HomeMy WebLinkAboutAgreement_General_7/8/2021_Hedrick BrothersAgenda Item No. 20 — 7/8/2021
This agenda item is being amended to reflect a decrease of $1,301.69 in total change orders.
This adjustment represents a credit that the Village received for markup on lumber cost
increases that was received after the agenda was prepared. The total amount of change orders
requested will therefore total $99,545.32.
{Authorize Additional Change Orders in the Amount of $ 90,84:.91 $99,545.32 with Hedrick
Brothers Construction in Connection with Construction of the New Community Center.}
Village of Tequesta - Community Center
Description/Reason for Change Order
Revision Change No.
Amount
Revised Contract Sum
Original Contract Sum
6,013,394.00
Direct Owner Purchases +tax savings/changes to bid set
1-3
(434,320.11)
5,579,073.89
Subcontractor cost components; time delay component of 51 calendar days
4
160,711.35
5,739,785.24
Plumbing changes per code
5
4,794.07
5,744,579.31
Truss modifications
6
13,647.20
5,758,226.51
Electrical owner requests
7
6,293.49
5,764,520.00
Barometric relief damper
8
2,598.07
5,767,118.07
Sink/shroud change
9
(634.44)
5,766,483.63
Additional fencing at Seabrook
10
3,998.19
5,770,481.82
Add 1 panel to operable partition
11
1,256.95
5,771,738.77
Lumbercost escalation
12
15,298.34
5,787,037.11
Correction to remove markup on price escalation items
13
(1,418.34)
5,785,618.77
Ductwork price escalation
14
22,928.00
5,808,546.77
N/A (Voided)
15
-
5,808,546.77
Milling&Overlay at Dover Road
16
22,771.56
5,831,318.33
Adjustmentoftax savings—A/V Equip. (The Experts)
17
1,7S8.42
5,833,076.75
Adjustmentoftaxsavings—structuralsteel(EpicMetals)
18
7,555.50
5,840,632.25
Correction to remove markup on price escalation items
19
(1,301.69)
5,839,330.56
■ ■ HEDRIC;K
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-019
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-019: Credit for Mark -Up
Charged on PCCO #12
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469
WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION: 2000-019 / 0 CONTRACT-
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
REQUEST RECEIVED FROM:
CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
STATUS: Pending - In Review
CREATED DATE:
7/8 /2021
REFERENCE:
PRIME CONTRACT
None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION:
ACCOUNTING
Amount Based
METHOD:
SCHEDULE IMPACT:
PAID IN FULL:
No
TOTAL AMOUNT:
($1,301.69)
POTENTIAL CHANGE ORDER TITLE: Credit for Mark -Up Charged on PCCO #12
Gi:IdlKell
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #034 - Credit for Mark -Up Charged on PCCO #12
This Change order serves to credit back the General Liability Insurance, Subcontractor Default Insurance, and Contractor's Fee that was charged on
PCCO #12- Lumber Cost Escalation. No mark-up is to be charged on Price Escalation Changes.
ATTACHMENTS:
PCCO #012 with PCO #12 back-up.pdf
#
SubJob
Cost Code
Description
Type
Amount
1
PCCO#012 LUMBER COST
15-18-105 - GENERAL LIABILITY
General Liability Insurance
Materials
($181.96)
INCREASE
INSURANCE
2
PCCO#012 LUMBER COST
15-18-107 - SUBCONTRACTOR
Subcontractor Default Insurance
Materials
($209.95)
INCREASE
DEFAULT INS
3
PCCO#012 LUMBER COST
15-18-110 - CONTRACTOR'S FEE
Contractor's Fee
Overhead
($909.78)
INCREASE
Subtotal:
($1,301.69)
General Liability: 0.00% Applies to all line item types.
$ 0.00
Contractor's Fee: 0.00% Applies to all line item types.
$ 0.00
Subcontractor Default Insurance: 0.00% Applies to all line item types.
$ 0.00
Grand Total:
(51,301.69)
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 7/8/ 2021 08 :14 AM
y*afar rsQGds
Regular Council
STAFF MEMO
Meeting: Regular Council - Jul 08 2021
Staff Contact: Jeremy Allen, Village Manager Department: Parks and Rec
FNNM
Authorize Additional Change Orders in the Amount of $100,847.01 with Hedrick Brothers Construction
in Connection with Construction of the New Community Center.
On February 11, 2021, the Village entered into a contract for Construction Manager at Risk services
with Hedrick Brothers Construction in the amount of $6,013,394.00 to construct the new community
center. On June 10, 2021, the Village Council approved Change Order No. 1 totaling $160,711.35. As
a condition of approval, staff was instructed to work with Hedrick Brothers to determine if any credits
could be generated. Since that time, Hedrick Brothers has received several subcontractor change
order requests that were necessitated by steep material pricing increases brought about by an overall
disruption in the global construction supply chain. According to Associated General Contractors,
government data released earlier during the year, revealed that costly pricing increases and supply
chain disruptions have perpetuated further hardships on contractors, not only driving up construction
costs, but also slowing down progress on their projects. In some cases, prices per unit have almost
doubled. Additionally, the data found that more than three -fourths of construction firms have indicated
projects are being postponed or canceled altogether due to unavailable materials or cost overruns.
The total additional change orders amount to $100,847.01, which brings the total change orders to date
to $261,558.36, excluding direct owner purchases/adjustments. A summary of the net change by
change orders is below:
Description/Reason for Change Revision Change No.
Order Amount
Original Contract Sum N/A $6,013,394.00
Direct Owner Purchases + Tax
Savings/Adjustments (Changes to bid
1-3
(434,320.11)
set)
Subcontractor cost components; time
4
160,711.35
delay of 51 calendar days
Plumbing changes per code
5
4,794.07
Truss modifications
6
13,647.20
Electrical owner requests
7
6,293.49
Barometric relief damper
8
2,598.07
Sink/shroud change
9
(634.44)
Additional fencing at Seabrook
10
3,998.19
Add 1 panel to operable partition
11
1,256.95
Lumber cost escalation
12
15,298.34
Correction to remove markup on price
13
(1,418.34)
escalation items
Ductwork price escalation
14
22,928.00
Description/Reason for Change
Order
N/A - "Voided"
Milling and overlay at Dover Road
Adjustment of tax savings — AN Equip.
(The Experts)
Adjustment of tax savings — structural
steel (Epic Metals)
Revised contract sum to date
(Hedrick Bros. Construction)
Revision Change No. Amount
15 0.00
16 22,771.56
17 1,758.42
18 7,555.50
$5,840,632.25
The change orders/adjustments reflected above will create a cost overrun for this project of
approximately $196,000.
The cost overrun was calculated as follows:
Description
Amount
Original Construction Budget
$6,157,841
Less: Hedrick Bros. Construction
(5,840,632)
Less: Direct owner purchases
(495,722)
Less: Other ancillary expenses to completion (17,000)
Budget Deficit (Funding Amount Needed) (195,513)
This document and any attachments may be reproduced upon request in an alternative format by completing
our Accessibility Feedback Form, sending an e-mail to the Village Clerk or calling 561-768-0443.
POTENTIAL MOTION- • e
Staff recommends approval of additional change orders as attached.
change orders hedrick bros 07.08.2021 V2.0
The following document is presented in a non-ADA compliant format.
Please contact the Village Clerk's office if you would like to receive an
ADA compliant version of this document.
Village of Tequesta - Community Center
Description/Reason for Change Order
Revision Change No.
Amount
Revised Contract Sum
Original Contract Sum
6,013,394.00
Direct Owner Purchases + tax savings/changes to bid set
1-3
(434,320.11)
5,579,073.89
Subcontractor cost components; time delay component of 51 calendar days
4
160,711.35
5,739,785.24
Plumbing changes per code
5
4,794.07
5,744,579.31
Truss modifications
6
13,647.20
5,758,226.51
Electrical owner requests
7
6,293.49
5,764,520.00
Barometric relief damper
8
2,598.07
5,767,118.07
Sink/shroud change
9
(634.44)
5,766,483.63
Additional fencing at Seabrook
10
3,998.19
5,770,481.82
Add 1 panel to operable partition
11
1,256.95
5,771,738.77
Lumber cost escalation
12
15,298.34
5,787,037.11
Correction to remove markup on price escalation items
13
(1,418.34)
5,785,618.77
Ductwork price escalation
14
22,928.00
5,808,546.77
N/A (Voided)
15
-
5,808,546.77
Milling & Overlay at Dover Road
16
22,771.56
5,831,318.33
Adjustment of tax savings — A/V Equip. (The Experts)
17
1,758.42
5,833,076.75
Adjustment of tax savings — structural steel (Epic Metals)
18
7,555.50
5,840,632.25
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #001
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #001: DPO #1-3
TO:
VILLAGE OF TEQUESTA
FROM: HEDRICK BROS CONST CO INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE
TEQUESTA, Florida 33469
100
WEST PALM BEACH, Florida 33409
DATE CREATED:
3/23/2021
CREATED BY: Kim Blair (HEDRICK BROS CONST CO
INC)
CONTRACT STATUS:
Approved
REVISION: 0
DESIGNATED REVIEWER:
REVIEWED BY:
DUE DATE:
REVIEW DATE: 04/01/2021
INVOICED DATE:
04/30/2021
PAID DATE:
SCHEDULE IMPACT:
EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR:
20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: ($371,290.00)
CTR
DESCRIPTION:
DPO# Owner P.O. #
P.O. Date Vendor
Subcontractor Material Amount Tax Savings amount
1 21.000480
2-5-2021 Epic Metals
Steel Fabricators LLC $143,500.00 $16,215.50
2 21-000483
2-10-2021 Peninsular Elec.
Lightning Electric $133.200.00 $10,303.00
3 21-000482
2-10-2021 Trane
Mechanicool $94,590.00 $6,621.00
TOTAL
ATTACHMENTS:
PCO92000-001 DPO#1-3.g_df
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
$371,290.00 $33,139.50
PCO #
Title
Schedule Impact
Amount
2000-001
CE #002 - DPO #1-3
($371,290.00)
Total:
($371,290.00)
CHANGE ORDER LINE ITEMS:
PCO # 2000-001: CE #002 - DPO 91-3
#
Budget Code
Description
Amount
1
2001.15-05-120.SUB
Epic Metal Material
S(143,500.00)
2
2001.15-05-120.SUB
Epic Metal Tax
$(16,215.50)
3
2001.15-18-150.SUB
Epic Metal Sales Tax Savings
$16.215.50
4
2001.15-16-110.SUB
Peninsular Elec. Dist. Inc. Material
$(133,200.00)
5
2001.15-16-110.SUB
Peninsular Elec. Dist. Tax
$(10,303.00)
6
2001.15-18-150.SU8
Peninsular Elec. Dist. Tax Savings
$10.303.00
7
2001.15-15-710.SUB
Trane Material
$(94,590.00)
8
2001.15-15-710.SUB
Trane Tax
$(6,621.00)
Hedrick Brothers Construction Co., Inc. Page 1 of 2 Printed On: 4/21/2021 12:54 PM
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
PCCO #001
#
Budget Code
Description Amount
9
2001.15-18-150.SUB
Trane Tax Savings $6,621.00
Grand Total:; $(371,290.00)
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be decreased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach, 33401
SIGNATURE ATE
q �evr
GustL%l ry�- MM,QkL� V ANK*Ct
PRINT NAME AND TITLE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
ld
S31G
2NATUR DATE
NAME AND TITLE
$6.013.394.00
$0.00
$6,013,394.00
($371.290.00)
$5,642,104.00
HEDRICK BROS CONST CO INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
4'a?C 4/21/2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co.. Inc. Page 2 of 2 Printed On: 4/21/2021 12:54 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc
2200 Centrepark West Drive. Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-002R
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta . Florida 33469
Prime Contract Potential Change Order #2000-002R: Shell Changes from
Bid Set to Rev 1 Set -REVISED
TO
PCO NUMBER!REVISION
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA Florida, 33469
2000-002R / 0
REQUEST RECEIVED FROM: Mark Stutler (BENCHMARK III
CORPORATION)
STATUS: pending - In Review
FROM: HEDRICK BROS CONST CO INC
2200 CENTERPARK WEST DRIVE SUITE 100
WEST PALM BEACH Florida, 33409
CONTRACT: 20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
CREATED BY: Kim Blair (HEDRICK BROS CONST CO INC)
CREATED DATE: 4/6 /2021
REFERENCE:
Benchmark COR1_7.r1&r2.3.23.21 and COR
PRIME CONTRACT
None
Request No.9-72bd lap
CHANGE ORDER:
FIELD CHANGE:
No
LOCATION:
ACCOUNTING
Amount Based
METHOD:
SCHEDULE IMPACT:
15 days
PAID IN FULL:
No
TOTAL AMOUNT:
$64,918.75
POTENTIAL CHANGE ORDER TITLE: Shell Changes from Bid Set to Rev 1 Set -REVISED
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #004 - Shell Changes Bid Set to Rev 1 Set
Shell changes from Bid set to Revision 1 set.
ATTACHMENTS:
COR 1 r cost breakdown-Ddf COR No. 3.131.3.23.21.Ddf_ COR No 2.TC2.3-23.21.Ddf COR Reguest No 9R - 72bd LaD-adf_ COR No. 5.b5 in
lieu of B4.3.23.21.Ddf_ C OR Request No 9R - 72bd Lac) cost breakdown.Ddf COR No 7R CMU Changes..4.8.21.Ddf_ COR No. 4.5m
ext.3.23.21.Ddf COR Requests 1 7 for Rev1 & Rev 2 Drawings Revised 4 8.21.odf COR No 6 Added b5 bms.3.23.21.odf
q
SubJob
Cost Code
Description
Type
Amount
Shell Changes old set to Rev 1
t 5.03-309 - Shell
Slab revisions
Subcontractor
5 13.098.00
Shell Changes bid set to Rev 7
15-03-309 - Shell
Added Concrete Column TC-2
Subcontractor
S1.20600
Shell Changes bid set to Rev ;
5 03-309 -Shell
Added Concrete Beams B-1
Subcontractor
5 2.252.00
4
Shell Changes bid set to Rev 1
15-03-309 - Shell
Acded Concrete Beam Extensions per New Sheet S-8
Subcontractor
5 7.504 00
Shell Changes bid set to Rev 1
15-03-309 - Shell
-oncrele Beam B-5 in lieu of B-t
Suocontractor
li23 001
Shell Changes bid set to Rev 1
1543-309 - Shell
4onec :oncrete Beams B-�
5„nc3ntr3ctJr
5 1,570.00
Shell Changes bid set to Res '
' S-03.309 - Snell
-MU Changes
Subcontractor
S20.62900
Shell Changes bid set to Rev 1
15.03-309 - Shell
CMU Rebar Lap Change
Subcontractor
3 13.259.00
Subtotal.
559.395 00
General Liability: 1.30% Applies to all line item types.
S 772.14
Contractor's Fee: 6 50% Applies to ail line item types.
3 3.86068
SUDCbntractor Default Insurance: 1.50% Applies to ad line item types.
$ 890.93
Grand Total
364,918.'S
Hedrick Brothers Construction Co., Inc. page ' or 2 Printed On: 4/8/ 2021 02 :06 PM
■ ■ HEDRIC;K
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
PCO #2000-002R
Contractor Owner
Hedrick Brothers Construction Co., Inc. VILLAGE OF TEQUESTA
2200 Centrepark West Drive. Suite 100 345 TEQUESTA DRIVE
West Palm Beach, Florida 33409 TEQUESTA, Florida 33469
4'cc 4-12-2021 cv-�' L-,— I k
Signature Date SiVa re Date
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #003
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #003:
DPO #4 AV Equipment
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONST CO INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE
TEQUESTA, Florida 33469
100
WEST PALM BEACH, Florida 33409
DATE CREATED: 4/19/2021 CREATED BY: Kim Blair (HEDRICK BROS CONST CO
INC)
CONTRACT STATUS: Approved
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS CONST CO
INC)
DUE DATE:
INVOICED DATE:
SCHEDULE IMPACT.
CONTRACTFOR
04/30/2021
REVISION: 0
REVIEWED BY:
REVIEW DATE:
PAID DATE:
EXECUTED:
SIGNED CHANGE ORDER
RECEIVED DATE:
20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT:
CTR
DESCRIPTION:
CE #005 - DPO#4 A/V Equipment
Owner Direct Purchase of A/V Equipment (The Experts) $124,431.97.
Tax Savings S7465.92
Tax savings included in GMP Budget = $-38,847.00
Tax savings to date (PCCO #1) - $33.139.50
Balance $5707.50
Tax Savings This PCCO #3 $7465.92
Less Balance of Tax Savings in GMP-$5707.50
Tax Savings difference to be realized on this PCO $1758.42
ATTACHMENTS:
PCO#2000-002S DPO#4 AV- Executed.odf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
04/ 19/2021
No
($127,948.86)
PCO # Title
Schedule Impact
Amount
2000-003 CE #005 - DPO#4 A/V Equipment
($127,948.86)
Total:
($127,948.86)
CHANGE ORDER LINE ITEMS:
PCO it 20n0-n03- CE 9005 - DPO#A AN Eauinment
#
Budget Code
Description
Amount
1
2003.15-16-110.SUB
A/V Equipment- Material
$(124,431.97)
2
2003.15-16-110.SUB
AN Equipment Tax
$(7,465.97)
3
2003.15-18-150.SUB
AN Equipment Tax Savings
$5.707.50
Hedrick Brothers Construction Co., Inc. Page 1 of 2 Printed On: 4/21/2021 12:56 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
PCCO #003
#
I Budget Code
Description
Amount
4
1 2003.15-18-150.SUB
AN Equipment Tax Savings
$(1,758.42)
Subtotal:
$(127,948.86)
General Liability (0.00% Applies to all line item types.):!
