DEPARTMENT AND STAFF
CONTACT:
Utilities - Matt Hammond
VENDOR:
Holtz Consulting
COUNCIL APPROVAL DATE:
11/15/2021
ORDINANCE/RESOLUTION
NUMBER:
TITLE OF AGREEMENT:
Work Authorization HCE U22.01
DOLLAR AMOUNT:
$167,320
AGREEMENT TERM END
DATE:
NUMBER OF DOCUMENTS
TO BE SIGNED:
1
SPECIAL INSTRUCTIONS
FOR CLERKS'S OFFICE:
VILLAGE OF TEQUESTA
1► 1 ► 1., 11 1►
DATE: 10/1/2021 VILLAGE RFQ. NO.:
WORK AUTHORIZATION HCE U22.01 FOR CONSULTING SERVICES
PROJECT No. G/L CODE: 401-411-663.632
HOLTZ CONSULTING PROJECT NO.:
PROJECT TITLE: Asbestos Cement Water Main Replacement Project Phase 3
This Work Authorization, when executed, shall be incorporated in and shall become an integral
part of the Agreement for Professional Services dated September 10, 2020 between the Village of
Tequesta ("VILLAGE"), and Holtz Consulting Engineers, Inc. ("CONSULTANT") hereafter
referred to as the Agreement.
The project will include engineering services for the design, permitting, bidding, and construction of
approximately 14,000 feet of potable water main to replace the existing AC pipe along the streets
listed below:
• Dover Road
• Dover Circle
• Evergreen Ave
• Beacon Street
• Church Road
• Franklin Road
• Division Street
• Daly Road
• Leigh Road
• Maple Ave
• Elm Ave
• Oak Ave
• Cedar Ave
• Seabrook Road from Tequesta Drive to Franklin Road
• Venus Ave from Tequesta Drive to Division Street
WORK AUTHORIZATION NO. HCE-U22.01 1 of 6
• Mars Ave
• Saturn Ave
• Fiesta Ave
The existing AC pipe was installed in the 1950's and 1960's and has reached the end of its useful life.
Replacing the AC pipe will reduce the risk of failure and increase the resiliency of the Village's potable
water distribution system. Included in the design will be the replacement of water services from the
new water mains to the existing water meters, new fire hydrants, and the grouting/abandonment of the
existing AC pipe after the new water mains are placed into service.
The following is a description of the services to be provided under this Work Authorization.
TASK 1— SITE INVESTIGATION AND SURVEYING SERVICES
Subtask 1.1 Utility Locates
Under this subtask the CONSULTANT will provide utility locating services for key existing buried
utilities along the watermain route. Locates will be performed utilizing ground penetrating radar to
obtain depth, diameter, and material information for the existing buried utilities to identify potential
design conflicts and aid in the protection of these existing facilities during construction. These
underground utility markings will be captured by the surveyor under Subtask 1.2 and depicted on the
survey and design drawings.
Subtask 1.2 Topographic Survey
Under this task, CONSULTANT will obtain a topographic survey from right-of-way to right-of-way
along the water main routes listed in the project description. The survey will depict the horizontal
location and vertical location of facilities and surface features and an AutoCAD version of the survey
will be provided along with one (1) signed and sealed hard copy. The survey will also depict the
markings provided by the underground locator in Subtask 1.1.
TASK 2 — DESIGN SERVICES
CONSULTANT will visit the project site and review existing record drawing information for utilities
in the project limits and GIS information to determine the optimal route for the new water mains in
consideration of the locations of existing utilities, landscaping, and water meters. CONSULTANT
will coordinate a project kick-off meeting to discuss the proposed pipe alignment and other critical
design aspects. CONSULTANT will summarize the decisions made in meeting minutes.
