.320(21)(b)3,F.A.C.,usingblue a redomi as p pant color. (Underground plastic pipe will be solid-wall blue pipe,will have a co-extruded blue external skin,or will be white or black pipe with blue stripes incorporated into,or applied to,the pipe wall;and underground metal or concrete pipe will have blue stripes applied to the pipe wall. Pipe striped during manufacturing of the pipe will have continuous stripes that run parallel to the axis of the pipe,that are located at no greater than 90-degree intervals around the pipe,and that will remain intact during and after installation of the pipe. If tape or paint is used to stripe pipe during installation of the pipe,the tape or paint will be applied in a continuous line that runs parallel to the axis of the pipe and that is located along the top of the pipe;for pipe with an internal diameter of 24 inches or greater,tape or paint will be applied in continuous lines along each side of the pipe as well as along the top of the pipe. Aboveground pipe will be painted blue or will be color coded or marked like underground pipe.) [FAC 62- 555.320(21)(b)3] x f. All new or altered water mains included in this project are sized after a hydraulic analysis based on flow demands and pressure requirements. ATTACH A HYDRAULIC ANALYSIS JUSTIFYING THE SIZE OF ANY NEW OR ALTERED WATER MAINS WITH AN INSIDE DIAMETER OF LESS THAN THREE INCHES. [FAC 62-555.320(21)(b)and RSWW 8.1] DEP Form 62-555.900(7)Altemate Page 3 Effective August 28,2003 (Updated September 8,2015) NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs PrO�eCt Name:Beach Rd Watennain Replacement � v Pernuttee,Vllage of Tequesta ,� �' g. The inside diameter of new or altered water mains that are included in this project and that are being designed to provide fire protection and serve fire hydrants will beat least six inches. [FAC 62-555.320(21)(b)and RSWW 8.1.2] h. New or altered water mains that are included in this project and that are not being designed to carry fire flows do not have fire hydrants connected to them. [FAC 62-555.320(21)(b)and RSWW 8.1.5] ,. L This project is being designed to minimize dead-end water mains by making appropriate tie-ins where practical. [FAC 62-555.320(21)(b)and RSWW 8.1.6.a] j. New or altered dead-end water mains included in this project will be provided with a fire or flushing hydrant or Y blow-off for flushing purposes. [FAC 62-555.320(21)(b)and RSWW 8.1.6.b] � . ` ' k. Sufficient valves will be provided on new or altered water mains included in this project so that inconvenience and sanitary hazards will be minimized during repairs. [FAC 62-555.320(21)(b)and RSWW 8.2] _ 1. New or altered fire hydrant leads included in this project will have an inside diameter of at least six inches and will include an auxiliary valve. [FAC 62-555.320(21)(b)and RSWW 8.33] 5 Y m. All fire hydrants that will be installed under this project and that will have unplugged,underground drains will be located at least three feet from any existing or proposed storm sewer,stormwater force main,pipeline conveying reclaimed water regulated under Part III of Chapter 62-610,F.A.C.,or vacuum-type sanitary sewer; at least six feet from any existing or proposed gravity-or pressure-type sanitary sewer,wastewater force main, or pipeline conveying reclaimed water not regulated under Part III of Chapter 62-10,F.A.C.;and at least ten feet from any existing or proposed"on-site sewage treatment and disposal system." [FAC 62-555.314(4)] n. At high points where air can accumulate in new or altered water mains included in this project,provisions will be made to remove the air by means of air relief valves,and automatic air relief valves will not be used in situations where flooding of the valve manhole or chamber may occur. [FAC 62-555.320(21)(b)and RSWW 8.4.1] X o. The open end of the air relief pipe from all automatic air relief valves installed under this project will be extended to at least one foot above grade and will be provided with a screened,downward-facing elbow. [FAC S rJ 62-555.320(21)(b)and RSWW 8.4.2] p. New or altered chambers,pits,or manholes that contain valves,blow-offs,meters,or other such water distribution system appurtenances and that are included in this project will not be connected directly to any sanitary or storm sewer,and blow-offs or air relief valves installed under this project will not be connected directly to any