$0.00
Contractor's Fee (0.00% Applies to all line item types.):
i $0.00
Subcontractor Default Insurance (0.00% Applies to all line item types.):
$0.00
Grand Total:
$(127,948.86)
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be decreased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach, 33401
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
PRINT NAME AND TITLE RRIN N ME AND TITLE
$6,013,394.00
($306,371.25)
$5,707.022.75
($127,948.86)
$5,579,073.89
HEDRICK BROS CONST CO INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
4'cic 4-22-2021
SIGNATURE DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 4/21/2021 12:56 PM
■ HE RI K
■ ■ ■ BROTHERS
S
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-005
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-005: Revision 3 Changes
TO:
VILLAGE OF TEQUESTA
FROM:
HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469
WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION:
2000-005 / 0
CONTRACT-
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
REQUEST RECEIVED FROM:
CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
STATUS:
Pending - In Review
CREATED DATE:
5/21 /2021
REFERENCE:
PRIME CONTRACT
#004 - Revision 3 Changes
CHANGE ORDER:
FIELD CHANGE:
No
LOCATION:
ACCOUNTING
Amount Based
METHOD:
SCHEDULE IMPACT:
51 days
PAID IN FULL:
No
TOTAL AMOUNT:
$160,711.35
POTENTIAL CHANGE ORDER TITLE: Revision 3 Changes
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #007 - Revision 3 Changes
Changes resulting from Plan Revision 1- 3
This change order consists of the subcontractor cost components that are a result of the Revision 3 Plan Change . It also includes a time delay
component as well. The total time of delay is based on the total time of the delay and the daily/monthly rates as identified in the contract for the General
Conditions and General Requirements. The total delay was calculated by
identifying the total number of days the schedule completion date increased
from original completion to the new completion date per the revised schedule. The total delay is 51 calendar
days.
ATTACHMENTS:
Rev#3 Cost Breakdown 5.21.Ddf Rev#3 Cost Breakdown 5.21.Ddf Tequesta - Change Order #1 revised 6-3-21.pddf_ Rev#3 Calender Duration
Backup 5.21.pdf-TCC- GMP Project Schedule.Ddf TCC- 5.21 Delay Schedule.pdf Rev#3 Daily GC's Calculation 5.21.pdf-Tequesta Rec
Center Deductive Change Order #1 (Decrease Height) 4-28-21.pdf AISI PROPOSAL- VILLAGE OF TEQUESTA- COMMUNITY CENTER.doc_
30759 Tequesta Rec Center Change order per 4-8-21 plans.Ddf Tequesta Rec Center RCO # 2 F&Lpdf- 21516 RCO 001-RFI#28- Steel Fab.pdf
TEQUESTA_REC CENTER C.O".docx
#
SubJob
Cost Code
Description
Type
Amount
1
PCCO #4 Rev. 3 Changes
15-16-110 - ELECTRICAL
Owner Accepted Added Electrical Scope
Subcontractor
$ 45,904.00
2
PCCO #4 Rev. 3 Changes
15-02-010 - SITEWORK
Site Work Changes
Subcontractor
$ 13,279.00
3
PCCO #4 Rev. 3 Changes
15-05-120 - STRUCTURAL STEEL
RFI#28 added 1.8T of Steel for additional loads
Subcontractor
$ 5,858.61
4
PCCO #4 Rev. 3 Changes
15-15-310 - FIRE SPRINKLERS
Steel Cost Escalation
Subcontractor
$ 5,100.00
5
PCCO #4 Rev. 3 Changes
15-02-805 - LANDSCAPING
Revised Landscape for Transformer
Subcontractor
($2,600.50)
6
PCCO #4 Rev. 3 Changes
15-09-610 - FLOOR TREATMENT
Ceramic and Carpet Material Increases
Subcontractor
$ 3,737.00
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 6/4/ 2021 09 :04 AM
� III
■ ■ BROTHERS
CONSTRUCTION
PCO #2000-005
7
PCCO #4 Rev. 3 Changes
15-10-650 - OPERABLE
Credit for smaller Operable Partitions
Subcontractor
($1,150.00)
PARTITIONS
8
PCCO #4 Rev. 3 Changes
15-15-410 - PLUMBING
Add sink, 3 faucets, Condensate Line to Drywall, and material
Subcontractor
$ 12,394.49
escalation
9
PCCO #4 Rev. 3 Changes
10-01-532 - OFFICE EQUIPMENT &
Office Equipment
Materials
$ 255.68
SUPPLIES
10
PCCO #4 Rev. 3 Changes
10-01-746 - GENERAL CLEANING
General Cleaning/Labor
Materials
$ 1,224.00
AND LABOR
11
PCCO #4 Rev. 3 Changes
10-01-025 - PLAN COPY EXPENSE
Plan Copy Expense
Materials
$ 255.00
12 j
PCCO #4 Rev. 3 Changes
10-01-515 - TEMPORARY FENCE
Temporary Fence
Materials
$ 255.00
13
PCCO #4 Rev. 3 Changes
10-01-521 - FIELD OFFICES &
Field Office
Materials
$ 2,550.00
SHEDS
14
PCCO #4 Rev. 3 Changes
10-01-523 - TEMPORARY TOILETS
Temporary Toilets
Materials
$ 511.70
15
PCCO #4 Rev. 3 Changes
10-01-311 - EXECUTIVE
Project Executive
Labor
$ 3.060.00
MANAGEMENT
16
1 PCCO #4 Rev. 3 Changes
10-01-318 - PROJECT MANAGER
Project Manager
Labor
$ 18,360.00
17
PCCO #4 Rev. 3 Changes
10-01-314 - SUPERVISION
Supervision
Labor
$ 27,685.86
18
PCCO #4 Rev. 3 Changes
10-01-317 - PROJECT
Project Coordinator
Labor
$ 7.577.07
COORDINATOR
19
PCCO #4 Rev. 3 Changes
10-01-310 -ACCOUNTING
Accounting
Labor
$ 2,273.07
20
PCCO #4 Rev. 3 Changes
10-01-460 - SAFETY
Safety
Labor
$ 506.94
Subtotal:
$147,036.92
General Liability: 1.30% Applies to all line item types.
$ 1,911.48
Contractor's Fee: 6.50 % Applies to all line Item types.
$ 9,557.40
Subcontractor Default Insurance: 1.50 % Applies to all line item types.
$ 2,205.55
Grand Total:
$160,711.35
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
Signature Date
7 02
Sig ture Date
TCC REC CENTER- REV 01,02,03 Cost Breakdown 5.21.21
Associated
Contract Company
Contract Type
Title
Sub CORN GMP to Rev#3 Description
Cost Time
LIGHTNING ELECTRIC INC
Subcontract
Electrical/ Light Fixtures
1
Owner accepted added electrical scope
$45,904.00 9
MECHANICOOL, INC
Subcontract
HVAC
N/A
BENCHMARK III CORPORATION
Subcontract
Concrete/Shell
1
Added reinforcing of slab areas to receive polished concrete
$13,098.00 2
2
Added column TC-2
$1,206.00 1
3
Added Beams B-1
$2,552.00 1
4
Added Concrete beam extensions per sheet S-8
$7,504.00 4
5
Added beam B-5 in lieu of 8-4 (deduct)
-S323.00 1
6
Added beams B-5
$1,S70.00 6
7
CMU Changes
$20,629.00
8
(Ommitted)
9
72 BD rebar lap detail add
$13,259.00 6
BCM CONSTRUCTION, INC.
Subcontract
Site Work
1
$13,279.00
WALLACE SURVEYING CORPORATION
Subcontract
Surveying
STEEL FABRICATORS LLC
Subcontract
Structural Steel
1
RFI#28, added 1.8T of steel for additional loads
$5,858.61
BORGZINNER, INC.
Subcontract
Cabinets and Casework
NICHOLS INDUSTRIES, INC.
Subcontract
Stucco
TONY RODRIGUES METAL FRAMING INC
Subcontract
Drywall & Metal Framing
DURA FLOOR, INC. dba DURA BOND COMPANY
Subcontract
Epoxy Flooring
ATLANTIC DOORS & HARDWARE INC
Subcontract
Doors, Frames and Hardware
HOFFMAN COMPANIES OF PBC, INC.
Subcontract
Painting
INSTATECH INDUSTRIES, INC.
Subcontract
Louvers
FARMER & IRWIN CORP
Subcontract
Fire Protection
1
Steel cost escalation
$5,100.00
DANIELS FENCE CORP
Subcontract
Site Furniture and PVC Fencing
FLORIDA EXOTIC A LANDSCAPE COMPANY INC
Subcontract
Irrigation & Landscape
1
Revised la ndscape for transformer
($2,600.50)
ATLANTIC INTERIOR SERVICES INC
Subcontract
Flooring and Tile
1
Ceramic & Carpet material increases
$3,737.00
BARON INTERNATIONAL LLC dba BARON SIGN
Subcontract
Signage
CROWN ROOFING & WATERPROOFING L-C.
Subcontract
Roofing
METRO CAULKING & WATERPROOFING
Subcontract
Waterproofing
SOUTHEASTERN SURFACES & EQUIPMENT
Subcontract
Operable Partitions
1
Credit for smaller Operable partition
($1,150.00)
BURGESS GLOBAL ENTERPRISES dba
Subcontract
Green Wallscape
HOLEMAN HOMES, INC
Subcontract
Hardi-Plank
CMS INTERNATIONAL GROUP L-C.
Subcontract
Windows and Interior Glass
1. Women's Vestibule: (1) sink (SK-1) D23322-3 and faucet 67425
2. Storage 111: (1) %" condensate line to (1) Drywell
CUSTOM PLUMBING INC
Subcontract
Plumbing (Main Construction)
1
3. Material escalation
$12,394.49
CORPORATE INTERIORS, INC.
Subcontract
Demountable Partitions
Total Rev#1-3 costs
$142,217.60
Deduct for Benchmarks changes previously submitted
-$59,695.00
$92,522.60
CTRIC inc.
4810 Georgia Avenue, West Palm Beach, FL 33405
Ph. 561-965-2323 Fax 561-965-2330
www.LightningElectdcinc.com
Our 60th Year!
June 3, 2021
Hendrick Brothers Construction.
2200 Centre Park West DR,
West Palm Beach, FL 33409
We are pleased to provide Change Order #1 based off of Addendum #1 dated 2-10-21. For the Project named
Village of Tequesta, located at 399 Seabrook road Tequesta, FL 33469 based upon plans by REG Architects Interiors
Planners.
• Deduct (2) type "J1" light fixtures per E401........................................................................-$1,463.00
• Provide and Install (2) type "EXEW" light fixture per E401.................................................
$595.00
• Provide and Install (3) type "D" light fixtures per E401.......................................................$1,423.00
• Deduct (2) Type "J2" light fixtures per E401..........................................................-$2,856.00
• Provide and Install four 3/4-inch raceways for car charger communication per E001 ........$2,254.00
• Provide and Install (2) data outlets in kid zone number 3 per E301..................................
$633.00
Provide and Install (1) floor box in kids zone number 3 per E301......................................
$1,228.00
• Provide and Install (1) GFI in kid zone number 3 per E301................................................
$322.00
• Provide and Install (5) quad outlets in lobby Key Kiosk per E301.......................................$909.00
• Provide and Install (1) data outlet in lobby Kiosk per E301.................................................$343.00
• Provide and Install (1) outlet in lobby ceiling per E301.......................................................
$239.00
• Provide and Install (1) data in lobby ceiling per E301........................................................
$343.00
• Provide and Install (3) data outlets in lobby per E301.........................................................$923.00
• Provide and Install (1) floor box with power and data in open workspace per E301............
$1,349.00
• Provide and Install (3) data's in gymnasium per E301........................................................$923.00
• Provide and Install (1) outlet in gymnasium per E301..........................................................$322.00
• Deduct for (1) data outlet in gymnasium E301.........................................................
$322.00
• Provide and Install (4) data outlets in youth activity room number 5 per E301 .....................$1,212.00
• Provide and Install (1) data outlet in youth activity room number 5 per E301......................
$343.00
• Provide and Install (3) data outlets in adult activity number 1 per E301 ..............................
$923.00
• Provide and Install (2) data outlets in adult activity room number 2 per E301.....................
$633.00
• Provide and Install (1) GFI weatherproof on roof top per E302...........................................
$748.00
• Deduct 60 KW Generator with 400A ATS............................................................................
$22,624.00
• Provide and Install 125 KW Generator 400A ATS...............................................................$35,788.00
• Audio Experts.....................................................................................................................
$18,712.00
Totalfor Change Order #1............................................................................................................. $45,904.00
Total Added Days underground scope- 5 Days
Total Added Days interior rough scope- 4 Days
Quote is valid for 30 days.
Billing done in AIA billing format on 251h each month and payment due by 15m of the following month.
Any patching of drywall, concrete, asphalt or roof to be done by others.
Any changes by owner or dictated by inspector not included.
Overtime work is not included. Hours based on a 40 hour week working schedule Monday through Friday.
Thank you for your consideration.
Devin Ouellette, Chief Estimator
Lightning Electric, Inc.
Accepted Date
PENINSULAR ELECTRIC DISTRIBUTORS, INC.
MEMBER 1301 Old Okeechobee Road MEMBER
West Palm Beach, FL 33401
/MARK GROUP Phone: (561) 832-1626 / (800) 842-6816 NAED
FAX: (561) 832-2108
CUSTOMER: LIGHTNING ELECTRIC DA TE: 31812021
JOB NAME: VILLAGE OF TEQUESTA ADDERS
ADDRESS.- ATTN DEVIN PO#:
ITEM QUANTITY
MANUFACTURER
CATALOG NUMBER
UNIT
PER
TOTAL
1
1 ABL
LDN6 35/20 L06AR LS MVOLT GZ10
130.00
E
1
TYPE BI
2
1
FOCA
FLCY4-RD-"""-1500L-35K-1C-UNV-SC
350.00
E
2
L1 1-C72-DNT-WFL-CD-"
2
TYPED
3
1
FLUX
PMI-F-D-C-3 5-"-06-S-F2-M-06
855.00
E
3
TYPE J2
4
1
FLUX
PM1-F-D-C-35-"-04-S-F2-M-06
605.00
E
4
TYPE JI
5
1
FLUX
PM1-F-D-C-35-"-08-S-F2-M-06
999.00
E
5
TYPE J3
6
1
ABL
LHQM LED R HO SD RO
170.00
E
6
TYPE EXEW1
6
6
6
6
6
6
6
6
6
6
6
6
TOTAL COST: $
JAS'ON CrrOS'St Y -
Tax NOT Included
Page 1 of I
III I11 I I II11111 I I I II I I I 111 II 111
Quotation
REXEL 1106 WPB
1707 OLD OKEECHOBEE ROAD
WEST PALM BEACH, FL 33409-5225
561-845-6110
Fax (561) 845-7558
QUOTE TO:
QUOTE DATE
QUOTE NUMBER PAGE NO.
02/18/2021
S130033606 1 of 1
OUST Po#:
TEQUESTA REC CENTER CAR
JOB/REL#:
SHIP TO:
LIGHTNING ELECTRIC INCORPORATED LIGHTNING ELECTRIC INCORPORATED
4810 GEORGIA AVE 4810 GEORGIA AVE
WEST PALM BEACH, FL 33405-2816 WEST PALM BEACH, FL 33405-2816
CUSTOMER NUMBER
CUSTOMER PHONE#
ORDERED BY
OUTSIDE SALESPERSON
186613
Devin Ouellette
David Reisner
INSIDE SALESPERSON
INSIDE SALESPERSON PHONE#
INSIDE SALESPERSON EMAIL
HOUSE
WRITER
SHIP VIA
TERMS
SHIP DATE
FREIGHT ALLOWED
David Reisner
WPB S
2% 10th, PROX 25th
02/18/2021
No
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
Many Rexel USA manufacturing partners have advised that until
further notice they reserve the right to amend the delivery
date, the price, the scope or quantity of supply and/or other
terms and conditions set out in their offer or quotation to
the extent affected by the COVID-19 pandemic.Be advised that
Rexel USA considers any COVID-19 related changes imposed by
manufacturers as outside its reasonable control and subject
to Force Majeure provisions.
4ea
PWRT DIRECT ITEM
5330.000/ea
21320.00
P20DPN - 30AMP DUAL PEDESTAL MOUNT
NETWORKED CAR CHARGER
Pn: 354404
8ea
PWRT DIRECT ITEM
375.000/ea
3000.00
EVC-NET-1 - 1 YEAR NETWORK
SUBSCRIPTION PER PORT
Pn: 354404
lea
PWRT DIRECT ITEM
425.000/ea
425.00
EVC-NET- ACTIVE - 1 TIME NETWORK
ACTIVATION FEE FOR ALL CHARGERS
Pn: 354404
8ea
PWRT DIRECT ITEM
375.000/ea
3000.00
EVCS-A-SI - CABLE RETRACTORS
Pn: 354404
All sales transactions are subject to credit approval. Any quotation
and all transactions with Rexel are conditioned upon Rexel's Terms
Subtotal
27745.00
and Conditions of Sale located at http://www rexelusa.com/terms.
Quotation is valid for 30 days after the date of issue unless
SB�H Charges
0.00
otherwise specified. Items subject to governmental tariffs effective
on or after quotation will be price in effect at time of shipment
unless otherwise specified. Quotation for commodity items is valid
Sales Tax
1778.95
for the day of the quote only unless otherwise specified. All
applicable taxes will be itemized and charged at the time of sale. Returns
may be subject to a restocking fee particularly if returned beyond 90 days
Total
29523.95
from original purchase date. Returns for special orders are subject to
vendor authorization before return can be processed.
11111111111111111111111111111111
Quotation
REXEL 1106 WPB
1707 OLD OKEECHOBEE ROAD
WEST PALM BEACH, FL 33409-5225
561-845-6110
Fax (561) 845-7558
QUOTE TO:
LIGHTNING ELECTRIC INCORPORATED
4810 GEORGIA AVE
WEST PALM BEACH. FL 33405-2816
QUOTE DATE
QUOTE NUMBER PAGE NO.
12/08/2020
S129494366 1 of 1
OUST Po#:
TEQUESTA REC CENTER
JOB/REL#:
SHIP TO:
LIGHTNING ELECTRIC INCORPORATED
4810 GEORGIA AVE
WEST PALM BEACH, FL 33405-2816
CUSTOMER NUMBER
CUSTOMER PHONE#
ORDERED BY
OUTSIDE SALESPERSON
186613
561-965-2323
David Reisner
INSIDE SALESPERSON
INSIDE SALESPERSON PHONE#
INSIDE SALESPERSON EMAIL
HOUSE
WRITER
SHIP VIA
TERMS
SHIP DATE
FREIGHT ALLOWED
David Reisner
WPB S
1 2% 10th, PROX 25th
12/08/2020
No
ORDER QTY
DESCRIPTION
UNIT PRICE
EXT PRICE
Many Rexel USA manufacturing partners have advised that until
further notice they reserve the right to amend the delivery
date, the price, the scope or quantity of supply and/or other
terms and conditions set out in their offer or quotation to
the extent affected by the COVID-19 pandemic.Be advised that
Rexel USA considers any COVID-19 related changes imposed by
manufacturers as outside its reasonable control and subject
to Force Majeure provisions.
lea
GNC DIRECT ITEM
26171.689/EA
26171.69
QT13068ANAC - 13OKW 120/240V 1 PH
NATURAL GAS GENERATOR ALUMINUM
ENCLOSURE LIQUID COOLED
Pn: 93958
lea
GNC RTSW400A3 SMART SWITCH SERVICE
2379.510/EA
2379.51
RATED 400A 120/240 1 OHM NEMA 3R
Pn: 863951
UPC: 69647161993
All sales transactions are subject to credit approval. Any quotation
and all transactions with Rexel are conditioned upon Rexel's Terms
Subtotal
28551.20
and Conditions of Sale located at http://www.rexelusa.com/terms
Quotation is valid for 30 days after the date of issue unless
S&H Charges
0.00
otherwise specified Items subject to governmental tariffs effective
on or after quotation will be price in effect at time of shipment
unless otherwise specified. Quotation for commodity items is valid
Sales Tax
1786.87
for the day of the quote only unless otherwise specified. All
applicable taxes will be itemized and charged at the time of sale. Returns
may be subject to a restocking fee particularly if returned beyond 90 days
Total
30338.07
from original purchase date. Returns for special orders are subject to
vendor autnonzanon before return can De processea.
