Undergrounding Project Phases
Project Initiation (-2 weeks)
Engineering —Preliminary Design (-4-5 months based on scope)
Outreach/Feedback (dependent on Municipality)
Engineering —Final Design (-2-3 months based on scope)
Construction (based on scope)
Alp—
_ _ - ►'
CH,PINI1iG THE CURRENT.. FRL
Project Initiation
Municipality notifies FPL of the interest to convert Overhead lines to
Underground.
FPL provides ball park estimate and the engineering fee cost for the
area requested.
If the initial request for the entire City/Town/Village limits, FPL works
with the municipality on a phasing plan. Subsequently, a new ball
park estimate is provided for the phases to be started.
Once the engineering deposit is paid, FPL starts the engineering
phase.
.z.
CHAN _ G THE CURRENT.. FPL
Engineering — Preliminary Design
The Municipality is required to provide a geographical survey
showing existing/proposed road ROW, properly lines, and all existing
underground utilities i.e. water, sewer, storm drains, etc.
FPL performs field checks
Verify existing facilities
Determine field conditions
Identify potential locations for new underground equipment
Preliminary design showing initial equipment placement
Preliminary design showing routing of conduit and cable
.z.
CH�1N { THE CURRENT.. FPL
Outreach & Feedback
► Municipality is responsible for outreach with all involved property
owners to obtain necessary easements and agreements.
► FPL works with the Municipality on design changes based on
easement acquisition, physical obstructions, and preference.
► Once all necessary easements are secured Municipality provides
FPL with final design change requests.
.z.
=--*NLCURRENT.. FPL
Engineering — Final Design
► FPL works to finalize design, no further changes to the design are to
be made.
► FPL provides a Binding Cost Estimate according to the tariff and
based on the Municipality's method of construction.
► Binding Cost Estimate is valid for a period of 180 days.
.z.
THE CURRENT..
Construction
3 options for Construction
FPL performs all work. FPL will construct the entire project with an FPL vendor. FPL cannot
guarantee the schedule coordination with the undergrounding efforts of the other utilities
(CATV/Telecom).
Municipality hires FPL approved vendor to install all underground facilities. Allows the
efficient coordination and scheduling of undergrounding all utiltiies.
Hybrid - Municipality hires vendor to install all conduit, FPL installs cable, equipment, and
terminations. —Allows for coordination of conduit installation efforts of other utilities, but lends
to risks associated once FPL commences installation of cable and equipment.
Municipality hires certified electrician to convert existing
overhead services to underground.
0
AM
i-AN'� CHANGING THE CURRENT.. FPL
Important notes
Municipality is responsible for
Outreach — Communication with property owners and obtaining necessary easements
Coordination with other utilities' efforts to underground (all utilities attached to FPL poles)
Conversions of existing overhead services to be performed by a certified electrictian
Restoration of landscaping related to the installation of underground faciltiies.
FPL will perform all overhead work related to the conversion
Overhead installation of necessary equipment to incorporate new underground system.
Removal of overhead facilities once all customers are converted to new underground
system.
.z.
CHAN G THE CURRENT.. FPL
Stage
Time
Required
Provide written I Investigate Other Facilities
request Issues
Include well-
defined
boundaries
f the
Municipality conversion
area
FPL
• Other utilities (e.g.
Telecom & CATV) costs
• Site restoration
• Individual customer
service entrances
• Lighting - street & other
• Location of existing
underground facilities
• Easements
• Planned road work or
utility projects
Develop & Provide Estimate
Free, order -of -magnitude Muni.
out-of-pocket cost
(Contribution -In Aid -of
Construction - "CIAC')
Non-refundable engineering
deposit cost if Muni. elects to
request a binding cost estimate
Requirements checklist for next
steps
FPL - Varies based on
project size
Establish & Provide Design
Requirements
• Establish project manager
or contact (for full
duration)
• Pay non-refundable
engineering deposit
• Provide an electronic CAD file
of a scaled drawing including a
plan view of all underground
utilities, existing and proposed.
• Determine if want to
contract any work to a 3rd
party
• Agree on underground facilities
& cable locations including
easements and/or road rights-
oDf- way
• etermine/decide
lighting ownership
• Begin securing easements &
review of applicable
agreements and tariffs
Develop Final Design and
Project Cost
Engineering deposit invoice
Agree on phasing of large
projects into phases with
roughly 1 year of construction
apiece (overlapping phased
approach)
Preliminary facilities layout
Several site visits to review
existing/future facilities
locations
A detail engineering design
including underground facilities
locations so applicant can pursue
easements
Provide binding cost estimate
Municipal Review & Execution of
Agreements
Applicant - 180 days (after
receipt of binding cost
estimate)
Complete Requirements for
Construction Release
• All easements executed
and recorded
• Pay CIAC & any applicable
additional charges due to
applicant -requested scope
changes (e.g. 2nd Estimate - Muni.
elects to perform some
underground work) Execute
Agreements (as needed):
• Underground Conversion
Applicant -Installed
Facilities Right -of -Way
• Other utilities (e.g.
telecom, CATV, etc.)
3rd-party construction
contracts
• Permits obtained, if required
Incorporate Requested Project
Scope Changes
• Provide cost estimate for any
requested scope changes
Complete design of any
requested scope changes, upon
receipt of payment
• Finalize engineering design
and cnst drawings
• Finalize CIAC
• Permits obtained after
payment and executed
agreements are recieved, w
required
(e.g., weather, material/equipment lead time, I subsequent to construction)
labor, project complexity, etc.)
Provide Construction Assistance
Facilitate 3rd party attachment removal (Telecom
& CATV)
If applicable, provide:
• Muni. -installed facilities (electric &
lighting) FPL-approved contractor
• Request & execute switching
orders As -built construction
drawings
• Site restoration (e.g., sod landscaping,
pavement, compaction, sidewalks, etc.)
Rearrangement of customer electric
service entrances (requires electrician)
Trenching/bwkfilling for backbone or
service laterals
Maintenance of Traffic (MOT)
• Resident / business interface
Construct New Underground
Procure & deliver
materials If amli
Secure labor - conduct bids &
award contractors, w required
Install main underground facilities,
coordinating with other utilities,
I
appropriate
Coordinate with electricians on scheduled
appointments with residents / businesses to
convert service drops
Remove all existing overhead facilities after all
electric service drops are removed
FPL to remove poles after all utilities convert to
underground
Reconcile estimated costs with actuals (post -
construction)
Provide Individual
Service Change
Requirements
Schedule appointments for
service changes Inspection
received Install
Downpipe
Meter Can
Service lateral conduit
Unde, ground Converted
S tem Services
Energized Energized