sanitary or storm sewer. [FAC 62-555.320(21)(b)and RSWW 8.4.3] q. New or altered water mains included in this project will be installed in accordance with applicable AWWA standards or in accordance with manufacturers'recommended procedures. [FAC 62-555.320(21)(b),RSWW 8.5.1,and AWWA standards as incorporated into FAC 62-555.330] r. A continuous and uniform bedding will be provided in trenches for underground pipe installed under this project;backfill material will be tamped in layers around underground pipe installed under this project and to a sufficient height above the pipe to adequately support and protect the pipe;and unsuitably sized stones(as described in applicable AWWA standards or manufacturers'recommended installation procedures)found in trenches will be removed for a depth of at least six inches below the bottom of underground pipe installed under this project. [FAC 62-555.320(21)(b),RSWW 8.5.2] m s. All water main tees,bends,plugs,and hydrants installed under this project will be provided with thrust blocks or restrained joints to prevent movement. [FAC 62-555.320(21)(b)and RSWW 8.5.4] J t. New or altered water mains that are included in this project and that will be constructed of asbestos-cement or polyvinyl chloride pipe will be pressure and leakage tested in accordance with AWWA Standard C603 or C605,respectively,as incorporated into Rule 62-555.330,F.A.C.,and all other new or altered water mains included in this project will be pressure and leakage tested in accordance with AWWA Standard C600 as incorporated into Rule 62-555.330. [FAC 62-555.320(21)(b)l and AWWA standards as incorporated into FAC 62-555.330] u. New or altered water mains,including fire hydrant leads and including service lines that will be under the control of a public water system and that have an inside diameter of three inches or greater,will be disinfected and bacteriologically evaluated in accordance with Rule 62-555.340,F.A.C. [FAC 62-555.320(21)(b)2 and FAC 62- 555.340] X v. New or altered water mains that are included in this project and that will be installed in areas where there are known aggressive soil conditions will be protected through use of corrosion-resistant water main materials, through encasement of the water mains in polyethylene,or through provision of cathodic protection. [FAC 62- 555.320(21)(b)and RSWW 8.5.7.d] DEP Form 62-555.900(7)Altemate Page 4 Effective August 28,2003 (Updated September 8,2015) ro NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs _ ame Beach Rd Watennam Replacement acemertt u Protect N .... ...Y p ...�.. ..—.....m...... ... .. ....a.... Village sra V ..� Permlttee,,,.....Ilage of Teque � ... ........ ,..--- .... .,,ww _........... .. w. New or relocated,underground water mains included in this project will be laid to provide a horizontal distance of at least three feet between the outside of the water main and the outside of any existing or proposed vacuum- type sanitary sewer,storm sewer,stormwater force main,or pipeline conveying reclaimed water regulated under Part III of Chapter 62-610,F.A.C.;a horizontal distance of at least six feet between the outside of the water main and the outside of any existing or proposed gravity-type sanitary sewer(or a horizontal distance of at least three feet between the outside of the water main and the outside of any existing or proposed gravity- type horizontal 1 distance oftary sewer th least six feet between the outside of ain will be laidat least six inches above the I% of the sewer);a he water main and the outside of any existing or proposed pressure-type sanitary sewer,wastewater force main,or pipeline conveying reclaimed water not regulated under Part III of Chapter 62-610,F.A.C.;and a horizontal distance of at least ten feet between the outside of the water main and all parts of any existing or proposed"on-site sewage treatment and disposal system." [FAC 62-555.314(1);exceptions allowed under FAC 62-555.314(5)] x. New or relocated,underground water mains that are included in this project and that will cross any existing or (� proposed gravity-or vacuum-type sanitary sewer or storm sewer will be laid so the outside of the water main is at least six inches above the other pipeline or at least 12 inches below the other pipeline;and new or relocated, underground water mains that are included in this project and that will cross any existing or proposed