Modified: 3/9/2021
TH EEXPERTS
CREATING YOUR AUDIO/VIDEO LIFESTYLE
Village of Tequesta
Community Center AN - Change Order 3.3.21
345 Tequesta Dr.
Tequesta, FL 33469 United States
The Experts • 7992 SW Jack James Drive • Stuart, Florida 34997
Tel: 772.232.9114 • Fax: 772.232.9688 • www.TheExperts.biz
Revision
Page 1 of 6
Presented By:
TH EEXPERTS
ORFATING YOUR AU010/VI5F0 � IFFSTYLF
The Experts
7992 SW Jack James Drive
Stuart, Florida 34997 USA
772.232.9114
Scope of
Modified: 3/9/2021
Revision: 0
Community Center AN -
Change Order 3.3.21
Village of Tequesta
345 Tequesta Dr.
Tequesta, FL 33469 United States
This proposal is for work to be completed at Village of Tequesta Community Center.
This change order includes:
101 Lobby
- Upgrade TV mount from flat mount bracket to ceiling mount*
- Add Optoma 1080p ultra -short throw laser projector
- Add Chief ceiling mount for projector"
- Add Crestron HDMI extender receiver for projector*"
- Add Crestron HDMI extender wall plate transmitter for projector
" Ceiling mounts' drop spec'd with 60'-84". May need to be changed depending on final application specs.
Projector only spec'd for HDMI input from desk. NOT on Crestron distributed media network.
*** No projector screen spec'd.
113 Open Workspace
- Upgrade Crestron 8 button Cameo to 7" touch panel
122 Adult Activities #2
- Crestron 7" wall -mount touch panel*
* Panel controls Adult Activities ONLY
123 Kid's Zone #3
- Upgrade Crestron 8 button Cameo to 7" touch panel
Exclusions are as follows:
- Permits/Submittal
- After hour/Weekend work
- Networking
- We estimate 2 technicians will require approximately 3 days to complete this installation inclusive of
configuration, programming, test and demo of items listed.
The Experts • 7992 SW Jack James Drive • Stuart, Florida 34997
Tel: 772.232.9114 • Fax: 772.232.9688 • www.TheExperts.biz
Page 2 of 6
Scope
Change Order(s):
-During the course of a project, the Client and/or his/her authorized rep may request changes, additions and/or
modifications without invalidating the contract.
Procedure:
The request for changes, additions, or modifications will be submitted in writing
The Client (or authorized representative) will receive a Change Order detailing additional labor, materials, and
equipment charges associated with the change request.
• The Client (or authorized representative) signs off on the resulting change order authorizing modifications to
the original scope of work and agreeing to changes in the overall project timeline, if needed. The billing
associated with the change order is due upon receipt and does not constitute payment towards this contract.
Labor Warranty: Your new system comes with The Experts 90 day limited labor warranty.
If a component The Experts supplies within the system is defective in normal use due to a fault of the product(s)
and/or materials, The Experts will at its discretion replace the defective item under it manufacturer's warranty for
a period of 90 days from the date of substantial completion.
Substantial completion is defined here as the point in time when your equipment has been delivered and
installed.
Warranty after 90 Days: Many components in your system will have manufacturer's warranties that extend past
the 90 day terms of this plan. If an item(s) becomes defective after the 90 day term is up The Experts will remove,
submit for repair, and reinstall this equipment for you at our standard service rate.
Non -Payment: Payments not received within 7 days of invoice is subject to interest of 18%
Credit Card Payments: The Experts would be glade to take your Credit Card payment, however credit card
payments are subject to a 3% surcharge.
Deposits, Balances, and scheduling your project:
Deposit: Before your project can be added to The Experts work schedule, a deposit consisting of all equipment,
Misc. Parts, and Sales Tax must be received by our office.
Cancellation: All deposits are refundable within 7 days, however in some cases, a re stocking fee (of up to 25%
for any equipment already ordered, plus all freight charges will be deducted from your deposit.
Balance: Your balance consisting of the labor and any additional changes are due at completion of the project.
***This proposal is valid 45 days from date of submission'
The Experts • 7992 SW Jack James Drive • Stuart, Florida 34997
Tel: 772.232.9114 • Fax: 772.232.9688 • www.TheExperts.biz
Page 3 of 6
THEEXPERTSQty Description
1
Wall Plate -Data/Control Pass -Through
Single -gang pass -through with (1) Data and (1) Control cable
***Includes (1) pass -through wall plate, (1) Cat6, and (1) Cat5e cable
•
1
Optoma ZH4000ST
Ultra Short Throw Laser Phosphor Projector, 4000 lum
1
Chief RPAU
3-axis adjustable universal projector mount
40
1
Chief CMA395
Vaulted Ceiling Adapter Bracket (black)
1
Chief CMS0507
5' - 7' Adjustable extension column, black
1
Crestron HD-TX-101-CAG-E-13-T
DM Lite HDMI over CATx transmitter, wall plate, black textured
Crestron DM-CBL-8G-P
Digital Media 8G cable, plenum (per foot)
1 Crestron HD-RX-101-C-E
DM Lite HDMI over CATx receiver, surface mount
1 Chief MCM10
Fusion medium ceiling mount for flat panel TV, black
4V
1 Chief CMA395
Vaulted Ceiling Adapter Bracket (black)
1 Chief CMS0507
5' - 7' Adjustable extension column, black
1 Crestron TSW-1070-B-S
10.1 in. Wall Mount Touch Screen, Black Smooth
The Experts CAT6-ORG
Category6 cable 23/4pr - ORANGE, for system control (per foot)
* Price Includes Accessories
Presented By: The Experts
Project Name: Community Center A/V - Change Order Project No.: 2973
3.3.21
Price
$79.82
$2,599.00
$229.95
$59.99
$185.00
$560.00
$330.00
$277.60
$59.99
$185.00
$2,840.26
3/9/2021
Page 4 of 6
THEEXPERTS Qty Description
1 Crestron TSW-1070-B-S
10.1 in. Wall Mount Touch Screen, Black Smooth
/j
The Experts CAT6-ORG
Category6 cable 23/4pr - ORANGE, for system control (per foot)
1 Crestron TSW-1070-B-S
10.1 in. Wall Mount Touch Screen, Black Smooth
The Experts CAT6-ORG
Category6 cable 23/4pr - ORANGE, for system control (per foot)
Miscellaneous Items:
Price
$2,840.26 *
$2,840.26 *
Project Subtotal: $13,087.13
1 CREDIT ON UPGRADES ($814.99) ($814.99)
(-2) C2N-CBD-P-W-T
(-1) VLL5BQ
Miscellaneous Items Total: ($814.99)
* Price Includes Accessories
Presented By: The Experts
Project Name: Community Center A/V - Change Order Project No.: 2973
3.3.21
3/9/2021
Page 5 of 6
M _-EXPERTS Project Summary
Equipment:
$13,087.13
Miscellaneous Parts & Materials:
$327.20
Pre-Wire/Rough Labor:
$243.75
Trim Installation Labor:
$35.00
Finish Installation Labor:
$1,268.75
Programming Labor:
$1,662.50
Sales Tax:
$1,163.70
Client:
Discounts: ($814.99)
Grand Total: $16,973.04
Date
Contractor: The Experts Date
Price Includes Accessories
Presented By: The Experts
Project Name: Community Center A/V - Change Order Project No.: 2973
3.3.21
3/9/2021
Page 6 of 6
BCM CONSTRUCTION, INC.
17810 93rd Road N.
o� Loxahatchee, FL 33470
PAGE 1
PROPOSAL
Office:561-793-7543
Fax:561-790-6996
PROPOSAL SUBMITTED TO
TEQUESTA REC CENTER AT CONSTITUTION
DATE
HEDRICK BROTHERS CONSTRUCTION
PARK
4/29/2021
STREET
2200 CENTREPARK WEXT DRIVE
CHANGES TO BASE BID
CITY
WPB, FL
CHANGES TO BASE BID
1) Modification inlet basin #5
$2,960.00
2) Addition of yard drain #5 and one 12" x8" wye
$2,557.00
3) Relocation of inlet basin #1 and added 15" pipe 531/f
$1,590.00
4) Addition of yard drain #6
$2,391.00
5) Addition of yard drain #7
$2,341.00
6) 48 I/f of 15" HDPE for yard drain #6 and #7
$1,440.00
TOTAL CHANGES TO BASE BID
$13,279.00
All material is guaranteed to be as specified. All work to be completed in a
AUTHORIZED SIGNATURE
workmanlike manner according to standard practices. Price above is only an
ROBERT L. BISKUPIAK, JR.
estimate of foreseen conditions. Unforeseen conditions can affect the amount of
time to complete the work, therefore increasing or decreasing estimate. All
agreements are contingent upon strikes, accidents or delays beyond our control.
This proposal subject to acceptance within thirty (30)
Owner is to carry file, tornado and other necessary insurance. Our workers are
days and is void thereafter at the option of the
fully covered by Workman's Compensation Insurance.
undersigned.
ACCEPTANCEPROPOSAL — The above prices,
specifications and conditions are satisfactory and hereby
Signature
accepted. You are authorized to do the work as specified.
Payment will be made as outlined above.
Signature
DATE OF ACCEPTANCE
5 F
STEEL FABRICATORS, LLC
721 N.E. 44th Street
Fort Lauderdale, FL 33334
Phone: 954-772-0440
Fax: 954-938-7527
REQUEST FOR CHANGE ORDER
NUMBER: 001.0
TITLE: RCO #001.0, RFI #28 DATE: 03/17/21
PROJECT: 21516 Tequesta Rec Ctr Ph 2 JOB: 21516
TO: Wanda Stan
Hendrick Brothers Construction Co. REASON: Price Only
Centrepark W. Drive CIC REFERENCE:
West Palm Beach, FL
Phone: 561-689-8880
Fax:
DESCRIPTION OF CHANGE
RFI #28. Cost associated with additional tonneage due to concentrated loads. Please refer to Can Am CO 01
Item
Description
Quantity
Units
Unit Price
Net Amount
001T
Steel Joist
1.00
Lot
4,714.00
4,714.00
002T
Sales Tax at 0.07
330.00
330.00
003
Overhead at 0.1
504.40
504.40
004
Profit at 0.05
252.20
252.20
005
Bond at 0.01
58.01
58.01
By my signature below, I attest that I am authorized by my firm to enter into an agreement to purchase goods and/or
services. As the Buyer, I hereby authorize Steel Fabricators, L.L.C. to proceed with the additional work described herein
and do guarantee compensation on the basis noted above. If schedule impact listed below is zero or not listed, additional
contract time required will be determined by Steel Fabricators at the time of implementation due to changes described
above.
The Contract Sum Will be Increased
5,858.61
The Contract Time Will Not be Changed
TBD
ACCEPTED:
BY: BY:
DATE: DATE:
PAGE 1 OF 1
Cr'1DKA- F (Yl n1 RTG RF
DocuSign Envelope ID: 681 A481 E-2271-4457-84CB-C94BA721 F29F
Date
Company
Attention
Fax
Email
03/15/2021
STEEL FABRICATORS LLC
Change order
Change Order No
Issued by
Eduardo Donminguez Project
(954)938-5862 Project Code
edominguez@sfab.com
140 S. Ellis Road
JACKSONVILLE
FL,UNITED STATES,32254
Tel: (904)781-0898
Fax:(904)781-4090
Email: jeremy.lord@cscsteelusa.com
001-1
Jeremy Lord
VILLAGE OF TEQUESTA JOIST ONLY
200600
You will find attached the contract modification for the above mentioned
project. Please sign and return the change order.
If you have any questions, please feel free to contact us.
Regards,
Jeremy Lord
DocuSign Envelope ID: 681A481E-2271-4457-84CB-C94BA721F29F
Change order
Date 03/15/2021 Change Order No
Company STEEL FABRICATORS LLC Issued by
Attention Eduardo Donminguez Project
Fax (954)938-5862 Project Code
Email edominguez cDsfab.com
140 S. Ellis Road
JACKSONVILLE
FL,UNITED STATES,32254
Tel: (904)781-0898
Fax:(904)781-4090
Email: jeremy.lord@cscsteelusa.com
001-1
Jeremy Lord
VILLAGE OF TEQUESTA JOIST ONLY
200600
The sales contract mentioned above is revised as follows:
Description of revisions
Additions
Deductions
Per RFI-003 response:
Reference framing plan S-2 and sections 6 and 7 on S-5 and sections
18 and 19 on S-6. Since no additional loading is shown in the
contract drawings for the additional framing, we asked if the
joist designation already had this loading included. The response
that was received was that we needed to add addtitional loading
into the joist designs pe the SSK-005 and SSK-007 that were included
with the RFI response. This caused a joist naterial weight increase
of approximately (1.8) tons. $4,464.00
- Additional drafting/engineering hours to incorporate the added
loading. $250.00
Total modifications (USD)
$4,714.00
$0.00
Previoustotal
--- ------------ ---
-------------------
Chan a Order Total (USD)
$4,714.00
TAXES EXTRA
TAXES EXTRA
TAXES EXTRA
ITAXES EXTRA
Accepted by Canam Accepted by client
Authorized Canam representative Authorized client representative
Jeremy Lord
5�F
Steel Fabricators, LLC
721 NE 44th Street
Fort Lauderdale, FL 33334
Phone:954-772-0440
Request For Information
To: Doug Gordon
Hedrick Brothers Construction
2200 Centrepark W Drive
West Palm Beach, FL 33401
Subject: Can Am RFI 003-Concentrated Loads
Sent Via: E-mail
Requested Information:
Please refer to Can Am RFI 003:
Date: 3/5/2021
Page 1 of 1
RFI #: 509
Job #: 0921516
Tequesta Community Center
CC: Kim Blair
Hedrick Brothers Construction
Eduardo Dominguez
Steel Fabricators, LLC
Vibin Koshy
Steel Fabricators, LLC
Reference framing plan S-2 and sections 6 and 7 on S-5 and sections 18 and 19 on S-6. CSC
understands that any loads from the additional framing have been accounted for in the specified
designations or by the use of increased and/or double joists. CSC will make no additional allowance for
this unless provided otherwise. Added costs for changes in design requirements may be issued.
The information requested above is crucial to the completion of the project. Please respond by
3/10/2021. If the requested response time is not met, the project may be delayed.
Eduardo Dominguez
Joist must be design for all concentrated loads as per Joist Note #2 on
S-3. See attached sketches SSK-005 thru SSK-007 for design loads.
A do
CANAM STEEL CORPORATION
REQUEST FOR INFORMATION
To: Steel Fabricators LLC
Attention: Eduardo Dominguez
E-mail /Fax:edominguez@sfab.com
Cc:
Attention:
E-mail /Fax: Need Reply By: 3/11/2021
Project Name: Village of Tequesta
Author Name: Craig Nasuti
Author RFI #: 003
Author Job No.: 200600
Date Issued: 03/05/2021
Subject: Additional Loads
Discipline: Secondary Structural Steel
Drawing Reference and Drawing Date: S-2 & Secs 6 &7 on S-5 & Secs 18 & 19 on S-6 dated 12-18-20
Specification Reference:
Question/Description of Issue: EOR, reference framing plan S-2 and sections 6 and 7 on S-5 and
sections 18 and 19 on S-6. CSC understands that any loads from the additional framing have been
accounted for in the specified designations or by the use of increased and/or double joists. CSC will
make no additional allowance for this unless provided otherwise. Added costs for changes in design
requirements may be issued.
Suggestion:
Attachments:
Potential Cost Impact: Yes
Response:
By: <Name>
<Company>
Drawing Update Required? ❑ Yes
Attachments:
Potential Schedule Impact: Yes
Date:
❑ No
V)
Q R
zJ w O
W V)
�w
�M U
O L) �j Z Z c� W
0 o R
wa �J �. O
o � �o -o
orr ww n n
S, Lix
CL tl LI) O J ® J ®
tl
A3
30
w
0
(n o
Z o I ��
QJ
wLJ
o
CL
U �g X
Q _ pe)
F- \ r7
Q Lo J 11 1
rl I
rl r
1 1
r r U
1 1 0
r r
1 0
I z
rr 1 0 o
q 1 in
r
r@ X
11 = z LO
�r o C
1 I
rl I D U Z v Cl. F- 00
4 1 Q V O xN 3 U
Ir r �I w 6
\o x
I 1 0
4 1 o o X �.
X �
4 1 i —�
4
1 1 cD
X X
LLJ
I f rjo
Ir 3 J N
4 r
11 I
L- J
QL-
n pt
LL-
z¢
w� U
�w
—� w
J '^
O U v,
W o-
or
>~
o�
� n r
. 't
0
O� Z�
Q O c`
y > v
V YmL-Ljrn
CP
Z Q c co coo ch
' i a) 00
J06rm
mo wz0)<io�
Z Z m d
0 Z d
O CLO
0 \
Z�
~
(A< N
O w I
it
oQ C+
Q
r
Q
w p� oW
mr,
II
�
oN �w
m= ~U
r
Up
\N
T
��
x OLLI
cn 0 CL
N U ..
N
-
C�
D-
Z
2
Z
Q
F
a
J
0
('WIS) S—S/d
w
v=i ^
z
LLJ
LLi
N
3 x
0 J
v
U1
OCL
QZ
\_
••
W
J ui
U7
Z O
Q W
Q
X g
O O
J Z
Q J
Ul
4
�m
Ja_
Lnrn0
Q W
J ^
W
W
u
Cl-
U�
O _j
F-:w
0 U
\ O
In .
