HomeMy WebLinkAboutDocumentation_Regular_Tab 24_11/15/2021Agenda Item #24.
Regular Council
STAFF MEMO
Meeting: Regular Council - Nov 15 2021
Staff Contact: Matthew Hammond, Utilities Department: Utilities
Director
M 1�
Approve Work Authorization HCE U22.01 —Water Main Replacement Program —Jupiter-in-the-Pines
(South) -Professional Engineering Services —Holtz Consulting Engineers
The Village delivers potable water to approximately 15,000 people through a transmission and
distribution network of 72 miles of underground water mains dating back to the 1950's, 30 miles of
which are asbestos cement pipe constructed between the 1950's and 1970's. Asbestos cement pipe is
highly resistant to corrosion yet is also "brittle" and difficult to tap and repair. Over time when asbestos
cement pipe fails it does so catastrophically (large breaks) without warning and repairing carries
inherent risks due to the brittle nature of the material. As a material that has not been manufactured for
40 years obtaining parts to complete these repairs is becoming increasingly difficult. The projected
lifespan of asbestos cement pipe ranges from 40 - 70 years.
As a result, an aggressive Water Main Replacement Program was included in the approved Capital
Improvement Program (CIP) that will replace the remaining asbestos cement pipe within the water
system over a 10 to 15-year time span. The initial phase of replacements, proposed to be funded
through a bond issue, will be completed over a 3-5 year period. Project WM-3 (Jupiter -in -the -Pines -
South) is a part of the initial phase and will replace approximately 14,000 feet of water main within the
portion of the Jupiter -in -the -Pines neighborhood south of Tequesta Drive.
Staff recommends the professional engineering services for this project be completed by Holtz
Consulting Engineers, one of the Village's on -board engineering consultants. The proposed Work
Authorization HCE U22.01, in the amount of $167,320.00, includes the design, permitting, bidding and
construction -phase services required for the project. If approved, the project will be completed in the
Summer of 2022. A subsequent work authorization for bidding and construction -phase services will be
submitted at a later date.
Budget Summary - 401-411-663.632 - Architecture & Engineering Services:
Project
WTP Upgrades &
Energy
Improvements
(Engineering)
Water Main
Replacement
Program - WM-3 -
Bud et Encumbered Proposed
Projected Projected
Remaining Total
$350)000.00
$2411000.00
$0.00
$110,000.00
$351 1000-00
$281)000.00
$0.00
$1671320.00
$90)000.00
$2571320.00
Page 424 of 433
Agenda Item #24.
Jupiter in the Pines
South (Engineering)
Water Main
Replacement
Program - WM-5 -
$160,000.00
$1575525.00
$0.00
$455000.00
$202Y525.00
Country Club Drive
North (Engineering)
Surficial Well
Replacement -Well
No. S18
$132)000.00
$0.00
$0.00
$1325000.00
$1323000.00
(Engineering)
Concentrate
Disposal Relocation
$111,000.00
$61 ,275.00
$0.00
$305000.00
$91 Y275.00
(Engineering)
Account Total
$150345000.00
$4595800.00
$1675320.00
$4075000.00
$1)0345120.00
This document and any
attachments may
be reproduced upon request in
an alternative format by completing
our Accessibility Feedback Form, sending an e-mail to the
Village Clerk or
calling 561-768-0443.
BUDGETED AMOUNT: AVAILABLE AMOUNT: EXPENDITURE AMOUNT:
$17034;000 $5747200 $1677320
Additional Budgetary Information: Funding Source(s):
Water Enterprise Fund
Approve Work Authorization HCE U22.01 with Holtz Consulting Engineers in the amount of $167,320.
Proposed Work Authorization HCE U22.01 - Water Main Replacement Project No. 3.ada
Project WM 3 - Jupiter -in -the -Pines - South
Page 425 of 433
Agenda Item #24.
The following documenti*s presented in a non=
ADA compliant format. Please contact the
Village Clerk's office if you would like to
receive an ADA compliant version of this
document.