pressure- type sanitary sewer,wastewater or stormwater force main,or pipeline conveying reclaimed water will be laid so the outside of the water main is at least 12 inches above or below the other pipeline. [FAC 62-555.314(2); exceptions allowed under FAC 62-555.314(5)] y. At the utility crossings described in Part II.C.l.w above,one full length of water main pipe will be centered above or below the other pipeline so the water main joints will be as far as possible from the other pipeline or the pipes will be arranged so that all water main joints are at least three feet from all joints in vacuum-type sanitary sewers,storm sewers,stormwater force mains,or pipelines conveying reclaimed water regulated under Part III of Chapter 62-610,F.A.C.,and at least six feet from all joints in gravity-or pressure-type sanitary sewers,wastewater force mains,or pipelines conveying reclaimed water not regulated under Part III of Chapter 62-610,F.A.C. [FAC 62-555.314(2);exceptions allowed under FAC 62-555.314(5)] x z. New or altered water mains that are included in this project and that will cross above surface water will be adequately supported and anchored,protected from damage and freezing,and accessible for repair or replacement. [FAC 62-555.320(21)(b)and RSWW 8.7.1] aa. New or altered water mains that are included in this project and that will cross under surface water will have a minimum cover of two feet.[FAC 62-555.320(21)(b)and RSWW 8.7.2] x bb. New or altered water mains that are included in this project and that will cross under surface water courses greater than 15 feet in width will have flexible or restrained,watertight pipe joints and will include valves at both ends of the water crossing so the underwater main can be isolated for testing and repair;the aforementioned isolation valves will be easily accessible and will not be subject to flooding;the isolation valve closest to the water supply source will be in a manhole;and permanent taps will be'provided on each side of the isolation valve within the manhole to allow for insertion of a small meter to determine leakage from the underwater main and to allow for sampling of water from the underwater main.[FAC 62-555.320(2l)(b)and RSWW 8.7.2] cc. This project is being designed to include proper backflow protection at those new or altered service connections where backflow protection is required or recommended under Rule 62-555.360,F.A.C.,or in Recommended Practice for Backflow Prevention and Cross-Connection Control,AWWA Manual M14,as incorporated into Rule 62-555.330,F.A.C.;or the public water system that will own'this project after it is placed into operation has a cross-connection control program requiring Water customers to install proper backflow protection at those service connections where backflow protection is required or recommended under Rule 62-555.360,F.A.C.,or in AWWA Manual M14. [FAC 62-555.360 and AWWA Manual M14 as incorporated into FAC 62-555.330] x dd. Neither steam condensate,cooling water from engine jackets,nor water used in conjunction with heat exchangers will be returned to the new or altered water mains included in this project. [FAC 62-555.320(21)(b)and RSWW 8.8.2] DEP Form 62-555.900(7)Altemate Page 5 Effective August 28,2003 (Updated September 8,2015) NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN EXTENSIONS FOR PWSs Pro eCt Name:Beach Rd Waterman Replacement Permlttee 'Village of Tequesta ...�..� ..... .,. .. um..... _,. ..... , u. . 2. Explanation for Requirements Marked"X"in Part H.C.1 Above,Including Justification,Documentation,Assurances,and/or Alternatives as Required by Rule for Exceptions to Requirements in Part H.C.1: Item F: N/A; we are increasing the size of the watermain so a hydraulic analysis wasn't performed. Item O: The ARV's used in this project are an offset design. This assembly provides for a screened, downward facing elbow above the top of pipe elevation within an offset vault. This can be seen on sheet D2.00. Item V: NIA; there are no known aggressive soils within the project limits. Item Z: N/A; there are no surface water crossings included in the project. Item AA & BB: N/A; there are no sub-aqueous crossings in the project. Item DD: N/A; there are no known steam or cooling systems connected to the system. I completed Part H of this notice,and the information provided in Part II and on the attachment(s)to Part II is true and