N 0
co ® cr
W
N�� �_
_
V)Z
\J Q x
t0
0 J
.Ni m 0
W
W
W
H
ul
J` 0
CCC rry J
LLI
3. O Li
C�
0
20 Opp
O
...
E g
ZU 0 U -<
F-O
Ulx
"
v
U) 9 OOwm
�0
W'^
cl)m LO20 ®m0
Oda
V,
L
x
U o cn
N
IL 1 LL.
> U) of
0
04
OZ�
�ZcnIt
Q O o cc"))
N � �
VYmwrn
ZQcuCcM
J N op
J0sr_m—
WZQ)aS
Z CO d
.r
O0Za�
OECD
a
O
J
I
♦�
Q �-
w z Y
Q
V)
<z
II
= U
"Zth
<
Qz
mm
0 CL0
m
N
CL ~ 0
�
U w
-}
g
N O W
x
zw
0 Ln
r
(n m
N
U . .
V)
--
j
J
z_
w
2
~
Q
W
z
0J
z
W J
0-H�
0a
QO_
Jm
3w
LO
w
zw
¢ w
zm``'
w
CL
m
X`)
J Q
U
�w
s 6
CL
x=
W
W
x
00 rh N
N
U ..
0 U
\ O
L.
3 N M
® W
N 0
J Q x
m V) 3
N �
w
�Ow
z
O
_ �UQ
p
era
2W Op
F
ZU 0 m
�2Q
ONZ
F-o
V)w
U
o0w
CO
00
n Z a0 c0 I~—
U
U cnU Lo 0 ®000
�0
LOH
x
Uo cn04
H Y IL
>t�wci
®1 a!nw & Irwin!
Farmer & Irwin Corporation
3300 Avenue K., Riviera Beach, FL 33404
P. 561.842.5316, F. 561.842.5999
REQUE}ST FOR CHANGE ORDER [RCO)
Please Sign and Neturn to rarmer a irwin _uip
------------
Po: Hedrick Brothers Construction Project: Tequsta Rec Center
2200 Centerpark West Drive A/E Reference:
West Palm Beach, Florida 33409
G C Reference:
gttn: Kim Blair Requested By: General Contractor
scription of Change: Steel Pipe Increase From Dates 1/19/2021-- 3/19/2021
Drawings Affected:
Comments:
We have received and reviewed your request and find that FIRE PROTECTION WORK is involved.
It therefore appears necessary to prepare a cost proposal at this time
JOB SCOPE: FIRE PROTECTION WORK
COST PROPOSAL:
TOTAL MATERIALS & EQUIPMENT $4,434
Steel Pipe Increase From Dates
Inclusions:
1/19/2021-- 3/19/2021
Labor Summary (Man -Hours)
Supervision 0.0 $0
Foreman 0.0 $0
Journeyman 0.0 $0
Apprentice 0.0 $0
Excavation 0.0 $0
Assistant Designer 0.0 $0
Lead Designer 0.0 $0
TOTAL LABOR 0 $0
2nd Tier Subcontractors and Equipment $0
Exclusions:
Permits $0
TOTAL DIRECT COST $4,434
2nd Tier Subs, Overhead @ 0.00% $0
Direct Cost Overhead @ 0.00% $0
TOTAL COST $4,434
Profit @ 15.00% $665
Bond @ 0.00% $0
Combined O/H & Profit @ 0.00% $0
TOTAL THIS PROPOSAL $5,100
This proposal may be withdrawn by us if not accepted within 0 working days.
Time extension requested: 0 working days.
submitted by:
Gary Fraser
proved by:
Date:
3/19/2021
gnature:
[Diate:
?&I Job #:
TBD
?&I RCO #:
2 Revision #:
Landscaping
Irrigation
4o16 SW Moore Street Palm City FL 34990
PROPOSAL
Date
Estimate #
4/12/2021
30759
Name / Address
Hedricks Brothers
2200 Centre Park West Ste 100
West Palm Beach, FL 33409
772-286-2924 office 772-286-1417 fax
Project
FloridaExotic@hughes.net
Tequesta Rec Center
Qty
Item
Size
Cost
Total
CHANGE ORDER
Plan Date 4/8/2021
DELETE:
-1
Quercus virginiana / Live Oak
18' oa
1,700.00
-1,700.00
-1
Chamaerops humilis / Silver European Fan Palm
4-5'
650.00
-650.00
-45
Chrysobalanus horizontalis / Horizontal Cocoplum
12"x12"
14.50
-652.50
-22
Ilex vomitoria 'Stokes Dwarf
12"x12"
9.00
-198.00
ADD:
3
Sabal palmetto / Cabbage Palm
8-10' ct
185.00
555.00
7
Podocarpus macrophyllus 'Pringles'
2'x2'
35.00
245.00
1
Total Deductive Change Order
2,400.50
2,400.50
Signature
Total $0.00
ATLANTIC
SERVICES,N�
REVISED PROPOSAL
Hedrick Brothers
Centrepark West Drive
West Palm Beach, FL 33409
Phone: 561-308-2995
Fax:
Attention: Kim Blair
Plans Dated: 12/18/20
Revisions: # 04/08/21 REVISED DRAWINGS
Addendums acknowledged: # 1 DATED 1/12/21
Pages 1 of 2
04/ 16/21
Job Name: Village of Tequesta
Community Center
Job Location: Tequesta, FLORIDA
Specification Section: 09310 CERAMIC, 09680 RESILIENT and CARPET
CERAMIC TILES ( 6 restroom)
CARPET AND RESILIENT FLOORING
CERAMIC MATERIAL INCREASE
CARPET MATERIAL INCREASES
$ 25,600.00
$ 9,963.00
Total: $ 35,563.00
TOTAL MATERIAL INCREASES
$ 39600.00
$ 137.00
$ 39737.00
TOTAL REVISED PROPOSAL $ 399300.00
GREG.COX, Project Manager
NO PERFORMANCE BOND INCLUDED.
PLEASE READ THE FOLLOWING PAGE.
ATLANTIC
Isl Ih, AK
SERVICES,.
Pages 2
EPDXY FLOORS AND 6" EPDXY BASE AT RESTROOMS- BY OTHERS
SECTION # 09310 CERAMIC- NO SPECS PROVIDED
RESTROOMS WALLS TO BE BY DALTIL COLOR WHEEL LINEAR 8"x 24" MATTE BISCUIT K775
4X16 BULL NOSE TILE MATTE BISCUIT K775
WAINSCOTT TO BE 6--5" PER DRAWINGS -
TILE FULL HEIGHT AT VANITY WALLS ONLY
ACCENT BAND RETRO ROUND 1 X 1
MENS - BLUE AND CREAM AT VANITY. 12" BANDS
WOMENS- YELLOW AND CREAM AT VANITY- 12" BANDS
UNISEX RESTROOM WITH 12" BAND AT PERIMETER.
METHOD OF INSTALLATION TO BE THIN -SET WITH STANDARD GROUT.
SECTION # 09660 RESILIENT FLOORING
ROPPE 4" RUBBER COVE BASE 1/8 GA. OR EQUAL FOR CARPET AND CONTRETE FLOOR
AREAS. B 1 LOCATIONS
SECTION # 09560 CARPET —
FT-7 CARPET TILE TO BE BY" SHAW CARPET TILE "DIFFUSE" COLOR FLYWAY
FT-5 SHAW CARPET TILE BELONG TILE- 4 COLOR.
METHOD OF INSTALLATION TO BE GLUE DOWN.
EXCLUSIONS:
EXCLUDING EPDXY FLOORS AND 6" EPDXY BASE AT RESTROOMS.BY OTHERS.
EXCLUDING ALL TARKETT SPORT FLOORS- BY OTHERS
EXCLUDING ALL FLOOR PROTECTION
EXCLUDING ALL OTHER FINISHES NOT MENTIONED ABOVE.
SSE SPACE MANAGEMENT
A DIVISION OF SOUTHEASTERN SURFACES & EQUIPMENT
Florida State Certified M. WBF
Change Order Request # 1
TO: Hedrick Brothers DATE: 4/28/2021
2200 Centrepark West Dr PHONE: 561-689-8880
West Palm Beach, FL 33409 EMAIL: dgordon@hedrickbrothers.com
ATTN: Doug Gordon JOB #: 24122-04282021
PROJECT: Tequesta Rec Center
Tequesta, Florida
We are pleased to offer the following change order:
Deductive Change Order to decrease height from 13'-7.5" to 10'-0"
Change Order #1
Southeastern Surfaces & Equipment, Inc.
$ 1,150.00
By: 51da i�clliaa
Assistant Project Manager, Space Management, LLC
Phone 386-428-8875
Email ekillian(aD-sseteam.com
P.O. Box 602 • 569 Canal Street • New Smyrna Beach • Florida • 32170
Phone: (386) 428-8875 • Fax: (386) 428-8767
www.sseteam.com
SSE SPACE MANAGEMENT
A DIVISION OF SOUTHEASTERN SURFACES & EQUIPMENT
Florida State Certified MIWSE
Notes:
• We accept Visa, Master Card and American Express. Payments made using a Visa or Master Card will require an additional fee of
2%. American Express payments will require an additional fee of 2.5%.
• Sales/Use taxes are INCLUDED in above bid amount.
• 50% Deposit required at time of Order. Balance due on completion, with prior approved credit.
Payment and Performance Bonds are NOT INCLUDED in the above price. Add 1 % for our standard bond form. If alternate bond
forms are required there may be an additional cost and the forms will be subject to approval by our bonding company.
Removal and disposal of existing equipment or materials is NOT INCLUDED.
• Materials stored at owner or GC's request will incur storage fees and handling charges.
• All electrical service requirements, including conduit, wiring and/or final hook which may be required shall be provided by
electrical subcontractor.
• Hoisting for non -ground floor access, unless specifically indicated above is not included.
• 100% Restocking fee on all material.
Permits, if required, are not included and shall be provided by others at others expense.
• Audience Seating —Aisle lights, "special/custom/designer" (other than standard) fabrics, flooring finishes, other accessories
(i.e. Tablet arms, donor plates, etc.), loose seating (i.e. folding chairs), or finished caps for floor anchors are not included unless
specifically indicated above.
• Exterior Grandstands — All site work including clearing, grading or leveling is excluded. Concrete slabs which may be required
beneath the grandstands are not included.
Telescopic Bleachers — All electrical connections including manual disconnect shall be provided by electrical subcontractor.
• This quotation is good for 60 days and subject to delivery and installation in six months.
TERMS AND CONDITIONS
• FINANCE CHARGES Purchaser will receive monthly statements; however, payment is due upon receipt of original invoice. If the balance shown
on a monthly statement is not paid before the 30'" day of the same month, interest will accrue on the unpaid amount at the highest rate allowable
by Florida law.
• PERSONAL JURISDICTION Any judicial proceeding by the Purchaser against the Seller or the Seller against the Purchaser involving, directly
or indirectly, any matter in any way arising out of related to, or connected with this agreement or any other credit document shall be brought in
the courts of the State of Florida, County of Volusia, and the parties accept exclusive personal jurisdiction of these courts for the purpose of any
suit, action or proceeding. In addition, the parties knowingly, intentionally, and irrevocably waive to the fullest extent permitted by law, any
objection which they may now or later have to the laying of venue of any suit, action or proceeding arising out of relating to this agreement, or
any judgment entered by any court brought in the State of Florida. Further, both parties intentionally and irrevocably waive any claim that any
suit, action or proceeding brought in the State of Florida, County of Volusia, has been brought in an inconvenient forum.
• ATTORNEY'S FEES If Seller employs an attorney to enforce any provision of this Quotation or invoice, or to defend any action brought by
Purchaser, its agents or employees against Seller, whether the action sounds in contract, in tort or otherwise, or to collect any payment due to
Seller from Purchaser whether or not suit is instituted, Seller will be entitled to recover from Purchaser all costs and expenses incurred including
a reasonable attorney's fee.
• VENUE/JURY TRIAL/INTEREST Purchaser will pay interest on all monies due to Seller at the highest lawful contract rate. Purchaser WAIVES
ANY RIGHT TO JURY TRIAL in any action brought by or against Purchaser involving Seller regardless of whether the claim sounds in contract,
in tort or otherwise, or is in any proceeding related, ancillary or supplementary to this Application. Purchaser waives any right of venue and
agrees that any legal action or arbitration proceeding between Purchaser and Seller regardless of whether it sounds in contract, in tort or
otherwise, will be brought in a state court of competent jurisdiction located in Volusia County, Florida.
• PERSONAL GUARANTY The person signing this Quotation on behalf of the Purchaser, personally and individually, guarantees the full and
prompt performance of the Purchaser and the payment of all sums due to Seller. As used in this PO, The term "Purchaser" will also include the
guarantor and any other party to this PO and all waivers are equally applicable to those persons.
I have read and agreed to the terms and conditions of this Quotation
SIGNATURE
TITLE
DATE
P.O. Box 602 • 569 Canal Street a New Smyrna Beach • Florida • 32170
Phone: (386) 428-8875 • Fax: (386) 428-8767
www.sseteam.com M
Custom Plumbing, Inc.
P.O. Box 18822
West Palm Beach, FL 33416
Phone: (561) 533-5470
Fax: (561) 687-1175
.J�_ rZar
rJ:J� Jr:J�r
To: Hedrick Brothers Construction
2200 Centrepark West Dr.
Ste. 100
West Palm Beach, FL 33409
Project: Tequesta Rec Center Phase II
RFC No: 1 - Revised
Date: 4/12/2021 — Rev. 1-3
Description:
Added scope per Revision 2: ($5,980.36)
Women's Vestibule: (1) sink (SK-1) D23322-3 and faucet 67425
Storage 111: (1) 1/4" condensate line to (1) Drywell
Material price increases: $6,414.09
The above work is subject to the same conditions as specified in the original contract
unless otherwise stipulated.
Upon approval the sum of $12,394.45 will be added to the contract price.
Authorized Signature:
This Request $12,394.45
Custom Plumbing, Inc.
Date:
Authorized Signature: Date:
Hedrick Brothers Construction
bm
BRADFORD MITE
W A T E R H E A T E R S
April 1, 2021
Subject: May 2021 Price Increase
Dear Valued Customer:
As we proceed through a challenging time, costs for key commodities, materials, and components used to
manufacture our products continue to increase. In addition, we have experienced added cost pressure in our
logistics operations due to equipment shortages and a rapid increase in fuel costs. The resulting cost analysis
has led to our decision to institute the following price increase effective with orders received on or after May
31, 2021.
Product Category
Approximate
Price Increase
Residential Products (Gas and Electric Tank Type)
9%
Commercial Products (Gas and Electric Tank Type)
9%
Large volume Storage Tanks (Niles Steel Tank)
4%
Commercial Storage Tanks
9%
Heat Pump Products
10%
Solar Products
9%
Tankless Products (Gas and Electric)
4%
To qualify for current pricing, all orders must be received at Bradford White by May 28, 2021, with
shipments at our discretion.
To ensure a consistent flow of product and minimize the impact on lead times during the increase period, we
will be limiting orders received on or before May 28, 2021 to your normal monthly purchase volume, or as
our production capacity will allow.
Thank you for your continued support. If you have any questions please feel free to contact your Sales
Representative, your Regional Sales Manager, Director of Sales, or me.
Sincerely,
Matt Kozak
Vice President of Sales
Built to be the Best
725 Talamore Drive • Ambler, PA 19002-1873 • 215-641-9400 • www.bradfordwhite.com
A Winsupply Company
NOLAND COMPANY
8870 BELVEDERE ROAD
WEST PALM BEACH, FL 33411
PHONE (561) 795-8700
FAX (561) 795-8788
CUSTOM PLUMBING INC
PO BOX 18822
WEST PALM BEACH, FL 33416-8822
Phone (561) 533-5470
Fax (561) 667-1175
:
TEQUESTA REC CENTER
� :i�`7A �r l►a
�rSf�kypi
z ii''���' t�t t
���
A3. r.
0030256
11123120
1
Exptration Date
12123120
Revised Date
11123120
Bid Due Date
11123120
�"! �.:F`• :: 5rrar..,s.._;L'.�"ltss
AUGIE
a/kuhnanoland.com
(561) 795-8700
r iil;nrri'ei�
; "yme'nt;,Torms a Quoaed 2'0 ` _'
NET 25TH PROX 1
Salesper'so'h
0
001831
JOHN ERRICKSON JR7
S�
Unit t
-
Exteltded,
Line
Qty,.
D e s c r i p t t-o nPrice
UON
- Prtce
TEA-1
2.0
1
ST-5-C ASME EXPANSION TANK
1095.0000
EA
i 1095.00
FIXED DIAPHRAGM/PROVIDE MODEL
FOR REMOVABLE BLADDER
SUBTOTAL
1095.00
FD-1/SEE DRAIN QUOTE
RD-1/SEE DRAIN QUOTE
FCO-1/SEE DRAIN QUOTE
i
I
IECO-1/SEE DRAIN QUOTE
I
WCO/1/SEE DRAIN QUOTE
DWH-1
13.2
1
RCT06-50 50GAL/208V/6KW/3PH
3615.3000
EA
3615.30
ASME
i
SUBTOTAL
1 3615.30
ASME
DCP-1
17.0
1
98126826 MAGNA3 32-100 SS 115V
1395.0000
EA
1395.00
18.0
1
519651 3/4 BRONZE FLNGE SET
40.3800
EA
40.38
SUBTOTAL
1435.38
NOLAIV DJ
A Winsupply Company
NOLAND COMPANY
8870 BELVEDERE ROAD
WEST PALM BEACH, FL 33411
PHONE (561) 795-8700
FAX (561) 795-8788
(2uat�d �'a; CustQrrrer ._
CUSTOM PLUMBING INC
PO BOX 18822
WEST PALM BEACH, FL 33416-8822
Phone (561) 533-5470
Fax (561) 687-1175
Job Name
TEQUESTA REC CENTER
Quoted By
AUGIE
ajkuhn@noland.com
(561) 795-8700
Customer Payment Terms
Quoted To -
Salesperson
FOB
001831 NET 25TH PROX keith
JOHN ERRICKSON JR
S
Unit
Men e
Line'
Qty.