CONSULTANT shall prepare construction drawings for the replacement of approximately fourteen
thousand (14,000') linear feet of existing AC water main in the road rights -of -way, including
connection to the existing water meters and installation of new fire hydrants. The existing AC pipes
range in size from four (4") inch to ten (10") inch in diameter. Proposed water mains shall be
minimum of six (6") inch in diameter and new main sizes will be determined by the VILLAGE based
on hydraulic modeling performed by the VILLAGE or the VILLAGE's other subconsultants. All
existing pipes to be replaced will be abandoned and grouted in place, if feasible.
WORK AUTHORIZATION NO. HCE-U22.01 2 of 6
The water main improvements installed via open -cut methods will be shown in plan view only. Water
mains to be installed via horizontal directional drill will be depicted in plan and profile views.
Conflicts with existing utilities will be addressed on the plan views with conflict box callouts showing
the proposed pipes and existing utilities identifying separation distances and elevations.
CONSULTANT shall provide drawings at the 30%, 60%, 90% and 100% design milestones for
VILLAGE review and comment and technical specifications for VILLAGE review and comment at
the 30%, 60%, and 90% design milestones. Technical specifications will be based on the CSI 16
division format. The front-end contract documents provided by the VILLAGE will be incorporated into
the Contract Documents by the CONSULTANT.
CONSULTANT shall also prepare engineer's opinion of probable cost of construction at the 30%,
60%, 90% and 100% design milestones. A blank and completed bid form will be prepared and
submitted to the VILLAGE for their insertion into the VILLAGE's front-end bidding and contract
documents.
Following the 30%, 60% and 90% submittal review by the VILLAGE, CONSULTANT shall meet
with VILLAGE to discuss comments, and then prepare the documents incorporating VILLAGE'S
comments for the next submittal.
TASK 3 — PERMITTING SERVICES
Subtask 3.1 Health Department Permit Application
CONSULTANT shall prepare permit applications for construction of the project and submit to the
following agencies:
Palm Beach County Health Department (PBCHD)
Permit fees will be paid by the VILLAGE.
Subtask 3.2 Agency Coordination and RAI Response
CONSULTANT will coordinate with the permitting agency (PBCHD) during the review process on
a regular basis in an effort to keep the project on schedule and respond to their review comments.
HCE will respond to Requests for Additional Information (RAI) during the permitting process. It is
anticipated that no more than one (1) RAI will be issued.
TASK 4 — SRF FUNDING ASSISTANCE
Subtask 4.1 Prepare and Submit Request for Inclusion Packages
CONSULTANT shall prepare and submit one Request for Inclusion (RFI) packages and supporting
documentation to the FDEP. One "Requests for Inclusion on the Priority List for Drinking Water
Facilities" (DEP Form 62-252.900(1)) and supporting documentation will be submitted to the
Drinking Water SRF program. There will be one construction loan request for this project.
WORK AUTHORIZATION NO. HCE-U22.01 3 of 6
Subtask 4.2 Prepare and Submit Water Facilities Plan
CONSULTANT shall include this project in the Water Facilities Plan being prepared under a separate
Work Authorization (HCE WA#2).
Subtask 4.3 Loan Application and Agreement Package Assistance
CONSULTANT shall assist the VILLAGE with the preparation, submission, and coordination of the
loan application and loan agreement package for the SRF Drinking Water Facilities Loan Application
(DEP Form 62-552.900(2).
Subtask 4.4 Assistance with SRF Compliance Components of Construction Contract
Documents
CONSULTANT shall assist with SRF bid and construction contract documents for the project. This
may include supplementary conditions and Davis -Bacon wage requirements to be included in the
contract documents, and assistance to the VILLAGE in submitting bid documents to the DEP such as
addenda, debarment certification, copy of advertisement, bid tabulation and recommendation of
award, and certification from Appendix A, FDEP Supplementary Conditions, and Davis Bacon wage
rates.
III. DELIVERABLES
Task 1 - Deliverables:
1. Information obtained from underground utility locating will be depicted on the survey
deliverable provided under Subtask 1.3.