accurate to the best of my knowleda e and belief ---------- ------- Signature,Seal,and Date of Professional Engineer(PE)or Signature, __ ...........Seal,and Date of Professional Engineer(PE)or Signature and Date of Other Person in Responsible Charge of Signature and Date of Other Person in Responsible Charge of Designing Project:* �`` 11111110// Designing Project:* C�MINELLO /jl Q�� ;56� r ENS+� N 81 '1r * ' 1/ „ �E F Printed MAL License lNumbSamantha C.Gybill,PE er of PE or Licen eraNumber or Title of Other . License Prmted/Tylmed ame: e Number of PE or License Number or Title of N Other Person in Responsible Charge of Designing Project:* Person in Responsible Charge of Designing Project:* 81326 9 ina Design Report ort for Which Responsible: [111111-1 Preliminary Design p for Which Responsible _...— 1 rY gn p P Civil Design* nsfble Portion of Prehmuii designed under Portion of Prelim Report Except as noted in paragraphs 62 555.520(3)(a)and(b), F.A.C.,projects shall be des g responsible charge of one or more PEs licensed in Florida. If this project is being designed under the responsible charge of one or more PEs licensed in Florida, Part II of this notice shall be completed, signed, sealed, and dated by the PE(s)in responsible charge. If this project is not being designed under the responsible charge of one or more PEs licensed in Florida, Part II shall be completed, signed, and dated by the person(s)in responsible charge of designing this project. DEP Form 62555.900(7)Altemate Page 6 Effective August 28,2003 (Updated September 8,2015) NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN 13 EXTENSIONS FOR PWSs Pro"jectName� ��.P'....�. �. ..—.. �_.. Pernvttee. lag �..� eadt Rd Watemiam Re lacement ...'-° .. ....... ......�.... .. •Vil a ol'r uesta _,,........ _. ___. ..e..._.�.....�,.... ._.. A. Certification�byPen­­mttee I am duly authorized to sign this notice on behalf of the permittee identified in Part I.F of this notice. I certify that,to the best of my knowledge and belief,this project complies with Chapter 62-555,F.A.C. I also certify that construction of this project has not begun yet and that,to the best of my knowledge and belief,this project does not include any of the following construction work: • construction of water mains conveying raw or partially treated drinking water, • construction of drinking water treatment,pumping,or storage facilities or conflict manholes; • construction of water mains in areas contaminated by low-molecular-weight petroleum products or organic solvents; • construction of an interconnection between previously separate public water systems or construction of water mains that create a"new system"as described under subsection 62-555.525(1),F.A.C.;or • construction of water mains that will remain dry following completion of construction. (A specific construction permit is required for each project involving any of the above listed construction work.) I understand that,if this project is designed under the responsible charge of one or more professional engineers(PEs)licensed in Florida,the permittee must retain a Florida-licensed PE to take responsible charge of inspecting construction of this project for the purpose of determining in general if the construction proceeds in compliance with the Department of Environmental Protection construction permit,including the approved preliminary design report,for this project. I understand that the permittee must have complete record drawings prepared for this project. I also understand that the permittee must submit a certification of construction completion to the Department and obtain written approval,or clearance,from the Department before the permittee places this project into operation for any purpose other than disinfection or testing for leaks. 