D e s c r i p t i o n
Price
UOM
Price
TEA-1
2.0
1
ST-S-C ASME EXPANSION TANK
1307.0200
EA
1307.02
FIXED DIAPHRAGM/PROVIDE MODEL
FOR REMOVABLE BLADDER
SUBTOTAL
1307.02
FD-1/SEE DRAIN QUOTE
RD-1/SEE DRAIN QUOTE
FCO-1/SEE DRAIN QUOTE
ECO-1/SEE DRAIN QUOTE
WCO/1/SEE DRAIN QUOTE
DWH-1
13.2
1
HCT06-50 SOGAL/208V/6KW/3PH
4707.7900
EA
4707.79
ASME
SUBTOTAL
4707.79
ASME
DCP-1
17.0
1
98126826 MAGNA3 32-100 SS 115V
1500.2500
EA
1500.25
18.0
1
519651 3/4 BRONZE FLNGE SET
41.3500
EA
41.35
SUBTOTAL
1541.60
March 31, 2021
To Our Valued Distributors:
As we continue to navigate these unprecedented times, A. 0. Smith remains committed to producing high quality
products at the lowest possible cost for our customers. Our priority in manufacturing and distribution has been, and will
continue to be, taking care of our customers in the most efficient and cost-effective manner possible. However, we
continue to experience significant increases in key materials, components, and freight costs. In addition, to meet our
commitment of keeping product flowing to our customers, we continue to take extraordinary measures to make sure we
have the necessary components required to match our increased demand. Component supply continues to be one of
the greatest challenges in this pandemic and has required us to spend significant dollars on airfreight from our
suppliers around the globe, as well as onboarding alternate suppliers, generally at much higher costs.
The price increases we announced on November 3, 2020 and January 19, 2021 were intended to cover these costs.
However, since we announced the increase on January 19, 2021, we have seen substantial material cost increases,
primarily in steel and other key materials. Since August 2020, steel index prices have gone up approximately 129%. In
just the last two months, the indexes have gone up approximately 20%. In addition to these steel increases, we have
seen significant increases in copper and petroleum -based components that are critical in the manufacturing of water
heaters.
Therefore, A. 0. Smith is announcing a price increase on residential and commercial product orders placed after May
31, 2021 to offset the cost increases that we have seen since our January 19, 2021 announcement.
As a result, we will implement the following price increases on orders placed after May 31, 2021:
• Residential and Commercial (standard and specialty) product at a blended rate of: 8.5%
• Gas Tankless product at a blended rate of: 3.0%
ORDER POLICY AND GUIDELINES
• New zone sheets will be distributed on or before April 26, 2021.
• Orders must be placed by May 31, 2021 for immediate shipment.
• To ensure we can meet all customer demand, orders placed between April 1, 2021 to May 31, 2021 cannot
exceed your average 2020 monthly demand or mix. You're A. 0. Smith/State/American representative agency
will provide an exact calculated order allotment for both residential and commercial tank type products for the
months of April and May.
• Orders received above the monthly allotment will be entered at the new price level and given a
delivery date based on production capacity at time of entry.
• All orders received after May 31, 2021 will be invoiced at the new price levels.
Please contact your Local Representative, Regional Sales Manager, or me with any questions.
Thank you for your patience and understanding as we try to manage our order input to our current production capacity.
Sincerely,
QJU C
Rick Hawk
Vice President Wholesale Sales
A. O. Smith Water Products Company 500 Tennessee Waltz Pkwy Ashland City, TN 37015 PH: 800.527.1953 FX: 615.792.2163 www.hotwater.com
From: Dan Hollabauoh
To: Sherri Wilson
Subject: FW: Charlotte 02-25-21 Plastic Pipe Immediate Price Increase
Date: Monday, April 12, 2021 1:12:22 PM
Attachment= 02-25-21 Plastic Pipe Pricing Increase Letter.odf
-----Forwarded by Colin E Davis/WPLM/NolandBranch/WinWholesale on 02/25/2021 01
From: Sourcing Announcements/custsvc/dst/WinWholesale
Sent by: Bruce W Pilbeam/comm/crp/WinWholesale
Date: 02/25/2021 12: 36PM
Subject: Charlotte 02-25-21 Plastic Pipe Immediate Price Increase
27PM -----
This letter represents an 18% price increase. Expect all other pipe producers to issue similar
increases and allocations. Pricing will most likely remain high and supply constrained throughout
2021. Be wary of new customers and business opportunities.
(See attached file: 02-25-21 Plastic Pipe Pricing Increase Letter, pdt)
CHARLOTTE
PIPE AND FOUNDRY COMPANY
February 25. 2021
TO: Charlotte Pipe and Foundry Customers
SLBJECT: PVC and ABS Plastic Pipe Price Increase Effective February 25, 2021
The winter storms that hit the Gulf Coast region last week have dealt a devastating blow to the
entire petrochemical industry. Numerous chemical manufacturing plants are either shut down or
operating at reduced production rates. Three of the four major PVC resin producers have
declared force majeure. and numerous minor ingredient producers have shut down or scaled back
production_ At the same time. demand for PVC resin is strong. Accordingly. all major PVC
resin and minor ingredient suppliers have increased their prices to as significantly.
ABS compound producers, for many of the same reasons as PVC producers, have also scaled
back production and some have declared force majeure. While supply has decreased, the
demand for ABS for use in automobiles. household appliances, and pipe and fittings has
sk-,Tocketed.
These circumstances. combined with weather -related delays in rail transportation of raw
materials. have put a tremendous strain on the plastic pipe and fittings supply chain. We
anticipate the availability of PVC and ABS pipe and fittings will be tight for the nest several
months.
Therefore- effective today- Thursday. Febrrary 25. 2021. we find it necessary to increase our
PVC and ABS pipe prices- Our new nine prices are net urices -we will not discount off these
new price sheets. In addition. we must limit price protection coverace on this increase.
New orders ulaced on the January 22. 2021 pipe price sheet will be limited to 1:24th (2
Reeks) of your annual pounds from Charlotte Pipe. Goin, forward, and until further
notice, we will limit incomins orders based on the February 25'h price sheet to 1i121h (one
month) of your annual pounds from Charlotte Pipe.
All of us at Charlotte Pipe are focused, as always. on taking care of our good, loyal customers.
Thank you for your patience and understanding during these unusual times_ Please contact your
Charlotte Pipe Regional Sales Manager or your local Charlotte Pipe sales rep with questions.
Thank you allowing our team to serve you.
CHARLOTTE PIPE AND FOUNDRY COMPANY
P O Box 35430 Charlotte. NC 28235 USA 7041372-5030 8001438-6091 Fax 8001553-1605
www.chariottepipe.com
This email message and any attachments is for use only by the named addressee(s) and may contain confidential,
privileged and/or proprietary information. If you have received this message in error, please immediately notify the
sender and delete and destroy the message and all copies. All unauthorized direct or indirect use or disclosure of this
message is strictly prohibited. No right to confidentiality or privilege is waived or lost by any error in transmission.
From:
Dave Weigel
To:
Sherri Wilson
Subject:
FW: Copper
Date:
Monday, April 12, 2021 1:20:34 PM
From: Dave Weigel
Sent: Tuesday, February 16, 2021 9:44 AM
To: James Savnik <james@customplumb.com>; Thomas Putnam <thomas@customplumb.com>;
Dan Hollabaugh <dan@customplumb.com>
Cc: Sherri Wilson <sherri@customplumb.com>
Subject: FW: Copper
See Below
From: < nlPnoland.com>
Sent: Tuesday, February 16, 2021 9:13 AM
Subject: Copper
Just a little note from my copper guy so keep a eye on it.
tube continues to go up. This morning we are going to tje new sheet that is 5.5%
higher on list than the 10 sheet. We had no warning other than a late email last night.
.We expect tube to continue to rise through end of July. Supply continues to fall short
of demand.
Sent from my iPhone
*********************************************************************************
************
This email message and any attachments is for use only by the named addressee(s) and may contain
confidential, privileged and/or proprietary information. If you have received this message in error,
please immediately notify the sender and delete and destroy the message and all copies. All
unauthorized direct or indirect use or disclosure of this message is strictly prohibited. No right to
confidentiality or privilege is waived or lost by any error in transmission.
*********************************************************************************
************
JOSAM
February '+ 8, 2021
Subject: Price Increase
Dear Valued Customer:
As a result of rapidly increasing prices in raw material, freight, insurance costs and the
volatility of the U.S. dollar, Josam Company is implementing a 5% list price increase
effective April 5, 2021. The 5% increase will be applied to all products included in our
2021 Josarn List Price Guide and our 2019 Stainless Steel Drain Price Sheet. The new
April-2021 LPG and 2021 Stainless Drain Price Guides will replace any previous price
guides.
All orders reflecting list prices prior to the April 5, 2021 price sheet must be entered with
Josam Company on or before April 3, 2021 and scheduled for immediate release.
Therefore, if you are bidding a project now that will not be released until after April 5,
2021, we kindly ask that you please factor the increase.
The April 2021 Josam LPG and the 2021 Stainless Steel price guides will be posted on
Josam's website under the literature tab by the end of today. A hard copy of the price
book will be mailed to you as soon as they are available and prior to April 5th.
We are currently at the mercy of a very uncertain economic environment and while we
hope to see some stability in costs, we cannot be certain of future increases which may
necessitate further adjustments. We will continue to monitor all factors and keep you
informed. We are committed to providing your company with the quality and service that
you have become accustomed to with Josam Company and we thank you for your
continued support and loyalty.
Should you have any questions please feel free to contact your local Josam Representative
or your Josam Regional Manager.
Sincerely,
44TV�471-1-
B. Scott Holloway Sr.
President/CEO
JOSAM COMPANY
ExeCLtive Office: 2501 S. Front Street * Philadelphia, PA 19148-4182 * 215-339-5370
Corporate Office: P.O. Box T * Michigan City, fN 46361-0360 * 219-872-5531
Count Days Add Days Workdays Add Workdays Weekday Week Ne
Start Date End Date
Month: Day: Year: Date: Month: Day: Year: Date:
12 / 13 / 2020 2 2 1 2021 VMS
Today Today
U Include end date in calculation (1 day is added)
Days in Results:
Exclude Public holidays (not in weekends)
,F 1nnda Ciangeountr, Change State
-,ale , Date ',JalCWatc,
From and including. Sunday, December 13, 2020
To. but not including Tuesday, February 2, 2021
Excluding Public holidays (not in weekends)
In United States - Florida Change Country / Change
grace
Result: 46 days
Add time hells
51 calendar days -
Excluded 5 holidays:
• Christmas Eve (Thursday. December 24 2020)
• Christmas Day (Fnday. December 25. 2020)
• New Year's Day (Friday January 1. 2021)
Martin Luther fling Jr. Cav (Monday. January I & 2021 t
• goDen E. Lee's 8irtnday !.Tuesday. January 19, 2021)
Rev #13 General Conditions Daily Calculation
Co-Vuc0on
Gsnsnl Condl0ons
G—I Rsq. - Flsld Of".
Gansnl Rsq.
Tofal
%Tura
Remarks
Dperlptlon
oty.0
Unit
Cost
I Court.
Cond.
Unit
Cost
Gananl
Unit
Coat
Gsnanl
Field labor - COmYud lon
360,949
ProjW E>< bve
43.0
wks
$ 420
S 18.060
S 18,060
5%
ecf Menew
43.0
wks
$ 2,520
S 108,360
S 104,360
50%
Eatima0n
1.0
is
S
S
$
AseiataM Pm'95 Man et W. 1
43.0
wka
S
S
S
A6aiataM e, Man er No. 2
0.0
wks
$
S
P eat Su 'Mendnt
43.0
wka
$ 3B00
f 163 400
100%
Aest. Su Menderd No. 1
43.0
*.
$Asst.
Su rdendent No. 2
0.0
wks
$
$
K$.
Foreman
43.0
wks
$MEP
Caanlini tar
43.0
wka
SP
eM Coordinator
43.0
wks
$ 1 040
S 720
50%
BIMMana er10
Is
$
S
AcwuMin
43.0
wka
$ 312
S 13416
f 13416
15%
Sef Su isor
43.0
wks
S 70
$ 2,993
f 2,993
3%
LU
z
W
u
u
LU
r'
N
w
D
W
i
w
.J
w
u
V)
z
O
r-
u
Z)
r-
z
O
u
0
w
W
w
m
C
N
0
0
w
w
C �
�Q
` � m
E � �
N \ N
�O N
m N � C
Of E Lu
cm
d
u m m d r2
rZ m « 9 c E c c
o O O d W DD y« d j `O
.5 0 �P LN Cj d V d p• O
T O ♦ O L L -— O d p E G N
t
N
Ol �N N Q1 N N
9 T f0 f0 N 'fl IC N Y N f0 Y f0 V
J p a a a a a 3 3 3 a 3 3 3 a a 3 N a a 3 a a 3 a
o a+ o �. .. o .-� m .+ o .-� M .•. ., o .. .� u+ 1 o N .•, o m o
O
m
E 3
N pd W_ N '0.
o . c oo A a
o w E
c
a` m (U
o E
E ow Y E a y o0
a v > E v p ar c
v E a 3
t a w Q a - cc a ¢ c a a
y C > d G! w c mt O p a m
a, m° r J 2e a 0°¢ m o E to
�n c `n o w O m m v .� .. ` :�
a+` p a W.
-0.
t �n c a c> c .E v E
`o_
c
j o v° v> °y v w o° U E v E y a' a Oc c o w
M- m j y ai a o u 'm a m a v u m o
c o c a z E¢ z°« v o a ', ?°° E E a o o o c
3 v w a a a m .> c x ,n E .E v v 'S a c z m ie `m E
u a d n w d .E .E o o" p a m a m u c«=°- Y v 'o n
u° 'a � > v u uE m
LU
oo
o E o uZ i 3 v>>w
u z l7 O m
�n 0 p W>O
a a a O
N M Q D 1� 07 T �2 �
.- N N N N N O C V Q C O O C
aci
0!
a
c a,-
L«-
cLLC �. c L
vNo._10 ; c
O Vm O 01r E
c m o o m d CC
ma c 9 r c ra>QCACN L
A Oc
ru0 o0c
tZ E d
p
LLcEm C Bp « t7 « c m
0
d O 7 01 r O C W W« C N 3 W
$ O E V H C yxj 'Z O
v m « w r p c V N\
N _ cc IVN C L C C=.- N 6 .� N O O O^ N
c EL 6 N D r c
N 3 « d d 4 Cc c m cn ° 1�
ra a E x v a? 'y Z 3 �► ►m
CY ;A75
O 2 L A} ►. ► 071 OI \ N
O A m O M O. c In
N fV \ m m M t V 19 N W ► N A n
c a rn o c Q c
O L O N
C E N z a9N ► ► °
m- y 0 H v a ► N
m10 o a
C T W W _► ► N
F u; ► ►' a
'^
r N N m m
nt \ N
O cN
g
v 0
C Z
a
L
V
ZQ T-Ni mmW Oa.., O E r W p mvO 0o1 TC
J� m 0LO UO Cm
o
.0.0 c
u° -i
3J3 U` mLL u u 7o a jm
° r �«u O Y �Y o
u w ,...o
xAC Q' C C v
C C Q N V J
>
N 0
m
.10-1 00
Lr lD N V01 l0
a N V V V1 V1 V1 t�fl Ill V1 Il1 VOi V1 10 10 mm w tDD w 10 to w 10 1� n n n n n n t0 00
H H H H
�••� N N N N H
\ H N H\\ N H \ H\ ry �••� N H N H N \ N N N M\ N N O I� R N \Nr•il \NN\ \ H H� \V1 \N C N NH \M\N HN \\VI \N HN \N\N\\I� lHND OM HN \O\- \Ill \H OHl \N \ H \N \\N
m I
10 N0\0\m\\ N\\N--H
M m m\ p CN 0 0 m 0HH \\
M M NVN
R O \ \ �D \ \ n W n \ \ Ol D1 H .-+ O O 00
y N W W y y > > N 7 c0 O N �0 w ID I� > > N oo cO a, O1 w w W w~ N N N d N w
�"� H H H H H H H rl •-� ry\\ N N N e-1 H �"�
N N H H H "� �"� ""� `••� N N N N N N H H H N N N
\ \ N N N N N �--� \ N H \ \ \ \ H �•"� N N N \ \ \ \ O 4!1 \ \ \ N ry N
aT C \ \ \ \ \ N H H \ N H lD m N N N
N N H H M "•� t0 \ m N N m\ M M H N H\ N D1 D1 tD H N\�\\\ �"� � Q1 Ol N
\ \ \ \ \ �••� H lD H \ \ H Q \ \ \ \ \ M m M \ \ \ \ O \ O O H \ \ \ \ H
N N M M M\\ N \ N CIt \\ V1 l!1 wlD N I� N n m m m 001
M M \ M \ \ C V1 \ \ m
a a c c a a s c c a c c a c c c a a a a c c c c
w m o o a, m v m � v v o o a, o o ._ ._ w o 0 o a, w wo o o � a, >> oZ
N
C m > >> T T > T > m
m > > > > > > > > m m > m > m > > T m m > > m > > > > > > > a > >
;o m a m m m m m m m m a a m a m a m" A m a a m m a m m m m m m m m m
m a N a a a a a a a a 'o a o a 3 a a- o a a 0 a a a a a m •o my a s
N m H N lD V1 m �!1 V1 I!1 N H 0 00 H m N m 00 H N N N .-1 ID -T M Ill w Il1 I!1 rl m m
.7
C
u
l7
7
w
0
u
E
m
Z
tg
r
m
3 c
o N a °°
c
"c m c n
m m
3 'm v a E 3 o a m
v1 m Q o 'Ny a c eo
a o c, u m n m 3 'o a J c m
lit m F o y LL O N o .r m
o m m a Y o c °
c m a 'o o c c c
u0 Ie U 00 N O X Y O 0 O '� Vf a O C= i0
L l7 M m m O m W O m N N m e G C V1 C m
c o o u rEo a, :3 .o° Y> a m '5
cO 0 r,j cc N ` OJ L O ° W y C m E m V
C G L G1 N ° 01 O % X 7 m U ry D_ Ol D- U J-
u L, v v y o m n W c o w t7 J o a o u z o o� V o
LL ccz LL w o ?i 'va-i in a c c c c Q in u°
.W C LL C c C Q C o O_... W
m A E C N imO
C q N OO l7 N V V M C E LL O. N C 7
m O C LL R C 7 9 W LL; ►.. N
A \
7 X m L Q C C C C C a N fr'f1 N M N
G N C y1
ro
7 C C N "' — ►- O in ► c P. el
0 n C
yC L O C .E ► ►_. \ \ \ M ►
ip L� C LL ► P P � � � P
v y m ► o
W N
N O �
C O \
M M O
A� CM 0\f
T O\i O
L > > a 3 m ~' t0 x O p0 C E N O
ar p K LL- m is G C O r O O O N u O v v
m m c c 3 3= u o o c v E v E u a E au Z a
o E a' o o E
3 u- 0 3 .E Q vi u H w y c u
o D_ « c E «« « m« «« a a n c E 6
3 a c
r 2 LL a` ,y c c c c c c c LL O Q ii
t a
0 m 0 n m
m m y m
u0i n In m en S 000
p m m oc (3i a m m V Ln l0 00
1 co 0000 m m W 0000 001 Ol m m m Oat m m m Oat ami am, 0 0 0 0 O O
O N N Ol rl m m \ t0 a er 10 ry \ Vl \ \ N \ ry \ \
00 N
Q1 Ol O N e-I '-1 N N N .y N \ \ ti \ \ \ rl N N
C O = N N O L J L O O CU j j N N N
LL 3 3 3 r r W r LL r 3 3 3
0 \ N\ \ N N N ry N
\ N N N N\ N N O
N \ � � \
N m O N 01
r, 3 �o i �333WLL�3LL3'LL"i�o v3a3 v
ia
3
E
z
0
> m m T T m > > > m coo > > > is > > > > > > > m
m a a m m-0 m m m a a m m m a m m m m m m m '� m
a H N ll'1 m �--� a s �/f rl N I� n m .-1 ID 1 10 V N � O
C
L
0
d O
0 C N
O. N `1
n c5 E a; m
C
m - eo o• �
u v
u w C
u a m & c E a m
w m e c > c m c
W c m S u C _0
5 m 0
a � a c �_
L00 U m U G m LL m G L
a r>> a 3 m r E
o° Y o o ,o a c u
m o LL c m o 00 r v c o o E
mo o m m m$ 5" 3 c o a u 0 f� u a
N c c 3 u o o E cco co 'o m W N E a a ob
m N u O a
0 u u m c LL w« v
CL a « E « « « « m « « « a aC a C>>
c
8
Y? i' i' iTiT\*it iT`r`?_Tit VON, lVvirei�t`1vW.."?