Page 426 of 433
Agenda Item #24.
DATE: 10/1/2021
VILLAGE OF TEQUESTA
CONSULTING SERVICES WORD AUTHORIZATION
VILLAGE RFQ. NO.
WORK AUTHORIZATION HCE U22.01 FOR CONSULTING SERVICES
PROJECT No.
GIL CODE: 401-411-663.632
HOLTZ CONSULTING PROJECT NO.:
PROJECT TITLE: Asbestos Cement Water Main Replacement Project Phase 3
This Work Authorization, when executed, shall be incorporated in and shall become an integral
part of the Agreement for Professional Services dated September 10, 2020 between the village of
Tequesta ("VILLAGE"), and Holtz Consulting Engineers, Inc. ("CONSULTANT") hereafter
referred to as the Agreement.
I. PROJECT DESCRIPTION
The project will include engineering services for the design, permitting, bidding, and construction of
approximately 14,000 feet of potable water main to replace the existing AC pipe along the streets
listed below:
• Dover Road
• Dover Circle
• Evergreen Ave
• Beacon Street
• Church Road
• Franklin Road
• Division Street
• Daly Road
• Leigh Road
• Maple Ave
• Elm Ave
• Oak Ave
• Cedar Ave
• Seabrook Road from Tequesta Drive to Franklin Road
• Venus Ave from Tequesta Drive to Division Street
WORK AUTHORIZATION NO. HCE-U22.01 1 of 6
Page 427 of 433
Agenda Item #24.
0 Mars Ave
0 Saturn Ave
9 Fiesta Ave
The existing AC pipe was installed in the 1950's and 1960's and has reached the end of its useful life.
Replacing the AC pipe will reduce the risk of failure and increase the resiliency of the Village's potable
water distribution system. Included in the design will be the replacement of water services from the
new water mains to the existing water meters, new fire hydrants, and the grout ing/abandonment of the
existing AC pipe after the new water mains are placed into service.
11. SCOPE OF SERVIC
The following is a description of the services to be provided under this Work Authorization.
TASK 1 — SITE INVESTIGATION AND SURVEYING SERVICES
Subtask 1.1 Utility Locates
Under this subtask the CONSULTANT will provide utility locating services for key existing buried
utilities along the 1 utilizing ground penetrating radar to
ti 1 watermain route, Locates w'11 be performed ut'l' '
obtain depth, diameter, and material information for the existing buried utilities to identify potential
design conflicts and aid in the protection of these existing facilities during construction. These
underground utility markings will be captured by the sun7eyor under Subtask 1.2 and depicted on the
survey and design drawings.
Subtask 1.2 Topographic Survey
Under this task, CONSULTANT will obtain a topographic survey from right-of-way to right-of-way
along the water main routes listed in the project description. The survey will depict the horizontal
location and vertical location of facilities and surface features and an AutoCAD version of the survey
will be provided along with one (1) signed and sealed hard copy. The survey will also depict the
markings provided by the underground locator in Subtask 1.1.
TASK 2 — DESIGN SERVICES
CONSULTANT will vt'sit the project site and review existing record drawing information for utilities
in the project limits and GIS information to determine the optimal route for the new water mains in
consideration of the locations of existing- utilities, landscaping, and water meters. CONSULTANT
will coordinate a project kick-off meeting to discuss the proposed pipe alignment and other critical
design aspects. CONSULTANT will summarize the decisions made in meeting minutes.
CONSULTANT shall prepare construction drawings for the rcptacement of approximately fourteen
thousand (14,000') linear feet of existing AC water main in the road rights -of -way, including
connection to the existing water meters and installation of new fire hydrants. The existing AC pipes
range in size from four (4" inch to ten (10"") inch in diameter. Proposed water mains shall be
minimum of six (6"') inch in diameter and new main sizes will be determined by the VILLAGE based
on hydraulic mod tin performed by the VILLAGE or the VILLAGE's other subconsultants. All
existing pipes to be replaced will be abandoned and grouted in place, if feasible.