4/10/2020 Matthew Hammond, PE Utility Director Signature and Date Printed or Typed Name Title B. Certification by PWS Supplying Water to Project I am duly authorized to sign this notice on behalf of the PWS identified in Part I.G of this notice. I certify that said PWS will supply the water necessary to meet the design water demands for this project. As indicated below,the water treatment plant(s)to which this project will be connected has(have)the capacity necessary to meet the design water demands for this project,and I certify that all other PWS components affected by this project also have the capacity necessary to meet the design water demands for this project. I certify that said PWS is in compliance with applicable planning requirements in Rule 62-555.348,F,A.C.; applicable cross-connection control requirements in Rule 62-555.360,F.A.C.;and to the best of my knowledge and belief,all other applicable rules in Chapters 62-550,62-555,and 62-699,F.A.C.;furthermore,I certify that,to the best of my knowledge and belief,said PWS's connection to this project will not cause said PWS to be in noncompliance with Chapter 62-550 or 62-555, F.A.C. I also certify that said PWS has reviewed the preliminary design report for this project and that said PWS considers the connection(s)between this project and said PWS acceptable as designed. • Name(s)of Water Treatment Plant(s)to Which this Project Will Be Connected: Village of Tequesta Water Treatment Plant • Total ed mum ng Capacity of ,330,000 • Total Maximum Day 1Flow Day Plant(s)as Recorded on Monthly Operating Reports During Past 12 Months,gpd 11,891 sig �� 4/a.ol2o20 � � Matthew Hammond, ..�_ ..ty nd, PE Utility Director andDate . ......-.. ..�,._....�... � .. Printed or Typed _ Name Title C. Certification by PWS that Will Own Project After It Is Placed into Permanent Operation I am duly authorized to sign this notice on behalf of the PWS identified in Part LH of this notice. I certify that said PWS will own this project after it is placed into permanent operation.i also certify that said PWS has reviewed the preliminary design report for this project and that said PWS considers this project acceptable as designed. 10/2020 Matthew Hammond, PE Utility Director Signature and Date Printed or Typed Name TitlemmW ITITmuWITIT min DEP Form 62-555.900(7)Akemate Page 7 Effective August 28,2003 (updated September 8,2015) NOTICE OF INTENT TO USE THE GENERAL PERMIT FOR CONSTRUCTION OF WATER MAIN „Pro ect Name B EXTENSIONS FOR PWSs D. Certification by Professional Engineer(s)m Res ons Responsible Chargetteevl!ase or Tag�e�ta - Pe ..rw_ pDesigning Project* . ..� .. _ I,the undersigned professional engineer licensed in Florida,am in responsible charge of designing this project. I certify that,to the best of my knowledge and belief,the design of this project complies with Chapter 62-555,F.A.C. I also certify that,to the best of my knowledge and belief,this project is not being designed to include any of the following construction work: • construction of water mains conveying raw or partially treated drinking water; • construction of drinking water treatment,pumping,or storage facilities or conflict manholes; • construction of water mains in areas contaminated by low-molecular-weight petroleum products or organic solvents; • construction of an interconnection between previously separate public water systems or construction of water mains that create a"new system"as described under subsection 62-555.525(1),F.A.C.;or • construction of water mains that will remain dry following completion of construction. Signature, listed construction work.) Signature,specific Sealt anctio_ e srequired! _ _e above . ` IN for each l�ro�ectminvolvmg any of the . � n > '���� ELLp Seal,and Date: _.. No. 51326 YE F N, _Prmted/T 1,ed Name Samantha C.ct�ybm PE ed/T�1. aed License N l__ —,_..;_. —._. Prmt Numb s�32s _ Responsible: Lice Name _.. Portion off PreliminaryDesignReport for Which Res License Number Civil Design p on ofPrehminary Design Report Which Responsible: ).( f.. P j p e * or more professional engineers(PEs)licensed g Except�noted anparagraphs 62 555.520 3 an Florida. I t s ro ect as being designed under the rese designed under the sortstblel chair e o on P P g of one or more PEs licensed in Florida, Part IHD of this notice shall be completed by the PE(s)in responsible charge. If this project is not being designed under the responsible charge of one or more PEs licensed in Florida, Part III.D does not have to be completed DEp Form 62555.900(7)Altemate Page 8 Effective August 28,2003 (Updated September 8,2015) APPENDIX B - PERMIT APPLICATIONS DQPart o. S NOTICE OF INTENT 14 TO USE THE GENERIC PERMIT FOR DISCHARGE OF GROUND WATER . FROM DEWATERING OPERATIONS -. °'")?,,tat 9101 (subsection 62-621.300(2), F.A.C.) PART I INSTRUCTIONS A. Will dewatering operations be performed as part of construction activities? ❑ NO Continue completing this form. ❑ YES You may elect to obtain coverage under the Generic Permit for Stormwater