c
0
E
u0
C
it
O
a
C �
m >
o'<
o
C
` =
C
C
v u
N <
C
C f
O
V
m
m
O
e °
z
C
U'
P O
o
y
N
m
Ch
c
a'
o
q;
m
w a
c
O g
O
`
F « ad
N <m
N T ry
N
y E N
O v 41
` fN
�D ry N
N N~
N
a ip
y p V
6
m
00 N ^ N
N N tp N
r
>
.E q o
►� ► y► v
a
N
a
0 0
a c E o m a c
z= a� a a w E
d c
j v `y r
o
E '^ f m
v
n 7
N
c'0 o v c
E w v-' q m w �m
o of
E E" c E m
O
^o v a O v=
A Ti o� c = Z E m o c
>
o d a a i 9 i 'w
p<2
uoi
y 6 m° a W(zu d a u N a n a
a" o •E m a
i.
-0
o_ e m u 7 a
m E
0 cm a G :o> a d E cc
> Q l7
v+ a m
7
w
mm dDN�� N ;
> C W N
N-
c o a o S
a' i v i z
w
N C
O
C ° cm Z N O
° ` E
v �
`
O
a
a z°
.0 O
o
Cc,O O N ti .r H N
\ N fn N\ N\
e•1 p pN pN rl r1
ti
•+ o
\ e•I N ti N
'-I N
0\0 1\A \ T •-I m N O1 l° N\ '\-1 m
T N\ lD N m m
Q
\ m\
N \��\ N N
N
�••I N N\ N
N
N
ti
N ey C r' C .Ny N .-I 'ti 'y N N N N
N •-I e4 �-•I N N
�O
C N
C N
7 J p J p _ G! W N W N N J J
W Ol Ol y Gl Ol 01
7
p 01 W N y U!
p p W
2 2 f-
0 0 0 0
0 o o o
0 0 0
N N
\\ N N\ N N O1 T O I� N N N
\
e•1 .+ N N\ N N
\ N
N
0 0 0\
m m m m I� n
N\\
N N
N
'•1 -N_
'-I - rl N �..� �..� �..i •.y \
N \\ N
�••1 N �y N ry \
�"�
N N
�••I e•I ti ti e-1 �-1
\ Ol N
N
e1 e-1 C r' C rl C C �
7
N
7 O 7 o LL._ o o v N W W N v J
O O
c
m > > > > > vv11 > > >
R T A N . 'x A 'x A m 'x
3 3 3
m > > > > >
7 N Y 10 f0 N
v 3
m
9
a m > > > >
9 N
> m >
A V T
O
: 3 v 3 n c 3
,y 0 c v 0 v 3
Of O �••� .� O .y m ti O ti m .+ ti 0 .+ .-�
ry v 3 v v v
�n in O N .+ O rn 0
o
ai
m o
N Q� v+ .•� �n
o
Q .i ti
m
o �
O
3
5 y w
a
❑ c v
o oo
v
v
w E
° m c
w
C 7 v ` W
m
v
v
v❑ a 071 .E LD m
v v o• v v v ¢
W
°
E o
c v a
c
v
w C > G1 c > m
v 1° `O a ¢ A
'^ a o y o m m v a �� u
M.
O❑
W° m
Ca `ga>
m
c
m°¢¢ c o'
vo
u.a
E
E '
N 2 o
m .ovE
m
c
3 a
o a
t u
o
vv
m
a
Z4
c
w w y
C
=c
y
`m
E
I
_❑❑ Q a
N C >
c c m a** '> E N a d c a 3 01
O C
•= E u a u
y
V 0❑ O u w
m E °-
m avi y N
vci ❑ u
Y
$ o J o 0 o v o 3 7 o w
v U v, U Z vi vi ¢ u -" 0 0 O
E in v, m ¢
`m
°
� ❑
a`
a
a
O
Q m M r! m m N N ryN N N N N m
�vmi ��+1 Q Q V Q
ri
E
o r
N E
Y _R E S
:
a
C
O S
mom Cl
c ka C C
OO i 4l
C
N aN 0-0 J J H
. p S c N. O d x O N a
C e O
a
Aa'$ e 3 o a a
_ 2 m E c � e E `m
'u y m 'a o, c .m m u
o
3 m df org
° o m° `o x c
o CL
O `0 9 `m -M in
W
v = N Y « O m d
c " O N C Ry e-
` A A d C N = O r2 O W C
O' c o• iil gL
co
Ol Ol O l7 7 .3 d "L O C « « •• �^ m m
M 5 9 7 tm .� 0,a c ` a _ '« 2. C m C m GO T
r E o al c a o u d m p 3 h► N CO ■aoo
m o 9 u° c a a-^ Wx o o r
IL
i LL IL S a c o 0
c 0 m cL ClC++ N OC a Io m
O 11 LL c LL N
d '�• Q n\1 M
m N
�N
C �
A Z
a
et
o.
C a
O a'
d;
of
a_
c a
N a
dE
A�
01
C �
m Z
d
ti
N ti ti e-I
N N\ N O n Q N N t0 N 00 N\\ N N N N
IO N
•1 t0 N N N r1 N 00 \ .-I � \ � N \ N V1 .-� N 01 ey N ti DO rl
lD \ \ n \ \ T \
m T m a e 0 in Ia I° n
y y y>>> o v v 0 0 v a v>>> O1 v v
N N r1 rl ,-1 � rl rl eY eY ,-1 e4 ei e-1 \
N\\
m N N N Ill N C ri
N N rl T �•'� IO N N N N rl NM T N N \ l0 •i N\\
\\-.+- M0 m \� n\ o 0
N N T T T \ \ N N N 01 1� Ill l0 1p 1p f� l0 N T _ Ol
u N 0 0 N N Al C C 7 V1 N d w m m m O iz d N 0 0
'-�LL�LLI�LL33��LL333�I�I��LL33��
.y
N
N N \ N N N
N N T
. N \ n m w
c n v c c a0
i LL � 3 a o r
rl r-I
\ N ry N N •-I N
Q m V m m m m m m L m a m m 'O 7 m m a m m m m m m m Q m m v V m m
01 9 7 7 9 N 0 9 �i a'o O
rl T N 1p V1 00 IR Vl I-1 V1 I -I m rl 01 N M m N n Ill 1p Q T Uf m ll1 tll rl T °l I-V IA m
N
W ao
cn ; c
Q 90 N v c
a 3 a E c 3 a 1 v
t0 'N c o c v ao
L N
o-CC_ C.,m m« o c g L>>
L iil w C Lo0 O m O m O L O d O N
w C VI ~ 7 N O C 00
ink v c o o a m E o o '^
c m o c z° 0` v° t `o
m m LL g v y o z a w
d .m. m :° ~ «m. C L° w w m
W a a « c- x
c u° S w LL c LL w o 3 v v a c c v-¢ c c u
u°
m il• it `I, it i, il. V V i' i, i, i' i'' i'. iI. 1'. ,r i', V W il, iI. W' i, iI. i` W, W' y, V, iI, i'. k it iv it w W
m m o N m r N o N
Iu I° n m rn o a In m m o e
m m m m m
�...- _ _ ._-. ..... ............
1
V V)
N
O
•-d u
C z
s w
X
a
W
n ~
C
mH d
� E d C
a < E •gym
c rn 5 e E m c
c = c a
A r :'m da c c ° ,Zl
a' i u u ce c 1°
v
Q rn N c ai ,5 c N a a` a c o >
5 m o o x e 3
` g - a LLv m tiui A3 qU O m m v O Ed ewa= c O Go
0 a
Y E
.E mVc fOe
U c(7 in V U �qq LL H iu m a O
N 253 LL° c
Y D
Y a'9 G c 0 " ► ► N N
oQ C
oC � N
N E _ N N
oc d N Ir
c c� C,� hN�► rn
C m V N C 0 0 O
O Q O O\1 \ N m O1 01
m
C
ai
c S
"v
C �
cyq
r�
I Z.
c a
oQ
m
"c S
cr E
a
e �
m a
OLL
C �
i0 0
O Z
ey •-I .I N��\ N O N\ O N N N T T
I� \ � 7 \ N \ O � •-I rl � N
'1 'i •-1 N N N N N N N �"� N
\ 00 N N N \ \ N \ \ N \ \ N
O
N Ol °1 01 C C C c v 'O '° C V C w C C a
_ d d o 0 o d d ._ o d o d J J o o d o
N � 10 A IO � V 10 10 N m IV 10 t0 (0 10 f0
O .I V O VI rl N 1� n T l0 I� �O Vl N N m O
u
a v �
m S E E m
c o. 3 c
cr
U w c w 2 �
v a E E m
c c S 10 l7 A c
u �
u 3 u=
°
3
3— u Jo 0 A v N 0 a
o E c E ar' A df
> N o> m o° J E o c
Qa: l7 _ U u m E a E W y a o
o
y U
c
O �
o
HEDRICK
BROTHER
CQN$TRVCTIQN
Hedrick Brothers Construction Co.. Inc.
2200 Centrepark West Drive. Suite 100
West Palm Beach. Florida 33409
Phone: (561) 689-8880
PCCO #005
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #005: Plumbing Changes per Code
TO: VILLAGE OF TEQUESTA
FROM: HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA, Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 5/21/2021
CREATED BY: Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved
REVISION: 0
DESIGNATED REVIEWER:
DUE DATE:
INVOICED DATE:
SCHEDULE IMPACT:
CONTRACT FOR:
06/3012021
20-399-01:VILLAGE OF TEQUESTA COMM
CTR
DESCRIPTION:
CE #011 - Plumbing Revisions/Code Compliance
1. Storm Water
(3) 6" WCO
2. Mech/Elec
(1) 3" Fd -1 w/trap primer. Josam
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
REVIEWED BY:
REVIEW DATE: 05/21/2021
PAID DATE:
EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $4,794.07
PCO #
Title
Schedule Impact
Amount
2000-004
1 Plumbing Changes for Code Compliance
$4,794.07
Total:
$4.794.07
CHANGE ORDER LINE ITEMS:
PCO # 2000-004: Plumbina Chanaes for Code Compliance
#
Budget Code
Description
Amount
1
2005.15-15-410.SUB PCCO #5 Rev 4 Plumbing
Changes. PLUM BING.Subcontractor
Plumbing Changes for Code Compliance
$4,386.16
Subtotal:
$4,386.16
General Liability (1.30% Applies to all line item types.):
$57.02
Contractor's Fee (6.50% Applies to all line item types.):
$285.10
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$65.79
Grand Total:
$4,794.07
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 5/21/2021 11:33 AM
HEDRI K
■ BROTHERS
CON$TRUrTIQN
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach. 33401
` 06/23 2 r
SIGNATURE DATE
Cauo Poke /^vice For poi T
PRINT NAME AND TITLE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
/031
GNATURE DATE
lei, Lllb ., NI-ft. - v,1k�
PRINT NAME AND TITLE
PCCO #005
$6.013, 394.00
($241,656.32)
$5.771.737.68
$4,794.07
$5,776.531.75
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
6-25-2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co.. Inc. Page 2 of 2 Printed On: 5/21/2021 11:33 AM
HEDRICK
■
BROTHERS
PCCO #006
M 0
.. CQN$TRLJCTIQN
Hedrick Brothers Construction Co.. Inc.
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
2200 Centrepark West Drive. Suite 100
399 Seabrook Road
West Palm Beach. Florida 33409
Tequesta , Florida 33469
Phone: (561) 689-8880
Prime Contract Change Order #006: Truss Modifications
TO: VILLAGE OF TEQUESTA
FROM: HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA. Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021
CREATED BY: Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved
REVISION: 0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS
REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE: REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021 PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: $13,647.20
CTR
DESCRIPTION:
CE #014 - Truss Modification for Pitch Break
Truss Modification for Pitch Break
ATTACHMENTS:
PCO#2000-006 Executed.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
I Title
I Schedule Impact
Amount
2000-006
1 Truss Modification for Pitch Break
12 days
$13,647.20
Total:
$13,647.20
CHANGE ORDER LINE ITEMS:
PCO # 2000-006- Truss Mndifiratinn fnr Pitch RraAk
#
Budget Code
Description
Amount
1
2006.15-03-309.SUB PCCO#006 TRUSS
MODIFICATION.SHELL. Subcontractor
Truss Modification for Pitch Break
$12.486.00
Subtotal:
$12,486.00
General Liability (1.30% Applies to all line item types.):
$162.32
Contractor's Fee (6.50% Applies to all line item types.):
$811.59
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$187.29
Grand Total:
$13,647.20
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 6/23/2021 09:25 AM
■HEDRICK
■ ■ ■
BROTHERS
PCCO #006
0
CQ N$T1t1jrTIQN
The original (Contract Sum)
$6.013,394.00
Net change by previously authorized Change Orders
($270,233.03)
The contract sum prior to this Change Order was
$5.743,160.97
The contract sum will be increased by this Change Order in the amount of
$13,647.20
The new contract sum including this Change Order will be
$5.756.808.17
The contract time will not be changed by this Change Order
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste, 210
West Palm Beach. 33401
G6/23
SIGNATURE DATE
(&./v7 / l91ce ,, vice &-r(~ f
PRINT NAME ANd TITLE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
la
7NATURE DATE
04t"'. kkll�'
PRINT NAMIL AND TITLE
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
/<-ac 6-25-2021
SIGNATURE
DATE
Robin. Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co.. Inc. Page 2 of 2 Printed On 6/23/2021 09:25 AM
HEDRICK
PCCO #007
BROTHERS
M X _.
rQN$TRV(:TIQN
Hedrick Brothers Construction Co.. Inc.
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
2200 Centrepark West Drive. Suite 100
399 Seabrook Road
West Palm Beach. Florida 33409
Tequesta , Florida 33469
Phone (561)689-8880
Prime Contract Change Order #007: Electrical Owner Requests
TO: VILLAGE OF TEQUESTA
FROM:
HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA, Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
DATE CREATED: 6/23/2021
CREATED BY:
Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved
REVISION:
0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS
REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE:
REVIEW DATE:
06/23/2021
INVOICED DATE: 06/30/2021
PAID DATE:
SCHEDULE IMPACT.
EXECUTED:
No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM
TOTAL AMOUNT:
$6,293.49
CTR
DESCRIPTION:
CE #015 - Electrical Owner Requests
-Cable Retractors to Car Chargers
- Additional 2" Conduit with pull string from data room to car charger location for future use.
ATTACHMENTS:
PCO #2000-007 Executed.odf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
Title
Schedule Impact
Amount
2000-007
1 Electrical Owner Requests
$6,293.49
Total:
$6,293.49
CHANGE ORDER LINE ITEMS:
PCO # 2000-007: Electrical Owner Reauests
#
Budget Code
Description
Amount
1
2007.15-16-110.SUB PCCO #007 ELECTRICAL
OWNER REQ. ELECTRICAL. Subcontractor
Cable Retractors to Car Chargers
$3,300.00
2
2007.15-16-110.SUB PCCO #007 ELECTRICAL
OWNER REQ. ELECTRICAL. Subcontractor
Additional 2" Conduit with pull string from data room to car charger
location for future use.
$2.458.00
Subtotal:
$5,758.00
General Liability (1.30% Applies to all line item types.)
$74.85
Contractor's Fee (6.50% Applies to all line item types.):
$374.27
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$86.37
Grand Total:
$6,293.49
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 6/23/2021 09:32 AM
HEDRICK
■ BROTHERS
2 01CONSTRUCTION
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
West Palm Beach. 33401 TEQUESTA, Florida 33469
/'�" k
-71 f
SIGNATURE DATE ]SIC -NATURE DATE
Cacwt r�2�c�/Nce ylZ�,p tf U—co , J MV, - V k' �4t Vv -w
PRINT NAME AN6 TITLE PRINT NAME AND TITLE
PCCO #007
$6.013, 394.00
($256.585.83)
$5.756,808.17
$6.293.49
$5,763.101.66
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
/<'ac 6-25-2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 6l23/2021 09:32 AM
HR1CK
BROTHERS
0 CQN$TP.VCTIQN
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive. Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #008
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta . Florida 33469
Prime Contract Change Order #008: Relief Damper
TO: VILLAGE OF TEQUESTA FROM: HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE INC
TEQUESTA, Florida 33469 2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021 CREATED BY: Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved REVISION: 0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE: REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021 PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: $2,598.07
CTR
DESCRIPTION:
CE #016 - RFI #41 Relief Damper
Ruskin Wall Louver with Barometric Relief Damper. material and labor per RFI #41.