2. One (1) signed and sealed PDF copy of Topographic Survey will be provided.
Task 2 - Deliverables
1. One (1) PDF copy of the 30% plans and specifications (TOC only) and 30% cost estimate.
2. One (1) PDF copy of the 60% plans and specifications and 60% cost estimate.
3. One (1) PDF copy of the 90% plans and specifications and 90% cost estimate.
4. One (1) signed and sealed PDF copy and one (1) signed and sealed hard copy of the final
(100%) plans and specifications and final cost estimate.
5. Electronic copies of all meeting agendas and minutes.
Task 3 - Deliverables
1. PDF copy of the fully executed permit application package_
2. PDF copy of each permit received.
WORK AUTHORIZATION NO. HCE-U22.01 4 of 6
Task 4 Deliverables:
1. Minutes distributed to all attendees of the kick-off meeting.
2. Written list of data needs to complete the SRF documentation.
3. PDF copy of each completed SRF Request for Inclusion (RFI) package and supporting
documentation submitted to the FDEP.
4. One (1) hard copy and one (1) PDF copy of the completed Water Facilities Plan.
5. PDF copy of minutes from the public meeting.
6. PDF copy of all loan application and loan agreement items provided to the VILLAGE in
assistance of submission to the FDEP. The VILLAGE will be required to submit the loan
application and loan agreement to the FDEP.
7. PDF copy of all required SRF bid and construction contract documents required.
IV. SCHEDULE
Upon receipt of Notice -To -Proceed the CONSULTANT will complete the services
identified in this
Work Authorization within the schedule outlined in Table 1.
Table 1
Schedule
Cumulative Time
Time to Complete
to Complete
Activity
(Calendar Days)
(Calendar Days)
1.1. Subsurface Utility Locating
21 days from NTP
21 days
1.2. Surveying Services
60
81
2. Design Services
30% Design Submittal
45 days from receipt of survey
126
60% Design Submittal
60 days from receipt of comments on
193
the 30% submittal
90% Design Submittal
60 days from receipt of comments on
260
60% submittal
100% Design Submittal
21 days from receipt of comments on
288
90% submittal
3. Permitting
Applications submitted with 90%
260
plans
4. SRF Funding Assistance
Request for Inclusion Submittal
30 days after kickoff meeting
Loan Application Submittal
30 days after approval from FDEP
* The schedule is based upon conducting a review meeting within 7 calendar days after the Village
receives the design submittal. All review comments shall be provided to Consultant within 7
calendar days after the Village receives the submittal. An adjustment to the overall schedule will
WORK AUTHORIZATION NO. HCE-U22.01 5 of 6
be required in the event the review meeting takes longer to be conducted and/or obtaining
comments takes longer to receive. Schedule assumes permits will be issued within 60 days.
The CONSULTANT will perform the tasks as outlined in the scope of services for Lump Sum Fee
of $167,320 in accordance with our approved billing rates with an estimate of costs by task provided
in Table 2. Monthly progress payments will be authorized based on percent complete as determined
by CONSULTANT and approved by VILLAGE.
Table 2
Budget Summary
Description
Total
1. Site Investigation and Surveying
$64,235
2. Design Services
$94,815
3. Permitting
$1,630
4. SRF Funding Assistance
$6,640
TOTAL
$167,320
1. All permit fees will be paid by the VILLAGE.
2. The new water main sizes will be determined by the VILLAGE. No hydraulic modeling
or fire -flow modeling is included in this proposal.
UI 04TUMM, OWN
The work authorized under this Work Authorization shall be performed under the terms and
conditions described within the Professional Services Agreement dated September 10, 2020, by and
between the Village of Tequesta ("VILLAGE") and Holtz Consulting ("CONSULTANT").
Compensation shall not exceed the hourly rates currently in effect under this Agreement.
HOLTZ CONSULTING
Print Name: Andrea Holtz
Title: President
VILLAGE OF TEQUESTA
Date: 11—I La -a
WORK AUTHORIZATION NO. HCE-U22.01 6 of 6