Discharge from Large and Small Construction Activities (CGP), DEP Form 62-621.300(4)(b),which will cover both the construction and dewatering operations. B. This Notice of Intent(NOI)form shall be completed and submitted to the industrial wastewater program at the local DEP office as part of the request for coverage under the Generic Permit for Discharge of Ground Water from Dewatering Operations subsection 62-621.300(2)(a), F.A.C., at least 14 days prior to planned commencement of discharge. For the purposes of this generic permit, `dewatering operations' means temporarily lowering the water table by draining or pumping of ground water from activities such as excavations, building foundations, vaults, trenches and aquifer performance tests for exploratory purposes. Applicants should be familiar with the rule, generic permit document and instructions before completing this NOI form. Attach additional information on separate sheets as necessary. 1. Submit this completed form and supporting documentation and the $100.00 application fee to the industrial wastewater program at the local DEP office. Electronic submittal is preferred and may be available at http://www.dep.state.fl.us/water/wastewater/iw/iw- forms.htm. To locate a local DEP office, go to: http://www.dep.state.fl.us/secretary/dist/default.htm. 2. Checks should be payable to the Florida Department of Environmental Protection. DEP will not process this form without the appropriate fee. 3. If an item is not applicable to your project, indicate "NA" in the appropriate space provided. PART II DEWATERING INFORMATION: A. Is the project site currently identified as contaminated, or is there a site within 500 feet of the dewatering project identified as contaminated, by a DEP or EPA cleanup/restoration program? You may use the Quick Links to DEP's Contamination Locator Map (CLM) and DEP's Institutional Controls Registry (ICR) Web Viewer to determine cleanup restoration status. You may access the CLM at: http://webapps.dep.state.fl.us/DepCInup/welcome.do, or http://ca.dep.state.fl.us/mapdirect/?focus=contamlocator. The ICR may be accessed at: http://www.dep.state.fl.us/waste/categories/brownfields/pages/ICR.htm, or http://ca.dep.state.fl.us/mapdirect/?focus=icr ❑ YES Continue to B. ❑NO Continue to D. Page 1 of 3 DEP Foam 62-621.300(2)(b)incorporated in subsection 62-621.300(2),F.A.C. Effective 02/2015 B. Has the site been remediated? ❑ YES Continue to D. ❑ NO Continue to C. C. Are the pollutants of concern (i.e. contamination)present in groundwater at the dewatering project site at concentrations equal to or exceeding the surface water criteria in Rule 62-302.530? ❑ YES Dewatering operations do not qualify for coverage under this generic permit. However, the site may qualify for coverage under Rule 62-621.300(1), F.A.C., or under an individual wastewater permit on the appropriate form listed in Rule 62-620.910, F.A.C. ❑NO Continue to D. D. Have Best Management Practices (BMPs)for this generic permit been developed or addressed in an existing BMP plan in accordance to the requirements of this generic permit. BMPs must be implemented upon commencement of the discharge ❑ YES Continue to Part III. ❑NO Your application cannot be processed until this item is complete. NOTE: Chemical treatment is allowed as described in the Best Management Practices of the Generic Permit. However, sites that use cationic treatment chemicals are not eligible for coverage under Generic Permit for Discharge of Ground Water from Dewatering Operations unless concurrence from the applicable local DEP office is obtained in advance of the submittal of this NOL Appropriate controls and implementation procedures designed to ensure that the use of cationic treatment chemicals will not cause or contribute to a violation of water quality standards shall be included in the site specific BMPs. PART III DISCHARGE INFORMATION: A. Please identify receiving surface water body. PART IV SITE INFORMATION A. COVERAGE STATUS: 1. Is this application for new coverage or for renewal of coverage New ❑ Renewal ❑ under the generic permit? 