ATTACHMENTS:
P_ CO#2000-008 Executed.pddf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
Title
Schedule Impact
Amount
2000-008 1
RFI#41 Relief Damper
$2,598.07
Total:
$2,598.07
CHANGE ORDER LINE ITEMS:
PCO # 2000-009- RFI#d1 Raliaf DamnPr
#
Budget Code
Description
Amount
1
2008.15-15-710.SUB PCCO#8 RELIEF
DAM PER. HVAC.Subcontractor
Ruskin Wall Louver with Barometric Relief Damper. material and labor
per RFI #41
$2 377.00
Subtotal:
$2,377.00
General Liability (1.30% Applies to all line item types.):
$30.90
Contractor's Fee (6.50% Applies to all line item types.):
$154.51
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$35.66
Grand Total:
$2,598.07
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 6/23/2021 09:30 AM
HEDRICK
■ ■ BROTHERS
0 CQN$TRI,ICTIQRI
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
West Pal each. 33401 TEQUESTA. Florida 33469
Q6/?S/2/ I
SIGNATURE DATE CUR.E DATE
PRINT NAME AND T TLE PRINT NAM9 AND TITLE
PCCO #008
$6,013, 394.00
($250.292.34)
$5.763.101.66
$2,598.07
$5.765,699.73
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
I<J:�Ic 6-25-2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co.. Inc. Page 2 of 2 Printed On: 6/23/2021 09:30 AM
■ ■ BROTHERS
N . GQN$TR41C;TIQN
Hedrick Brothers Construction Co.. Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #009
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #009:
Sink/Shroud Change
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA, Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021 CREATED BY: Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved REVISION:
0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS REVIEWED
BY:
CONSTRUCTION CO., INC)
DUE DATE: REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021 PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: ($634.44)
CTR
DESCRIPTION:
CE #017 - Sink/Shroud Change
Credit: (6) K-5027-1 Lav and K-5031 Shroud (-$2815.00)
ADD: (6) AS0059.020EC.020 Lav and 9134.001 EC.020 Shroud ($2175.56)
ATTACHMENTS:
PCO#2000-009 Executed.odf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
Title
Schedule Impact
Amount
2000-009
1 CE #017 - Sink/Shroud Change
($634.44)
Total:
($634.44)
CHANGE ORDER LINE ITEMS:
PCO # 2000-009: CE #017 - Sink/Shroud Chance
#
Budget Code
Description
Amount
1
2009.15-15-410.SUB PCCO#009 Sink/Shroud
Change. PLUM BI NG.Subcontractor
Sink/Shroud change credit
$(634.44)
Subtotal:
$(634.44)
General Liability (0.00% Applies to all line item types.):
$0.00
Contractor's Fee (0.00% Applies to all line item types.):
$0.00
Subcontractor Default Insurance (0.00% Applies to all line item types.):
$0.00
Grand Total:
$(634.44)
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On 6/23/2021 09:33 AM
■ HEDRICK
M ■ ■
BROTHERS
PCCO #009
N CONSTRUCTION
The original (Contract Sum)
$6.013,394.00
Net change by previously authorized Change Orders
($247.694.27)
The contract sum prior to this Change Order was
$5.765,699.73
The contract sum will be decreased by this Change Order in the amount of
($634.44)
The new contract sum including this Change Order will be
$5.765,065.29
The contract time will not be changed by this Change Order
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach. 33401
J"I
W3 t2l,
SIGNATURE DATE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
64nPRic,F / Vlcetj2ja 1��-L,
PRINT NAME AND tITLE PRINT
TURE
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
/<,ac 6-25-2021
DATE SIGNATURE
DATE
_Vj\\ram f^9-w .V Robin Lunsford, Sr. Project Executive
AND TITLE PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 6/23/2021 09:33 AM
■ HEDRICK
■ ■ BROTHERS
CQNSTRVC;TIQAI
Hedrick Brothers Construction Co.. Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #010
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #010: Additional
Fencing at Seabrook
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA. Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021 CREATED BY:
Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved REVISION:
0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE:
REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021
PAID DATE:
SCHEDULE IMPACT:
EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM
TOTAL AMOUNT: $3,998.19
CTR
DESCRIPTION:
CE #018 -Added Fencing to Seabrook Road
South Building- Extension to Seabrook Road- 6' high PVC Privacy Fence
ATTACHMENTS:
PCO#2000-010 Executed.odf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
I Title
Schedule Impact
Amount
2000-010
1 Additional Fencing to Seabrook Road
$3,998.19
Total:
$3.998.19
CHANGE ORDER LINE ITEMS:
PCO # 2000-010- Addifinnal Fencinn to Saahrnnk Pnad
#
Budget Code
Description
Amount
1
2010.15-02-870.SUB PCCO#010 FENCE
EXTENSION.SITE FURNISHINGS.Subcontractor
South Building- Extension to Searook Road- 6' high PVC Privacy
Fence
$3,658.00
Subtotal:
$3,658.00
General Liability (1.30% Applies to all line item types.):
$47.55
Contractor's Fee (6.50% Applies to all line item types.):
$237.77
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$54.87
Grand Total:
$3,998.19
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 6/23/2021 09:37 AM
■ ■ HEDRICK
■ ■ ■
BROTHEM
PCCO #010
M
CONSTRUCTION
The original (Contract Sum)
$6.013,394.00
Net change by previously authorized Change Orders
($248,328.71)
The contract sum prior to this Change Order was
$5.765,065.29
The contract sum will be increased by this Change Order in the amount of
$3,998.19
The new contract sum including this Change Order will be
$5.769,063.48
The contract time will not be changed by this Change Order
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach. 33401
SIGNATURE DATE
40" R&ce / ✓rce I *1P&'4 T-
PRINT NAME AND TITLE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA. Florida 33469
Z
I NATURE DATE
:9 104 -y Ay'V- W-.. 6&
PRINT NA E AND TITLE
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
/<'ac 6-25-2021
'. CJJ'Iti9d;I
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 6/23/2021 09:37 AM
■ HEDRICK
■ ■ BROTHERS
0 0 _ CON$TRLJ(;T10N
Hedrick Brothers Construction Co.. Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #011
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #011: Add 1
panel to Op. Partition
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA. Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021 CREATED BY:
Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved REVISION:
0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE: REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021 PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: $1.256.95
CTR
DESCRIPTION:
CE #019 -Add 1 Panel to Modernfold Operable Partition
Add 1 Panel to Modernfold Operable Partition per the approved shop drawings
ATTACHMENTS:
PCO#2000-011 Executed.gdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
I Title
Schedule Impact
Amount
2000-011
1 Add 1 Panel to Operable Partition
$1.256.95
Total:
$1,256.95
CHANGE ORDER LINE ITEMS:
PCO # 2000-011: Add 1 Panel to Ooerahle Partition
#
Budget Code
Description
Amount
1
2011.15-10-650.SUB PCCO#011 ADD 1 PANEL TO
OP PAR.OPERABLE PARTITIONS. Subcontractor
Add 1 Panel to Moderfold Operable Partition per the approved shop
drawings
$1,150.00
Subtotal:
$1,150.00
General Liability (1.30% Applies to all line item types.):
$14.95
Contractor's Fee (6.50% Applies to all line item types.)
$74.75
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$17.25
Grand Total:
$1,256.95
Hedrick Brothers Construction Co.. Inc. Page 1 of 2 Printed On: 6/23/2021 09A1 AM
HEDR1CK
BROTHERS
2 E r,QN$TP.VCTIQN
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach, 33401
05 /23
-4&1 a SIGNATURE DATE
aN01 Mee / Vice 19QgJ1P4Jr-
PRINT NAME AND TITLE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
LATURE DATE
Ate -V, k-w w-,-„u
PRINT NAME AND TITLE
PCCO #011
$6,013,394.00
($244,330.52)
$5.769,063.48
$1.256.95
$5.770.320.43
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
SIGNATURE
6-25-2021
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co.. Inc. Page 2 of 2 Printed On: 6/23/2021 09:41 AM
■ HEDRICK
■ ■ ■ BROTHERS
0 N .. CQN$TRUCTIQN
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #012
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #012: Lumber Cost Escalation
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE
INC
TEQUESTA, Florida 33469
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
DATE CREATED: 6/23/2021 CREATED BY:
Kim Blair (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Approved REVISION:
0
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS REVIEWED BY:
CONSTRUCTION CO., INC)
DUE DATE: REVIEW DATE: 06/23/2021
INVOICED DATE: 06/30/2021 PAID DATE:
SCHEDULE IMPACT: EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: $15,298.34
CTR
DESCRIPTION:
CE #020 - Lumber Cost Escalation
Lumber Cost Escalation
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO #
I Title
Schedule Impact
Amount
2000-012
1 Lumber Cost Escalation
$15,298.34
Total:
$15,298.34
CHANGE ORDER LINE ITEMS:
PCO # 2000-012: Lumber Cost Escalation
#
Budget Code
Description
Amount
1
2012.15-03-309.SUB PCCO#012 LUMBER COST
I NCR EASE. SHELL. Subcontractor
Lumber Cost Escalation
$13,996.65
Subtotal:
$13,996.65
General Liability (1.30% Applies to all line item types.)
$181.96
Contractor's Fee (6.50% Applies to all line item types.):
$909.78
Subcontractor Default Insurance (1.50% Applies to all line item types.).
$209.95
Grand Total:
$15,298.34
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be increased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
$6.013.394.00
($243.073.57)
$5.770,320.43
$15,298.34
$5.785,618.77
Hedrick Brothers Construction Co- Inc. Page 1 of 2 Printed On: 6/23/2021 09:40 AM
■ HEDRICK
■ ■ BROTHERS
0 N _ CQNSTRUCTIQW
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
West Pa Beach. 33401 TEQUESTA, Florida 33469
� a
wo / - L 1
SIGNATURE DATE SI ATURE DATE
01
PRINT NAME AND TITLE PRINT NAM A WD TITLE
PCCO #012
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH. Florida 33409
6-25-2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 6/23/2021 09:40 AM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-013
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-013: Correction to remove
mark-up on Price Escalation Items from PCO#2000-005
TO: VILLAGE OF TEQUESTA FROM: HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE 2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469 WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION: 2000-013 / 0
CONTRACT:
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
REQUEST RECEIVED FROM:
CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
STATUS: Pending - In Review
CREATED DATE:
6/15 /2021
REFERENCE:
PRIME CONTRACT
None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION:
ACCOUNTING
Amount Based
METHOD:
SCHEDULE IMPACT:
PAID IN FULL:
No
TOTAL AMOUNT:
($1,418.34)
POTENTIAL CHANGE ORDER TITLE: Correction to remove mark-up on Price Escalation Items from PCO#2000-005
CHANGE REASON: Other
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #027 - Remove GL. Fee and SDI from Escalation Items on PCO #5
PCO #5 had GL, Fee and SDI charged on all items totaling $147,036.92
This Change Order serves to remove GL, Fee and SDI on the Price Escalation items.
The escalation items on PCO #5 were: Farmer & Irwin Steel Cost Escalation $5,100.00
Atlantic Interiors Material Escalation $3,737.00
Custom Plumbing Material Escalation $6,414.09
TOTAL PRICE ESCALATION $15,251.09
This change order will deduct the following:
GL: $15,251.09 * 1.30% = $198.26
Fee: $15,251.09 * 6.50% = $991.32
SDI: $15,251.09 * 1.50% = $228.76
ATTACHMENTS:
Summary showing Fee only applied to non -escalation items.pdf
#
SubJob
Cost Code
Description
Type
Amount
1
PCCO #4 Rev. 3 Changes
15-18-105 - GENERAL LIABILITY
INSURANCE
Adjust to remove fee on Price -Escalation Items
Materials
($198.26)
2
PCCO #4 Rev. 3 Changes
15-18-110 - CONTRACTOR'S FEE
Adjust to remove fee on Price -Escalation Items
Overhead
($991,32)
3
PCCO #4 Rev. 3 Changes
15-18-107 - SUBCONTRACTOR
DEFAULT INS
Adjust to remove fee on Price -Escalation Items
Materials
($228.76)
Subtotal:
($1,418.34)
General Liability: 0.00 % Applies to all line item types.
$ 0.00
Contractor's Fee: 0.00 % Applies to all line item types.
$ 0.00
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 6/15/ 2021 03 :11 PM
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Signature Date
PCO #2000-013
Subcontractor Default Insurance: 0.00 % Applies to all line item types. $ 0.00
Grand Total: ($1,418.34)
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
� eU'A'-- �1619\
Sign ture Date
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-014R
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-014R: Ductwork Price
Escalation
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469
WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION: 2000-014R / 0 CONTRACT:
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
REQUEST RECEIVED FROM: Joe Joyce (MECHANICOOL, INC) CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
STATUS: Pending - In Review CREATED DATE:
6/23 /2021
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING Amount Based
METHOD:
SCHEDULE IMPACT: PAID IN FULL: No
TOTAL AMOUNT: $22,928.00
POTENTIAL CHANGE ORDER TITLE: Ductwork Price Escalation
CHANGE REASON: Other
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #028 - Ductwork Cost Escalations
Ductwork Cost Escalations
No GL, SDI or Contractor Fee to be charged on Price Escalation"
This Revision to PCO 2000-0014 now includes a negotiated reduction given by subcontractor in the amount of $10,000.00
ATTACHMENTS:
Back-up documentation- Revised 7.1.2021.pdf
#
SubJob
Cost Code
Description
Type
Amount
1
PCCO#013 Duct Price Escalation
15-15-710 - HVAC
Ductwork Cost Escalations
Subcontractor
$ 32.928.00
2
PCCO#013 Duct Price Escalation
15-15-710 - HVAC
Negotiated reduction from Subcontractor
Subcontractor
($10.000.00)
Subtotal:
$22,928.00
General Liability: 0.00 % Applies to all line Item types.
$ 0.00
Contractor's Fee: 0.00 % Applies to all line item types.
$ 0.00
Subcontractor Default Insurance: 0.00 % Applies to all line Item types.
$ 0.00
Grand Total:
$22,928.00
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 7/l/ 2021 10 :12 AM
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
PCO #2000-014R
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
Signature Date
S_a
g ature Date
lWechanicool, Inc.
Change Order Request
Hedrick Brothers Construction
2200 Centerpark West Drive
West Palm Beach, FL 33409
RE: Tequesta Rec Center
June 21, 2021
Revised
7.1.21-DG
Provide all labor, materials, tools, equipment, supervision, and rigging to install a complete and operational
system as designed, which includes:
ADD:
Ductwork Cost Escalations................................................................$ 32,928.00
TOTAL LUMP CHANGE ORDER PRICE ................................... $-3Z;926 0&
Negotiated to
Exclusions: Quick Ship Options $22,928.00- DG
Overtime and Premium Time Working Hours
Note: Change Order Request may be withdrawn by Mechanicool, Inc. if not accepted within 30 days.
This proposal is submitted by:
This document has been signed by Joseph M. Joyce
Joseph M. Joyce
President
�d 2436 North Federal Highway #348 Insured
Lighthouse Point, Florida 33064
Toll Free. 1.800.868.3134
t. (954) 913.6172 f. (954) 570.8763
Email: Lm@mechanicoolfl.com
LICENSE # CAC033553
LICENSE # CAC1819122
EPA universal Certification # P185473BD2D228481
MFH Sheet Metal Fabricators, Corp.
2400 NW 1501h St., Opa Locka, FL 33054 - Phone: (305) 685-1874 - Fax: (305) 749-7092
Re: Village of Tequesta - Community Center at Constitution Park —Tequesta, FL
Project
To: Mechanicool
Date: 12/03/20
Estimate:
Attn: Joe Joyce
Page: 1 of 1
27451
Project Scope
1. The specifications for this project areas requested by customer and do NOT follow all specifications on plans
2. Fabricate ductwork as per customer's print M101, dated 11/13/20
3. Round ductwork construction standards to follow SMACNA 4" W.G.
- exposed round supply duct for RTU-3 and RTU-4 to be galvanized double wall with a solid inner wall
> liner to be 1" thick and 1% lb density Owens Corning fiberglass liner
> spiral taps to be installed at the shop
> seams to be clinch lock and gore lock
> joint connections to be slip -in couplings
4. Rectangular ductwork construction standards to follow SMACNA 2" W.G.
- exposed rectangular supply duct for RTU-3 and RTU-4 to be galvanized double wall with a solid inner wall
> liner to be 1" thick and 1% lb density Owens Corning fiberglass liner
- rectangular general exhaust duct for EF-1 and EF-2 to be galvanized bare metal
- joint connections and all straight duct seams to be Pittsburgh and fitting seams to follow SMACNA
5. Material to be prime galvanized G-90
6. Straight duct and fittings assembled
7. 1" x 22 gauge hanger straps
8. Connection materials included
9. Flexible connections between duct and vibrating equipment included
10. Delivery included
Exclusions
1. Taxes
2. Diffusers, grilles, grille cans, return boots and linear diffuser plenums
3. All other round ductwork
4. All other rectangular ductwork
5. Ductsox
6. Roof ductwork
Total...........................................................................................................................................: $ 31,768.00
Alternates
1. Exposed round and rectangular duct material to be paint grip ........................................................ ADD.: $1,042.00
Submitted by:
( by email )
Warley Sousa
Authorization to proceed:
Signature:
Date PO#
Estimates are valid for 30 days and are based strictly on information provided by customer. Every effort is taken to ensure correct content and
calculations, however the accuracy of each estimate depends directly on accuracy of plans and information provided by customer. When required
information and specifications are not provided by plans or customer, estimates are based solely on our interpretation and may not reflect the actual
project. Estimate prices are provided free of charge and are based on availability and pricing at time of issue.
MFH Sheet Metal Fabricators, Corp.
