K3DD DRILLING PROPOSAL / CONTRACT
rhis bid proposal is strictly confidential and meont solely for our prospecthe client and not robe shored without KYs prior written approval.
April 17, 2023
Village of Tequesta
345 Tequesta Dr
Jupiter, FL. 33469
Attn: David Tinoco
Re: 3450 Harbor Rd N, Tequesta
K3 Directional Drilling, Inc. (hereinafter "K3") proposes to provide Horizontal Directional Drilling (HDD) services that include
all labor and relevant equipment and tooling for the prices indicated.
THE FOLLOWING ARE INCLUDED IN THE ESTIMATE:
Description Units U/M Unit Price Extension
2" Water Service Casing D. Bore 1,00 IS $2,000.00 $2,000.00
Mobilization 1.00 L.5 $1,500.001500.10Q
TOTAL $3,500.00
• No pressure testing.
• All MOT by others.
• Material included.
• No retainage will be held from K3 by the owner or general contractor.
• Bonding available at 2.5% of total invoiced contract amount.
Contractor Initials Page 1 of 3 L k Subcontractor Initials
ia� K3 DIRECTIONAL
DRILLING INC.
ADDITIONAL COSTS:
A. Additional mobilization and demobilization to the site for any reason will be based on size of the HOD spread per
move each way (see below).
B. This proposal does not include any stand-by time due to delay or suspension of operations for any reason not
created by K3, its subs or its suppliers including, but not limited to, waiting on Owner or General Contractor to
complete any portion of their work or change in the site conditions. Our standby rate for our HOD Spread is
dependent on HOD spread (see below). If K3 loses the hole, and K3 must re -drill, it shall be treated as a new bore
hole and K3 will be paid the contract price for the additional work.
Standby/Remobilization Rates:
[✓j 10K Lb. HOD spread @ $350 per hr. up to five hours, or $2,8CO per shift. Demob/Remob @ $1,800
[ J 20K Lb. HOD spread @ $450 per hr. up to five hours, or $3,600 per shift. Demob/Remob @ $2,500
[ ] 40K Lb. HOD spread @ $775 per hr. up to five hours, or $6,200 per shift. Demob/Remob @ $5,000
[ J 100K Lb. HOD spread @ $1,315 per hr. up to five hours, or $10,500 per shift. Demob/Remob @ $7,500
[) 200k Lb. HOD spread @ $1,725 per hr. up to five hours, or $13,800 per shift. Demob/Remob @ $1D,000
GENERAL CONDITIONS & PRICING ASSUMPTIONS:
A. Prices include drill and pull HOD installation of the product pipe.
B. Post bore profiles.
C. K3 will be responsible for hauling off excess bentonite to contractor supplied dump site. GC is responsible for any
dump fees at the supplied dump site. The dump site must be located with 10 miles of job site. If dump site is more
than 10 miles, then additional charges apply.
D. GC will be responsible for acquiring all drilling water for HOD operations at the project. K3 will transport water if not
available at site.
E. Our price assumes that site conditions are conducive to horizontal directional
drilling and that no obstacles such as caverns, fissures, or any unknown objects such as but not limited to concrete
slabs, rebar, steel pilings and timber, will be encountered underground, or any situation resulting in the loss of
returns or loss of drilling fluids (slurry), or anything resulting in the redesign of the HOD crossing. If such conditions
exist, K3 reserves the right to cease operations and/or renegotiate at an equitable adjustment with the
Owner or General Contractor. If unable to negotiate, our standby rate plus mobilization charges will be enforced
until such time that operations can resume.
F. All efforts will be made to prevent inadvertent returns (IR). If an IR occurs, K3 will assist with clean-up services,
provided the IR occurs in an area accessible by semi -truck. If IR area is inaccessible, clean-up will be billed on a time
and material bases.
G. Pricing is based on 10 hour shifts up to 6 days per week and does not include costs for Inspections.
Contractor Initials Page 2 of 3 b jL Subcontractor Initials
ia K3 DIRECTIONAL
DRILLING INC.
EXCLUSIONS FRON1 HDD SCOPE (to be provided by others at no cost to K3 Directional Drilling, Inc.):
A. GC will ensure ample access to the project right-of-way and HDO drill pad. GC is responsible to protect sidewalk,
curb, and roadway to allow K3 to access drill pad, work area and receiving pit. Any damages by K3 accessing these
areas shall be repaired by GC at no cost to K3.
S. GC Is responsible for the location of utilities or structures not located by the local one call utility locating service.
C. Quote does not include hazardous waste or non -hazardous contaminated soils boring. If these conditions are
discovered, clean-up will be billed on a time and material bases. If operations are stopped the standby rates will
apply.
D. All restoration of K3 work areas is to be completed by the Owner or GC at no cost to K3.
E. Permits, licenses and written permission from governmental authorities and private landowners to perform work.
F. All MOT/safety signage as necessary on water/land as per the D.O.T. and flagmen, if required.
G. GC to provide any noise mitigation requirements.
H. K3 will not be held responsible for costs incurred to the GC or Owner for re -drill operations including, but not limited
to Liquidated Damages.