2. If this application is for renewal of coverage under the generic FLG No: permit, provide the FLG No. B. NAME OF SITE: Site Name: Page 2 of 3 DEP Foam 62-621.300(2)(b)incorporated in subsection 62-621.300(2),F.A.C. Effective 02/2015 C. PERMITTEE INFORMATION: 1. Name: 2. Title (Owner, Operator, Contractor, etc.): 3. Phone No.: ( ) - T4- Fax No.: ( ) - 4. Email Address: 5. Street or P. O. Box: 6. City or Town: 7. State: 8. Zip Code: D. SITE LOCATION INFORMATION: 1. Street, Route or Other Specific Identifier: 2. County: 3. City or Town: 4. State: 5. Zip Code: 6. Latitude: 07. Longitude: ° 8. If records required in accordance with Part V. of DEP Document 62-621.300(2)(a), are kept off-site,please provide the physical address of site where records will be kept. Note: location must be accessible for inspection of records by the Department. PART V CERTIFICATIONS A. OWNER OR OPERATOR' I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. Name & Official Title (type or print) Signature Telephone No. Date signed Email Address 'Signatory requirements are contained in Rule 62-620.305,F.A.C. Page 3 of 3 DEP Foam 62-621.300(2)(b)incorporated in subsection 62-621.300(2),F.A.C. Effective 02/2015 Ex. B SCHEDULE OF BID PRICES Project No.:WUD 19-040 Project Name:2019 PipelineContinuing Construction Contract Beach Road Water Main Replacement Project No.040097024 DRAT'T Johnson-Davis,Inc. Village of Tequesta Piggyback Contract 6/25120 604 Hillbrath Dr., Lantana,FL 33462 6ID ITEM No. BID ITEM(Furnish and Install with Appurtenances) UNIT QUANTITY UNIT PRICE TOTAL 7 8"PVC Push-On Joint Water Main/Reclaimed Water Main/Wastewater Force Main LF 168 $ 30.00 $ 5,040.00 10 10"PVC Push-On Joint Water Main//Reclaimed Water Main/Wastewater Force Main LF 3208 j $ 35.00 $ 112,280.00 23 Ductile Iron Fittings for Water Main/Reclaimed Water Main Tons 1.2320 $ 5,000.00 $ 6,160.00 42 8"Mechanical Joint Restraint for PVC Each 28 $ 280.00 $ 7,840.00 43 10"Mechanical Joint Restraint for PVC Each 56 $ 325.00 $ 18,200.00 55 10"PVC Pressure Pipe Restraint Harness Each 20 $ 225.00 $ 4,500.00 66 8"Gate Valve&Valve Box Each 6 $ 1,500.00 $ 9,000.00 126 Fire Hydrant Assembly with Captivator Caps,6"Gate Valve&Anchor Tee Assembly&10-ft of 6"R.J.DIP Each 3 $ 6,000.00 $ 18,000.00 129 Sample Points W/Double Strap Saddle&Corp.Stop Each 4 $ 500.00 $ 2,000.00 132 2"Blow off Piping Assembly with Box Each 2 $ 1,000.00 $ 2,000.00 145 Long Single 5/8"Meter Service(1-1/2"Polyethylene with 3"Casing up to 40'long) Each 4 $ 1,800.00 $ 7,200.00 153 8"DIP X AC Pipe Adapter Each 4 $ 3,500.00 $ 14,000.00 157 8"Asbestos Pipe Removal/Abatement LF 400 $ 15.00 $ 6,000.00 159 4"to 12"Diameter Connection to Existing Water Main/Reclaimed Water Main or Force Main(Joint Restraint Each 4 $ 3,000.00 $ 12,000.00 163 Grouting/Deactivation of Existing 8"Pipe LF 2,785 $ 10.00 $ 27,850.00 166 Milling of Asphalt SY 740 $ 15.00 $ 11,100.00 167 Asphalt Overlay Tons 41 $ 200.00 $ 8,200.00 168 Asphalt Roadway Removal and Restoration(2.5"thick) SY 75 $ 50.00 $ 3,750.00 180 Floratam Sod SY 295 $ 6.00 $ 1,770.00 181 Bahia Sod SY 93 $ 5.00 $ 465.00 184 Record Drawing LF 3,500 $ 2.50 $ 8,750.00 185 Construction Survey LF 3,500 $ 2.50 $ 8,750.00 186 Preconstruction Video Taping LF 3,800 $ 1.00 $ 3,800.00 190 Maintenance of FDOT Roadway LF 4,000 $ 4.00 $ 16,000.00 191 Density Tests Each 120 $ 40.00 $ 4,800.00 192 Proctor Tests Each 2 $ 100.00 $ 200.00 200 Remove&Replace Signs Each 2 $ 150.00 $ 300.00 231 Silt Fence LF 3,500 $ 1.00 $ 3,500.00 238 8"Single Line Stop(for PVC/DIP/CIP/AC) Each 1 $ 8,500.00 $ 8,500.00 (A)SUBTOTAL BASE BID(Bid Items 1-240) $ 331,955.00 241 Additional Work not inculuded in Bid Items(15%of Subtotal Bid Price(A) LSU 1 $ 56,200.00 242 Mobilization(2.5%of Subtotal Bid Price(A) LSU 1 $ 8,298.88 243 Demobilization(1%of Subtotal Bid Price(A) LSU 1 $ 3,319.55 244 Contingency 5% LSU 1 $ 19,408.00 (B)SUBTOTAL ADDITIONAL WORK BID PRICE(Bid Items 241-243) $ 87,226.43 TOTAL BID PRICE(A+B) $ 419,181.43 241A 10"Gate Valve&Valve Box Each 5 $ 1,900.00 $ 9,500.00 241B Drainage Conflicts(Including Dewatering) Each 5 $ 2,600.00 $ 13,000.00 241C Remove Existing Fire Hydrant Each 3 $ 500.00 $ 1,500.00 241E Gravel Parking Area SY 900 $ 30.00 $ 27,000.00 241G Relocate Existing VOT Sampling Point Each 1 $ 1,100.00 $ 1,100.00 241H Remove and Replace Gravel Walk SY 4 $ 150.00 $ 600.00 2411 HDD for Water Service I Each 1 1 1 $ 3,500.001 $ 3,500.00 (B)TOTAL BID PRICE ADDITIONAL WORK NOT INCLUDED IN BID ITEMS(Bid Item 241) $ 56,200.00 1 OF i PBCWUD 19-040 6/25/2020 w a W w 0 = w U J r w < Q Ur Y Z ~ a 0 Q y O w U J ~ Z Z Z Q (n W Q Q Q Q Q 0 Q t F F p a a a w w a Q Z W O tr z z z o o O a ;? W z a ¢ ¢ ¢ o 0 0 0 0 U) Q 0 w w W w w w W r,! > W u ° o >0 w w Y 2 U) J W N s O ///�/� VJ 0 O O O N O O who a) O O O O O O O O fn C7 C7 U U U U 0 0 Gm- ova - wkQ W - cQc G � a a Wz w w w o � D x Qg �oc) z oLL � w �� ~ N DU <0 O C o oJaw N o d < � Q � 0 W H o m LU .