2400 NW 15011 St., Opa Locka, FL 33054 - Phone: (305) 685-1874 - Fax: (305) 749-7092
Re: Village of Tequesta -Community Center at Constitution Park—Tequesta, FL Estimator: quote...: 27451 Rev4
To: Mechanicool Warley Sousa —
Attn: Joe Joyce Valid for: 5 daVS* Date......: 06/11/21
Project Scope
1. The specifications for this project are as requested by customer and do NOT follow all specifications on plans
2. Fabricate ductwork as per customer's print SM1.1, dated 06/10/21
3. Round ductwork construction standards to follow SMACNA 4" W.G.
- exposed round air transfer and supply duct for RTU-3 and RTU-4 to be galvanized double wall with a solid inner wall
> liner to be 1" thick and 1%: lb density
> spiral taps to be installed at the shop
> seams to be clinch lock and gore lock and joint connections to be slip -in couplings
4. Rectangular ductwork construction standards to follow SMACNA 2" W.G.
- exposed rectangular supply duct for RTU-3 and RTU-4 to be galvanized double wall with a solid inner wall
> liner to be 1" thick and 1%Z Ib density
- rectangular general exhaust duct for EF-1 and EF-2 to be galvanized bare metal
- joint connections and all straight duct seams to be Pittsburgh and fitting seams to follow SMACNA
5. Material to be prime galvanized G-90
6. Straight duct and fittings assembled
7. 1" x 22 gauge hanger straps and connection materials included
8. Flexible connections between duct and vibrating equipment included
9. Delivery included
Exclusions
1. Taxes, equipment, diffusers, grille cans, linear diffuser plenums, return boots and round snap lock ductwork
2. All other round ductwork and Ductsox
3. Accu-Flanges, 0-rings, and flange gaskets for joint connections
4. All other rectangular ductwork
5. Ductwork for RTU-1 and RTU-2
6. Roof ductwork
Our Price (*subject to material availability)......................................................................................................................: $ 62,542.00
Alternates
1. Ductwork to be cleaned with alcohol and have open ends covered with plastic..................................................................... ADD.: $1,910.00
Authorization
Signature: Date: PO:
Estimates are based strictly on documents and information provided by customer. Every effort is taken to ensure correct content and calculations; however, its accuracy depends on
accuracy of the documentation provided. When required information and specifications are not provided by plans or customer, estimates are based solely on our interpretation and
may not reflect the actual project specifications. Estimate prices are provided free of charge and are based on availability and pricing at time of issue.
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-016
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-016: Milling and Overlay @
Dover Road
TO
PCO NUMBER/REVISION
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA Florida, 33469
2000-016 / 0
REQUEST RECEIVED FROM: Robert Biskupiak, Jr. (BCM
CONSTRUCTION, INC.)
STATUS: Pending - In Review
REFERENCE: BCM Construction Proposal date 6-24-21
FIELD CHANGE: No
LOCATION:
SCHEDULEIMPACT:
POTENTIAL CHANGE ORDER TITLE: Milling and Overlay @ Dover Road
CHANGE REASON: Other
FROM:
HEDRICK BROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE 100
WEST PALM BEACH Florida, 33409
CONTRACT:
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
CREATED DATE:
6/28 /2021
PRIME CONTRACT None
CHANGE ORDER:
ACCOUNTING Amount Based
METHOD:
PAID IN FULL: No
TOTAL AMOUNT. $22,771.56
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #031 - Milling and Overlay (a) Dover Road
Milling and overlay of existing roadway asphalt at Dover Road
ATTACHMENTS:
Teouesta Community Center ( Dover Road Changes Asphalt Paving ).pdf
#
I SubJob
Cost Code
Description
Type
Amount
1
1 PCCO#15 MILLING AND OVERLAY
15-02-010 - SITEWORK
Milling and overlay of existing roadway asphalt at Dover Road
Subcontractor
$ 20,834.00
Subtotal:
$20,834.00
General Liability: 1.30 % Applies to all line item types.
$ 270.84
Contractor's Fee: 6.50 h Applies to all line item types.
$ 1,354.21
Subcontractor Default Insurance: 1.50 % Applies to all line item types.
$ 312.51
Grand Total:
$22,771.56
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
Signature Date
�\
Si Mre Date
BCM CONSTRUCTION, INC.
868 Whippoorwill Trail
fl West Palm Beach, FL 33411
PROPOSAL / CHANGE ORDER
PAGE 1
Office.-561-793-7543
Fax: 561-790-6996
PROPOSAL SUBMITTED TO
TEQUESTA COMMUNITY CENTER
DATE
HEDRICK BROTHERS CONSTRUCTION
6/24/2021
STREET
2200 CENTREPARK WEST DRIVE
339 SEABROOK ROAD TEQUESTA, FL
CITY
WEST PALM BEACH, FL 33409
Project # 20-399-01
ATT: Doug Gordon
280 OF OF MILLING AND OVERLAY OF EXISTING ROADWAY ASPHALT
DOVER STREET CHANGES
1) Supply equipment & manpower to mill road 280' x 24' 1" to 3" deep of milling
$7,800.00
2) Cleaning of road and haul out of millings
$2,830.00
3) Prep and tack for overlay
$3,024.00
4) Paving 1" to 1.5" of asphalt overlay SIP 9.5 280' X 24'
$8,430.00
5) Credit for patching final lift 890 s/f 1" CREDIT
-$1,250.00
MILL AND OVERLAY TOTAL
$20,834.00
No striping and no signs
All material is guaranteed to be as specified. All work to be completed in a AUTHORIZED SIGNATURE
workmanlike manner according to standard practices. Price above is only an estimate ROBERT L. BISKUPIAK, JR.
of foreseen conditions. Unforeseen conditions can affect the amount of time to
complete the work, therefore increasing or decreasing estimate. All agreements are
contingent upon strikes, accidents or delays beyond our control. Owner is to carry file,
tornado and other necessary insurance. Our workers are fully covered by Workman's This proposal subject to acceptance
within thirty (30) days
Compensation Insurance. and is void thereafter at the option of the undersigned.
ACCEPTANCE OF PROPOSAL — The above prices,
specifications and conditions are satisfactory and hereby Signature
accepted. You are authorized to do the work as specified.
Payment will be made as outlined above. Signature
DATE OF ACCEPTANCE
■ ■ HEDRICK
■ ■ ■ BROTHERS
CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-017
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-017:
Correction for incorrect
Tax Saving Amount given on PCCO #003
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469
WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION: 2000-017 / 0 CONTRACT:
20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
REQUEST RECEIVED FROM: CREATED BY:
Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
STATUS: Pending - In Review CREATED DATE:
6/28 /2021
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING Amount Based
METHOD:
SCHEDULE IMPACT: PAID IN FULL: No
TOTAL AMOUNT: $1,758.42
POTENTIAL CHANGE ORDER TITLE: Correction for incorrect Tax Saving Amount given on PCCO #003
CHANGE REASON: No Change Reason
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #032 - Correction for PCCO #3 Incorrect Tax Savino Credit Amount
PCCO #3 Errantly gave too much credit for tax savings. This Change Order corrects the error.
Owner Direct Purchase of A/V Equipment (The Experts) $124,431.97.
Tax Savings $7465.92
Tax savings included in GMP Budget = $-38,847.00
Tax savings to date (PCCO #1) - $33,139.50
Balance $5707.50
Tax Savings This PCCO #3 $7465.92
Less Balance of Tax Savings Remaining in GMP-$5707.50
Tax Savings difference to be realized on this PCO $1758.42
PCCO #3 should have been for a total of (-$124,431.97)
+(-7465.97)
+5707.50
(-$126,190.44)
instead it was for a total of (-$127,948.86)
$127,948.86
-$126190.44
$1758.42
Too much credit was given in the amount of $1758.42
Therefore, this change order is for that amount.
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 6/28/ 2021 02 :18 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
ATTACHMENTS:
PCCO#003 Executed.pdf PCCO#003 Executed.adf
PCO #2000-017
#
Sub.lob
Cost Code
Description
Type
Amount
1
PCCO#16 Math Error Correction
15-18-150 - SALES TAX RECOVERY
PCCO #3 Errantly gave too much credit for tax savings. This
Change Order corrects the error.
Subcontractor
$ 1,758.42
Subtotal:
$1,758.42
General Liability: 0.00 % Applies to all line item types.
$ 0.00
Contractor's Fee: 0.00 % Applies to all line item types.
$ 0.00
Subcontractor Default Insurance: 0.00% Applies to all line item types.
$ 0.00
Grand Total:
$1,758.42
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
Signature Date
Si ture Date
■ ■ HEDRICK
■ ■ BROTHERS
■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #003
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #003: DPO #4 AV Equipment
TO: VILLAGE OF TEQUESTA FROM:
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
DATE CREATED: 4/19/2021 CREATED BY:
CONTRACT STATUS: Approved REVISION:
DESIGNATED REVIEWER: Doug Gordon (HEDRICK BROS CONST CO REVIEWED BY:
INC)
DUE DATE:
INVOICED DATE: 04/30/2021
SCHEDULE IMPACT.
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM
CTR
DESCRIPTION:
CE #005 - DPO#4 A/V Equipment
Owner Direct Purchase of AN Equipment (The
Experts) $124,431.97.
Tax Savings S7465.92
Tax savings included in GMP Budget
= $-38,847.00
Tax savings to date (PCCO #1)
- $33,139,50
Balance
$5707.50
Tax Savings This PCCO #3
$7465.92
Less Balance of Tax Savings in GMP
-$5707.50
Tax Savings difference to be realized on this
PCO $1758.42
ATTACHMENTS:
PCO#2000-002S DPO#4 AV- Executed.odf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
REVIEW DATE:
PAID DATE:
EXECUTED:
SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT:
HEDRICK BROS CONST CO INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
Kim Blair (HEDRICK BROS CONST CO
INC)
0
04/1912021
No
($127,948.86)
PCO # Title
Schedule Impact
Amount
2000-003 CE #005 - DPO#4 AN Equipment
($127,948.86)
Total:
($127,948.86)
CHANGE ORDER LINE ITEMS:
PCO # 2000-003- CE 9005 - DPOSd AN Fnuinment
#
Budget Code
Description
Amount
1
2003.15-16-110.SUB
AN Equipment- Material
$(124,431.97)
2
2003.15-16-110.SUB
AN Equipment Tax
$(7,465.97)
3
2003.15-18-150.SUB
AN Equipment Tax Savings
$5,707.50
Hedrick Brothers Construction Co., Inc. Page 1 of 2 Printed On: 4/21/2021 12:56 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
PCCO #003
#
Budget Code
Description
Amount
4
2003.15-18-150.SUB
AN Equipment Tax Savings
$(1,758.42)
Subtotal:
$(127,948.86)
General Liability (0.00% Applies to all line item types.):
$0.00
Contractor's Fee (0.00% Applies to all line item types.):
i $0.00
Subcontractor Default Insurance (0.00% Applies to all line item types.):
$0.00
Grand Total:
$(127,948.86)
The original (Contract Sum)
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was
The contract sum will be decreased by this Change Order in the amount of
The new contract sum including this Change Order will be
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach, 33401
NATURE
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
z y l
k1-
IkTE S IM At U R E DATE
C14610 NE 06(ul&L 4,41• I1
PRINT NAME AND TITLE RRIN N ME AND TITLE
$6,013,394.00
($306,371.25)
$5,707.022.75
($127,948.86)
$5.579,073.89
HEDRICK BROS CONST CO INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
1<j�2-c 4-22-2021
SIGNATURE
DATE
Robin Lunsford, Sr. Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 4/21/2021 12:56 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCO #2000-018
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Potential Change Order #2000-018: Correction to Tax
Savings Amount on Epic Metal Material
TO: VILLAGE OF TEQUESTA FROM: HEDRICK BROS CONSTRUCTION CO., INC
345 TEQUESTA DRIVE 2200 CENTERPARK WEST DRIVE SUITE 100
TEQUESTA Florida, 33469 WEST PALM BEACH Florida, 33409
PCO NUMBER/REVISION: 2000-018 / 0
REQUEST RECEIVED FROM:
STATUS: Pending - In Review
REFERENCE:
FIELD CHANGE: No
LOCATION:
SCHEDULE IMPACT:
CONTRACT: 20-399-01 - VILLAGE OF TEQUESTA COMM
CTR
CREATED BY: Kim Blair (HEDRICK BROS CONSTRUCTION
CO., INC)
CREATED DATE: 6/28 /2021
PRIME CONTRACT None
CHANGE ORDER:
ACCOUNTING
METHOD:
PAID IN FULL:
Amount Based
No
TOTAL AMOUNT: $7,555.50
POTENTIAL CHANGE ORDER TITLE: Correction to Tax Savings Amount on Epic Metal Material
CHANGE REASON: Other
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE #033 - Epic Metal Sales Tax Savings Correction
Subcontractor provided incorrect Sales Tax amount for Epic Metal Material. This amount was used in calculating PCCO #1 in which the owner was given
the sales tax savings. Therefore a correction needs to be done to reconcile to the correct sales tax savings amount:
Below is a summary of how PCCO #1 was Calculated.
1 CONSTRUCTION 15-05-120 - STRUCTURAL STEEL Epic Metal Material ($143,500.00)
2 CONSTRUCTION 15-05-120 - STRUCTURAL STEEL Epic Metal Tax ($16,215.50)
3 CONSTRUCTION 15-18-150 - SALES TAX SAVINGS Epic Metal Sales Tax Savings $ 16,215.50
4 CONSTRUCTION 15-16-110 - ELECTRICAL Peninsular Elec. Dist. Inc. Material ($133,200.00)
5 CONSTRUCTION 15-16-110 - ELECTRICAL Peninsular Elec. Dist. Tax ($10,303.00)
6 CONSTRUCTION 15-18-150 - SALES TAX SAVINGS Peninsular Elec. Dist. Tax Savings $ 10,303.00
7 CONSTRUCTION 15-15-710 - HVAC Trane Material ($94,590.00)
8 CONSTRUCTION 15-15-710 - HVAC Trane Tax ($6,621.00)
9 CONSTRUCTION 15-18-150 - SALES TAX SAVINGS $ 6,621.00
Total: ($371,290.00)
There was an incorrect tax and tax savings amount given for the Epic Metal Material.
The correct sales tax amount is $8,660.00
Which is calculated based on the following:
Epic Materials DPO Material = $143,500.00
FL State Sales Tax 6% = $8,610.00
County Tax Palm Beach (1 % of first $5000 of sales amount) = $50.00
Total Tax deduct ($8610.00+ $50 = $8,660.00)
Therefore the value of this change order is the difference: Sales Tax Savings Credit given in PCCO#001 $16,215.50
Hedrick Brothers Construction Co., Inc. page 1 of 2 Printed On: 6/28/ 2021 02 :26 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
ATTACHMENTS:
PCCO#001 Executed.Ddf
Less Correct sales tax amount $8660.00
Amount to reconcile excess credit $7555.50
PCO #2000-018
#
Sub.lob
Cost Code
Description
Type
Amount
1
PCCO#17 Correct Epic Metal Tax
15-18-150 - SALES TAX RECOVERY
Subcontractor provided incorrect Sales Tax amount for Epic
Metal Material. This amount was used in calculating PCCO #1 in
which the owner was given the sales tax savings. Therefore a
correction needs to be done to reconcile to the correct sales tax
savings amount:
Subcontractor
$ 7.555.50
Subtotal:
$7,555.50
General Liability: 0.00 % Applies to all line item types.
$ 0.00
Contractor's Fee: 0.00 % Applies to all line item types.
$ 0.00
Subcontractor Default Insurance: 0.00 % Applies to all line item types.
$ 0.00
Grand Total:
$7,555.50
Contractor
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Owner
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
Signature Date
Si ture Date
■ ■ HEDRICK
■ ■ BROTHERS
■ ■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #001
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #001:
DPO #1-3
TO: VILLAGE OF TEQUESTA FROM:
HEDRICK BROS CONST CO INC
345 TEQUESTA DRIVE
2200 CENTERPARK WEST DRIVE SUITE
TEQUESTA, Florida 33469
100
WEST PALM BEACH, Florida 33409
DATE CREATED: 3/23/2021 CREATED BY:
Kim Blair (HEDRICK BROS CONST CO
INC)
CONTRACT STATUS: Approved REVISION:
0
DESIGNATED REVIEWER:
REVIEWED BY:
DUE DATE:
REVIEW DATE: 04/01/2021
INVOICED DATE:
04/30/2021
PAID DATE:
SCHEDULE IMPACT:
EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR:
20-399-01 VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: ($371,290.00)
CTR
DESCRIPTION:
DPO# Owner P.O. #
P.O. Date
Vendor
Subcontractor Material Amount Tax Savings amount
1 21-000480
2-5-2021
Epic Metals
Steel Fabricators LLC $143,500.00 $16,215.50
2 21-000483
2-10-2021
Peninsular Elec.
Lightning Electric $133.200.00 $10,303.00
3 21-000482
2-10-2021
Trane
Mechanicool $94,590.00 $6,621.00
TOTAL
ATTACHMENTS:
PCO#2000-001 DPO#1-3.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
$371.290.00 $33,139.50
PCO # Title
Schedule Impact
Amount
2000-001 ! CE #002 - DPO #1-3
($371,290.00)
Total:
($371,290.00)
CHANGE ORDER LINE ITEMS:
pco it 2nnn-nni • cF imn2 . npn ni-s
#
Budget Code
Description
Amount
1
2001.15-05-120.SUB
Epic Metal Material
S(143,500.00)
2
2001.15-05-120.SUB
Epic Metal Tax
$(16,215.50)
3
2001.15-18-150.SUB
Epic Metal Sales Tax Savings
$16,215.50
4
2001.15-16-110.SUB
Peninsular Elec. Dist. Inc. Material
$(133,200.00)
5
2001.15-16-110.SUB
Peninsular Elec. Dist. Tax
$(10,303.00)
6
2001.15-18-150.SUB
Peninsular Elec. Dist. Tax Savings
$10,303.00
7
2001.15-15-710.SU8
Trane Material
$(94,590.00)
8
2001.15-15-710.SUB
Trane Tax
$(6,621.00)
Hedrick Brothers Construction Co., Inc. Page 1 of 2 Printed On: 4/21/2021 12:54 PM
■ ■ HEDRICK
■ ■ ■ BROTHERS
■ ■ CONSTRUCTION
PCCO #001
#
I Budget Code
Description Amount
9
2001.15-18-150.SUB
Trane Tax Savings $6,621.00
Grand Total: $(371,290.00)
The original (Contract Sum) $6,013,394.00
Net change by previously authorized Change Orders $0.00
The contract sum prior to this Change Order was $6,013,394.00
The contract sum will be decreased by this Change Order in the amount of ($371,290.00)
The new contract sum including this Change Order will be $5,642,104.00
The contract time will not be changed by this Change Order.
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach, 33401
SIGNATURE 6ATE
'T t (-i
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc.
VILLAGE OF TEQUESTA HEDRICK BROS CONST CO INC
345 TEQUESTA DRIVE 2200 CENTERPARK WEST DRIVE SUITE
100
TEQUESTA, Florida 33469 WEST PALM BEACH, Florida 33409
i
4/21/2021
SIGN UR DATE SIGNATURE DATE
Robin Lunsfcrd, Sr. Project Executive
NAME AND TITLE PRINT NAME AND TITLE
Page 2 of 2 Printed On: 4/21/2021 12:54 PM