HomeMy WebLinkAboutAgreement_General_7/8/2021_Johnson Davis- Work AuthorizationDate of Issuance: June 10, 2021
Project: Beach Road Water Main
CONTRACT CHANGE ORDER
Change OrderNo. 1
Effective Date: June 10, 2021
Owner: Village of Tequesta Owner's Contract No.: Work Authorization No. 1
Contract: Piggyback Agreement to PBC 2019 Pipeline Continuing
Construction Contract
Contractor: Johnson -Davis, Inc.
Date of Contract: July 9, 2020
Engineer's Project No.: 040097024
The Contract Documents are modified as follows upon execution of this Change Order:
Description: During construction of this project, the Sea Glass project encountered a modification to their plans resulting
in their fire hydrants being located within the public ROW. Due to the new location, the Sea Glass developer has asked
the Village's contractor to install the piping and fire hydrants as part of this contract.
Attachments (list documents supporting change):
Proposed CO #1 Request prepared by Johnson -Davis, dated 5/25/2021
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price:
Original Contract Times: ❑ Working days ❑ Calendar days
Substantial completion (days or date): 4/16/2021
$ 419,181.43
Ready for final payment (days or date): 5/16/2021
_
Ale. 0 to
Substantial completion (days): N/A
$ N/A
Ready for final payment (days): N/A
Contract Price prior to this Change Order:
Contract Times prior to this Change Order:
Substantial completion (days or date): 4/16/2021
$ 419 181.43
Ready for final payment (days or date): 5/16/2021
[Increase] iDeerease} of this Change Order:
[Increase] f9e6Feas4of this Change Order:
Substantial completion (days or date): 100 days
$ 310,710.00
Ready for final payment (days or date): 0 days
Contract Price incorporating this Change Order:
Contract Times with all approved Change Orders:
Substantial completion (days or date): 7/25/2021
$ 449,891.43
Ready for final payment (days or date): 8/24/2021
RECOMKf i'IDE
Engineer (Authorized Si Mature)
Date: June 4, 2021
Approved by Funding Agency (if applicable)
By: Frank E Ambra - Mayor
Owner (Authorized Signature)
Date: 0yi.p 12, 20
N/A
END OF SECTION
ACCEPTED
By: .
Contrac or (Authorized
Date: June 3, 2021