- z N^ 1i4 d J ) W � a ^W^ -p3 Y�I z z Qle O W O Lu Q m Z Z W z z < Q W Q m a � O � m U) Y W W z/] > W z cje U ai ui Wm > cl� Q ll�Q Y W o 3= W m � Z W $V �� W Q m s a // V Q J J W �o x_ r%, Z O O z z z d w W wD D Da E� Q U O O O a � d Q > U U U w b,P.33us a�o oo��s,aausod���Pa uoae�s,>aio„a �a wao.eso ozoz a rtow .33us a�o oo� o, ,uawa,oaaa ow,e,oM Pooa uoae.,as,ear.00,e ago, e Pa„od C) 08 o 3: 0 woo < U) �popoHn w H ovago 00 w < M H w 99 A, 9m. 00 -0 0 w M o o A p goy - �o = - - � _ C Q 'o lo o o ...... W z LLI 'o ww xw10 W H <LL o� 0 T Lu 9. Ww. o 0 o o a� w o E Mo -o =J LLJ <E o- -o pz <�o pro > 'I A n olo o o< E -MO q pip w oow� o m HIE. H Mw o T AM n -o- H o. > W...o 'o o ob o o I o o o o- '-o 's Eo oo n�H 2H Wo 0 Mo- HoE M., gTow-o-iT., ag ;Ep;0, Mao 2Eo W NET M HE! 'o .10 Ma Noo ­n -o o'o -o-- Mo -<! -, - ­g- Hw W Mo2w- �S_E -<ofor - -2-L ­Og <. ow ow <9m 2R ffo. Aff. H E2 HE wo-< 9 H. a O O U d Q U � ww w U) d � J w J Y w a Q �. x o Q � 0C1 w H aLL 0 I � lii �����✓ ru i €�' a " i Q J a LLJ r 0 d U �✓ D� J �0 �� ➢ Y U w co 4 oo � m � '��" r✓r� ��l✓✓/���. i�an r ' rairavra�r ir�r%%`/.��is �" ��i f lW U/I �rd�p/T'rl✓� � n i „� y� fi elYji �� ^J.✓�+ � r!!n{Y��n �a,"'�/,%��%%� %��l/?��yllUia "�'' i o0 o &w h� �Y Mpg ej�/f ✓ i r � W �U m — a �o _ aMp erw.�3roaa��a�o oo�ar�eeusuoiarwarPa a=oae��i.+aio,e ac iw�ra Waze.e�so oaoz �z Rory erry.�3roaa��ra�o 00�a.��wo� �uawa.,oiaaa wow,e�oM Pooa u�oae.ias ieaus.po,e a�o�ne Pa��oia NVO 133HS) O AM WS 3NnHOiVW Lb+2 NiS 3NnHOIVW O N NORwr IN ON W a Go 0, R� d 0 R� Q W � W H 211 /l(I J a w } /lI j N Q /lo 03 /,✓//i/ G���/ il/I�� �i i�/ III %l'��%% NO / a ; //� 1 On r 'i/✓l o i � w i Axi. g fIJ iir r n/ / Nil_ r, iI 5, Z' �flt`� r a = i/��Jf tr' �MR,I( �r 99+0 NiS 3NnHOIVW wmo.m„...... „. _..9„0®„ ..,.,...o,..o N�.w,77 7777 us,77—��Pa a...7=a�o,d a������� wneos�so ozoz a.ow Nd,d Nrory a3.dM ooz�,� o, ,uawa,o�aaa��ow,"7' Pooa u�oae,as,ear.00,e „od (ZO"ZO 133HS) ��+LZ :V1S 3NIIHOIVW Ll+22 :V1S 3NI�HOlVW O UF D Ofr%, , w a o/ IN, �/%... a r e > �a f/r// %i/ a D/ e< �i / / r ri �Gi///�'r ' a ME— /Jo f Nor lU r r� roz %} i Q mNw� Q I 1,I// a :�� r �� //%///�ri//�: ri�Dll'/r r ip w z w /%i Ji/ / / H W Q M/�" W op f /� f a R woi,t o 0 OJaUJ m (7 W Q /I�'hibm U LL 0 r Me a o s m !r N = o m �s x N3 �o o�wo = o o> f!//r / /�%j era, w� oP �rai r/ f i r / l// iMM amo I'll/ rril I %/ U r / AAA, ir 0 " Lb+IZ :V1S 3NI�H0IVW 22+LZ :V1S 3NI�HOlVW (00'Z0 133HS)�P N..ne Nvrva3"vM oozorre"uoeravoroa a>o"es,=arose ac no,m wnasso oaoz a aory Nvra wvw a3.vM o zo.mwo, ,u"wa.,o,a"a woweroM Pooa a=oee.ras r""us.00ze ago;ne Penoa 90+6£ V1S 3NIIHOIVW O LL J� so, a 3:o IN WIN RN H=R Aa / r t / r / I/// a l, IN- a ? l /y /A� � W Z Lu L11mo W �H poo m O W o / N o3m � rf� LLB IF W,w M U /., r� ✓A / -r ao o> < a a r S m Wwo <ffio �LL iww 3 �% �ww rQ i/�/% 0 o w 1 � '�'f'%�%r��ii /i.✓/r,3 ;�! I 7, ��J�/��/, �II rIJ j7�/,� /���/'% � i���I%/�, %/ V ' /i/�,'/ // e r rc / 'i//il / r /i /al ri/%/✓ Z +�2 :V1S 31NI�HXVW 90+K :V1S 31NI�HXVW (l0'ZO 133HS) b,o Nd,d Nrowa3.dM oo��s,aausod����Pa a>oee�n=a�o,d a����� wn9ssso ozoz a.ow Nd,d Nrory a3.dM zoz�,��o, ,uawa,oaaa�ow,e,oM Pooa u�oae,as,ear.00,e ago, e Pa„od C) C) Qo 3: U) LU o " G"gu Y O r\\y € 6' O E p o Q! H o . ... .......... O ............. o U) Ow '6 ---------- 2 "N. AU 00 0, z e a w Z Lu 6 LLJ z CY Lu E <0 LL W LLJ -F-�.......... ol ol 00- (D w < a�Vdl Mul --0- NTVWdl,IV UMrlWM law�lfjro > LU co I V o or w -I ey g wx z > o o rc ol I Jrc 0 mo3 15 o ......... . IN p— nn Ho vu L O �6 z v ....... RIX -'-wTU. H 0 H HUM O 0 w ` — _ — zo lo — J p � 'a- — ro�3o a w _ ms _ oappo� o p 25 - 3Y� - pE--�a Q Noz �-<zo�3 0 6 <_ �3 � <mz ry��« az ,� Q i a z Q N I�1 0 Z Lu I W w Q w W� J � o w � Lu g pUaLL _ OJa� a c� - - � ww Q ZO W Q ro 3 0 m y Q M 1 o�m�=�_ � a v z3 u a o B"A a dNgA 4 E'P g rsEr� Il a n. a o ,u i £ o � <a u N s r 4 & q r��r, rr Gr u �{. Apr s j k4 { q I�$i fip e ��a6 4 ���M� afl 7 � µ �_ to d r I� r�na' �lN�! y gP ai H 0g'xa �" b,Ps,�..3a ooza�s,aausuod�ad��Pa u�oae��,>aio„a�w��� wdaz 9�so ozoz a ory s,d.3a a�.aNds oozy—o, 7awa377a Pooa ago, e Pa„od !\ � § � J - § 110 g \ / \/ \ E Z » _ / < Ez § RL o \ : \/ \ w < \ \\ a 3> ] ) ) E j}}\