WORK AUTHORIZATION NO. HCE-U22.01 2 of 6
Page 428 of 433
Agenda Item #24.
The water main improvements installed via open -cut methods will be shown in plan view only. Water
mains to be installed via horizontal directional drill will be depleted in plan and profile views.
Conflicts with existing utilitics will be addressed on the plan views with conflict box callouts showing
the proposed pipes and existing utilities identifying separation distances and elevations.
CONSULTANT shall provide drawings at the 30%, 60%, 90% and 100% design milestones for
VILLAGE review and comment and technical specifications for VILLAGE review and comment at
the 30%, 60%, and 90% design milestones. Technical specifications will be based on the CSI 16
division format. The front-end contract documents provided by the VILLAGE will be incorporated into
the Contract Documents by the CONSULTANT.
CONSULTANT shall also prepare engineer's opinion of probable cost of construction at the 30%,
60%1 90% and 100% design milestones. A blank and completed bid form will be prepared and
submitted to the VILLAGE for their insertion into the VILLAGE's front-end bidding and contract
documents.
Following the 30%, 60% and 90% submittal review by the VILLAGE, CONSULTANT shall meet
with VILLAGE to discuss comments, and they. prepare the documents incorporating VILLAGE'S
comments for the next submittal.
TASK 3 — PERMITTING SERVICES
Subtask 3.1 Health Department Permit Application
CONSULTANT shall prepare permit applications for construction of the project and submit to the
following agencies:
Palm Beach County Health Department (PBCHD)
Perinit fees will be paid by the VILLAGE.
Subtask 3.2 Agency Coordination and RAI Response
CONSULTANT will coordinate with the permitting agency (PBCHD) during the review process on
a regular basis in an effort to keep the project on schedule and respond to their review comments.
I ICE. will respond to Requests for Additional Information (RAI ) during the permitting process. It is
anticipated that no more than one (1) RAI will be issued.
TASK 4 — SRF FUNDING ASSISTANCE
Subtask 4.1 Prepare and Submit Request for Inclusion, Packages
CONSULTANT shall prepare and submit one Request for Inclusion (RFI) packages and Supporting
documentation to the FDEP. One "Requests for Inclusion on the Priority.List for Drinking Water
Facilities" (DEP Fort 62-252.900(l)) and supporting documentation will be submitted to the
Drinking Water SIF program. There will be one construction loan request for this project.
WORK AUTHORIZATION NO. HCE-U22.01 of 6
Page 429 of 433
Agenda Item #24.
Subtask 4.2 Prepare and Submit Water Facilities Plan,
CONSULTANT shall include this project in the Water Facilities Plan being prepared under a separate
Work Authorization (HCE WA#2).
Subtask 4.3 Loan Application and Agreement Package Assistance
1W W
CONSULTANT shall assist the VILLAGE with the preparationT submission, and coordination of the
loan application and loan agreement package for the SRF Drinking Water Facilities Loan Application
(DEP Fonn 62-552.900(2).
Subtask 4.4 Assistance with SRF Compliance Components of Construction Contract
Documents
CONSULTANT shall assist with SRF bid and construction contract documents for the proJect. This
may include supplementary conditions and Davis -Bacon wage requirements, to be included in the
contract documents,, and assistance to the VILLAGE in submitting bid documents to the DEP such as
addenda, debarment certification COPY of advertisement bid tabulation and recommendation of
award, and certification from Appendix A, FIEF Supplementary Conditions, and Davis Bacon wage
rates.
111.1 DELIVERAB
Task I - Deliverables:
1. Information obtained from underground utility locating will be depicted on the survey
deliverable provided under Subtask 1.3.
2. One (I) signed and sealed PDF copy of Topographic Survey will be provided.
Task 2 - Deliverables
1. One (1) PDF copy of the 30% plans and specifications (TOC only) and 30% cost estimate.
2. One (1) PT F copy of the 60% plans and specifications and 60% cost estimate.
3. One (1) PDF copy of the 90% plans and specifications and 90% cost estimate.
4. One (1) signed and sealed PT F copy and one (1) signed and sealed hard copy of the final
(100%) plans and specifications and final cost estimate.
