Loading...
HomeMy WebLinkAboutDocumentation_Regular_Tab 06_7/8/2021Agenda Item #6. Regular Council STAFF MEMO Meeting: Regular Council - Jul 08 2021 Staff Contact: Matthew Hammond, Utilities Department: Utilities Director Approve Change Order #1 — Beach Road Water Main Replacement -Phase 1 — Johnson -Davis On July 9, 2020, the Village Council approved Work Authorization No. 1 to Johnson -Davis, Inc. to construct the Beach Road Water Main Replacement -Phase 1 project replacing approximately 3,200 feet of asbestos cement water main constructed in the 1960's. To ensure the best value for this project, the Village awarded the project to Johnson -Davis, Inc. using a piggyback agreement based on the Palm Beach County 2019 Pipeline Continuing Construction Contract. During construction the design for the fire hydrant locations serving the Sea Glass project was modified moving the hydrant locations into the right-of-way. Due to the new location the developer for the Sea Glass project has requested that the Village install the piping and fire hydrants as part of the current Beach Road Water Main Replacement - Phase 1 project with 100% of the costs being reimbursed by Turnberry Beach Road, LLC. As a result, the Utilities Department is requesting a change order (Change Order #1) to the previously approved work authorization in the amount of $30,710.00 for the changes to the project scope requested by the Sea Glass developer. Note that the Sea Glass has funded $70,046.21 of the construction for the Beach Road Water Main Replacement -Phase 1 to date which the Village has received payment for. If approved, the revised total cost for the project will be $449,891.43. Additionally, the proposed Change Order is requested to include an extension to the approved contract of 100 days due to delays related to this request and unforeseen circumstances. The Beach Road Water Main Replacement -Phase 1 project is anticipated to be completed in June 2021. This document and any attachments may be reproduced upon request in an alternative format by completing our Accessibility Feedback Form, sending an e-mail to the Village Clerk or calling 561-768-0443. BUDGETED AMOUNT: AVAILABLE AMOUNT: EXPENDITURE AMOUNT: $0 $419,181.43 $419,181.43 Additional Budgetary Information: Funding Source(s): The cost for Change Order No. 1 will be Water Enterprise Fund reimbursed by the Turnberry Beach Road, LLC Approve Change Order #1 with Johnson -Davis. Page 100 of 287 Agenda Item #6. Proposed Change Order No. 1 - Johnson-Davis.ada Page 101 of 287 Agenda Item #6. The following document is presented in a non- ADA compliant format. Please contact the Village Clerk's office if you would like to receive an ADA compliant version of this document. Page 102 of 287 Agenda Item #6. CONTRACT CHANGE ORDER Change OrderNo. 1 Date of Issuance: June 10, 2021 Effective Date: June 10, 2021 Project: Beach Road Water Main Owner: Village of Tequesta Owner's Contract No.: Work Authorization No. 1 Replacement Project Contract: Piggyback Agreement to PBC 2019 Pipeline Continuing Date of Contract: July 9, 2020 Construction Contract Contractor: Johnson -Davis, Inc. Engineer's Project No.: 040097024 The Contract Documents are modified as follows upon execution of this Change Order: Description: During construction of this project, the Sea Glass project encountered a modification to their plans resulting in their fire hydrants being located within the public ROW. Due to the new location, the Sea Glass developer has asked the Village's contractor to install the piping and fire hydrants as part of this contract. Attachments (list documents supporting change): Proposed CO #1 Request prepared by Johnson -Davis, dated 5/25/2021 CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price: Original Contract Times: ❑ Working days ❑ Calendar days Substantial completion (days or date): 4/16/2021 $ 419,181.43 Ready for final payment (days or date): 5/16/2021 A Contract Price prior to this Change Order: $ 419,181.43 [increase] [DeGFeas] of this Change Order: $ 30,710.00 Substantial completion (days): N/A Ready for final payment (days): N/A Contract Times prior to this Change Order: Substantial completion (days or date): 4/16/2021 Ready for final payment (days or date): 5/16/2021 [increase] ] of this Change Order: Substantial completion (days or date): 100 days Ready for final payment (days or date): 0 days Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial completion (days or date): 7/25/2021 $ 449,891.43 Ready for final payment (days or date): 8/24/2021 RECOMMENDEpp ACCEPTED: ACCEPTED. 7 9 By: v ` _= } By: Frank D'Ambra - Mayor By: Engineer (Authorized Signature) Owner (Authorized Signature) Contrac or (Authorized Date: June 4, 2021 Date: Date: June 3, 2021 Approved by Funding Agency (if applicable): N/A Date: END OF SECTION Project Name Page 103MA71