HomeMy WebLinkAboutAgreement_General_1/13/2022_Hedrick Brothers■ ■ HEDRICK
■ BROTHERS
■ CONSTRUCTION
Hedrick Brothers Construction Co., Inc.
2200 Centrepark West Drive, Suite 100
West Palm Beach, Florida 33409
Phone: (561) 689-8880
PCCO #024
Project: 20-399-01 - TEQUESTA COMMUNITY CTR
399 Seabrook Road
Tequesta , Florida 33469
Prime Contract Change Order #024: PCCO#24-ELECTRICAL CHANGES
TO: VILLAGE OF TEQUESTA FROM: HEDRICK BROS CONSTRUCTION CO.,
345 TEQUESTA DRIVE INC
TEQUESTA, Florida 33469 2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
DATE CREATED: 11 /19/2021 CREATED BY: Monica Crowley (HEDRICK BROS
CONSTRUCTION CO., INC)
CONTRACT STATUS: Pending - In Review REVISION: 0
DESIGNATED REVIEWER: REVIEWED BY:
DUE DATE: REVIEW DATE:
INVOICED DATE: PAID DATE:
SCHEDULEIMPACT- EXECUTED: No
SIGNED CHANGE ORDER
RECEIVED DATE:
CONTRACT FOR: 20-399-01:VILLAGE OF TEQUESTA COMM TOTAL AMOUNT: $3,569.43
CTR
DESCRIPTION:
CE24-ELECTRICA...L._CHAN.QES.
1. Provide power for the projector and sub woofer. During a walk through with the Village of Tequesta's IT director, this request was made and it differs
from the drawings and scope performed = $721.65
2. Provide relocation power, data and J-box for gym projector as requested by the Village of Tequesta's IT Director = $2,544.07
ATTACHMENTS:
21-C7 H13_IE-QUESTA R>=C 1.6R LQ 1_rE—FWDAAPAA.-@9XEORGYUPfROJECTOR,Rd1 21C796-H$-TEQUESTA RFC1,:PROYtOE
POW_E_RIO R_-PROJECTOR &_$UQWQOFER-pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE nRDFR-
PCO #
Title
Schedule Impact
Amount
2000-028
PCCO#24-ELECTRICAL CHANGES
$3,569,43
Total:
$3,569.43
CHANGE ORDER LINE ITEMS:
PCO # 2000-028- PCC01124-FI FCTRICAI CNANr:FS
#
Budget Code
Description
Amount
1
2024.15-16-110.SUB PCCO#24-ELECTRICAL
CHANGES. ELECTRICAL. Subcontractor
PCCO#24-Power to Project/Sub Woofer
$721.65
2
2024.15-16-110.SUB PCCO#24-ELECTRICAL
CHANGES. ELECTRICAL.Subcontractor
PCCO#24-Power to Gym Projector
$2,544,07
Subtotal:
$3,265.72
General Liability (1.30% Applies to all line item types.):
$42.45
Contractor's Fee (6.50% Applies to all line item types.):
$212.27
Subcontractor Default Insurance (1.50% Applies to all line item types.):
$48.99
Grand Total:
$3,569.43
Hedrick Brothers Construction Co., Inc. Page 1 of 2 Printed On: 11/19/2021 12:33 PM
■ ■ HEDRICK PCCO #024
BROTHERS
■ CONSTRUCTION
The original (Contract Sum) $6,013,394.00
Net change by previously authorized Change Orders
The contract sum prior to this Change Order was $5,816,039.36
The contract sum would be changed by this Change Order in the amount of $3,569.43
The new contract sum including this Change Order will be $5,819,608.79
The contract time will not be changed by this Change Order
REG ARCHITECTS, INC.
120 S. Olive Ave. Ste. 210
West Palm Beach. 33401
VILLAGE OF TEQUESTA
345 TEQUESTA DRIVE
TEQUESTA, Florida 33469
led
SIGNATURE DATE SI ATURE DATE
PRINT NAME AND TITLE PO4,�05(' PRINT NAME AND TITLE { �,
HEDRICK SROS CONSTRUCTION CO., INC
2200 CENTERPARK WEST DRIVE SUITE
100
WEST PALM BEACH, Florida 33409
115122
SIGNATURE DATE
Senior Project Executive
PRINT NAME AND TITLE
Hedrick Brothers Construction Co., Inc. Page 2 of 2 Printed On: 11/19/2021 12:33 PM
f