5. Electronic copies of all meeting agendas and minutes.
Task 3 - Deliverables,
1. PDF copy of the fully executed permit application package.
2. PDF copy of each permit received.
WORK AUTHORIZATION N. HCE-U22.01 4 of 6
Page 430 of 433
Agenda Item #24.
Task 4 Deliverables:
1. Minutes distributed to all attendecs of the kick-off meeting.
2. Written list of data needs to complete the SRF documentation.
3. FIEF copy of each completed SRF Request for Inclusion (RFI) package and supporting
documentation submittcd to the FDEP.
4. One (1) hard copy and one (1) ICI F copy of the completed Water Facilities Plan.
5. PDF copy of minutes ftorn the public meeting.
6. FIEF copy of all loan application and loan agreement items provided to the VILLAGE in
assistance of submission to the FDEP. The VILLAGE will be -required to submit the loan
application and loan agreement to the FDEP.
7. FIEF copy of all required SRF bid and construction contract documents required.
IV, SCHEDULE
Upon receipt of Notice -To -Proceed the CONSULTANT will. complete the services
identified in this
Work Authorization within the schedule outlined in Table I.
Table 1
Schedule
Cumulative'l'ime
Time to Complete
to Complete
(Calendar Da
(Calendar D
Activity
1.1. Subsurface Utility Locating
21 days from NTP
21 days
1.2. Surveying Services
60
81
2. Design Services
30% Design Submittal
45 days from receipt of survey
126
60 % Design Submittal
60 days from receipt of comments on
V
193
the 30% submittal
90% Design Submittal
60 days from receipt of comments on
260
60% submittal
100% Dcsign Submittal
21 days fron-1 receipt of comments on
288
90% submittal
3. Permitting
Applications submitted with 90%
260
plans
4. SRF Funding Assistance
Request for Inclusion Submittal
30 days after kickoff meeting
Loan Application Submittal
30 days after approval from FDEP
The schedule is based upon conducting a review meeting within 7 calendar days after the Village
receives the design submittal. All review comments shall be provided to Consultant within 7
calendar days after the Village receives the submittal. An adjustment to the overall schedule will
WORK AUTHORIZATION NO. HCE-U22.01 5 of 6
Page 431 of 433
Agenda Item #24.
I
be required in the event the review meeting takes totiger to be conducted and..."or obtaining
comments takes longer to receive. Schedule assumes permits will be issued within 60 days.
V. COMPENSATION AND PAYMENT
The CONSULTANT will perform the tasks as outlined in the scope of services for Lump Sum Fee
of $167,320 in accordance with our approved billing rates with an estimate of costs by task provided
in Table 2. Monthly progress payments will be authorized based on percent complete as determined
by CONSULTANT and approved by VILLAGE.
Table 2
Budget Summary
Description
Total
1. Site Investigation and Surveying
$645235
2, Design Services
$941815
3. Permitting
S 1, 0
4. SRF Funding Assistance
$6,640
TOTAL
$167,320
I. ASSUMPTIONS
1. All permit fees will be paid by the VILLAGE.
2. The new water main sizes will be determined by the VILLAGE. No hydraulic modeling
or fire -flow modeling is included in this proposal.
I. AGREEMENT REFERENCE
The work authorized under this Work Authorization shall be perfonned under the terms and
conditions described within the Professional Services Agreement dated September 10, 2020, by and
between the Village of Tequesta (""VILLAGE") and Holtz Consulting ( 6C. CONSULTANTI I
Compensation shall not exceed the hourly rates currently in effect under this Agreement.
HOOT Z CONSULTING
was
Print Name:
Title:
VILLAGE OF TEQUESTA
0
Date.-
WORK AUTHORIZATION NO. HE-U22.01
6 of 6
Page 432 of 433
=0
O
�
C:
U
C6
(6
Q
C6
Pag 433 c