Terms:
A. Proposal does no- include any, use tax, sales tax, occupational tax, or any other taxes.
B. This quotation is subject to mutually agreeable contract terms and conditions and will not be acknowledged without
this proposal added as an attachment.
C. Should K3 or its subcontractors cause any damages to anything while in the performance of its contract work, the
contractor or the owner shall notify K3 (Lewis Krantz) in writing within 5 calendar days that said damages have
occurred. Should K3 not be notified in 5 calendar days of said damages occurrence, the contractor or the owner shall
assume all liability and costs of repairs. K3 shall then be given 48 hours to proceed with cure of said damages after
being notified in writing.
D. Bore Logs provided upon payment to K3.
E. Quote is good for 30 days and is contingent upon rig availability.
F. No retainage will be held from K3 by the owner or general contractor.
G. Net 30 days. Bills not paid in 30 days can be subject to 1.5 % per month (18% per year) service charge.
GC Village of Tequesta, FL, Utilities Department
�i r:'. By
Pri t Name: Jeremy Allen
Title: Village Manager
Date: 04i26/2023
Witness:
7—
Printed Name: AT.01 c7a e G?-ZoGjeeS
61 ,--7 L i 77,5-r ,01 "cTa r
K3 Directional Drilling, Inc.
By. ���- - ---_
16inWd Name: L c✓4i )ZRrAP' FL,
Title: "✓'Vc'k_
Date: Z. Z-3
Witness:
Printed Name:
Contractor Initials Page 3 of 3 LL- Subcontractor Initials
PUBLIC RECORDS. In accordance with Sec. 119.0701, Florida Statutes, CONTRACTOR must keep
and maintain this Agreement and any other records associated therewith and that are associated
with the performance of the work described in the Proposal or Bid. Upon request from the
Village's custodian of public records, CONTRACTOR must provide the Village with copies of
requested records, or allow such records to be inspected or copied, within a reasonable time in
accordance with access and cost requirements of Chapter 119, Florida Statutes. A CONTRACTOR
who fails to provide the public records to the Village, or fails to make them available for
inspection or copying, within a reasonable time may be subject to attorney's fees and costs
pursuant to Sec. 119.0701, Florida Statutes, and other penalties under Sec. 119.10, Florida
Statutes. Further, CONTRACTOR shall ensure that any exempt or confidential records associated
with this Agreement or associated with the performance of the work described in the Proposal
or Bid are not disclosed except as authorized by law for the duration of the Agreement term, and
following completion of the Agreement if the CONTRACTOR does not transfer the records to the
Village. Finally, upon completion of the Agreement, CONTRACTOR shall transfer, at no cost to
the Village, all public records in possession of the CONTRACTOR, or keep and maintain public
records required by the Village. If the CONTRACTOR transfers all public records to the Village
upon completion of the Agreement, the CONTRACTOR shall destroy any duplicate public records
that are exempt or confidential and exempt from public records disclosure requirements. If the
CONTRACTOR keeps and maintains public records upon completion of the Agreement, the
CONTRACTOR shall meet all applicable requirements for retaining public records. Records that
are stored electronically must be provided to the VILLAGE, upon request from the Village's
custodian of public records, in a format that is compatible with the Village's information
technology systems.
IF CONTRACTOR HAS QUESTIONS REGARDING THE APPLICATION OF CHAPTER
119, FLORIDA STATUTES, TO CONTRACTOR'S DUTY TO PROVIDE PUBLIC RECORDS
RELATING TO THIS AGREEMENT, PLEASE CONTACT THE VILLAGE CLERK, RECORDS
CUSTODIAN FOR THE VILLAGE, AT (561) 768-0440, OR AT
Imcwilliams@teguesta.org, OR AT 345 TEQUESTA DRIVE, TEQUESTA, FLORIDA
33469.
Pursuant to Article XII of the Palm Beach County Charter, the Office of the Inspector General has
jurisdiction to investigate municipal matters, review and audit municipal contracts and other
transactions, and make reports and recommendations to municipal governing bodies based on
such audits, reviews, or investigations. All parties doing business with the Village shall fully
cooperate with the inspector general in the exercise of the inspector general's functions,
authority, and power. The inspector general has the power to take sworn statements, require
the production of records, and to audit, monitor, investigate and inspect the activities of the
Village, as well as contractors and lobbyists of the Village in order to detect, deter, prevent, and
eradicate fraud, waste, mismanagement, misconduct, and abuses.
"The Village of Tequesta strives to be an inclusive environment. As such, it is the Village's policy
to comply with the requirements of Title II of the American with Disabilities Act of 1990 ("ADA")
by ensuring that the Contractor's [ agreement /bid documents and specifications ] are accessible
to individuals with disabilities. To comply with the ADA, the Contractor shall provide a written
statement indicating that all [ agreement /bid documents and specifications], from Contractor,
including files, images, graphics, text, audio, video, and multimedia, shall be provided in a format
that ultimately conforms to the Level AA Success Criteria and Conformance Requirements of the