TEQUESTA LIBRARY PROJECT SCHEDULE
1 ) 01/10/94 : Review PBC Contract Documents and Delete all
Inapplicable Items for Tequesta
2 ) 01/13/94 : Village Council Direction:
a) Oversight Decision
3) 01/17/94 : Public Works Committee:
a) Site Alternatives
4) 01/19/94 : Complete Contract Document Review
- 5) 01/20/94 : Coordinate Contract Document Changes with Palm
Beach County staff and/or Consulting Engineers
6) 02/02/94 : Gee & Jenson draft bid language for
alternative site.
7 ) 02/07/94 : Prepare ad for placement in The Jupiter
Courier, The Stuart News, The Port St. Lucie
News and The Palm Beach Post.
8) 02/09/94 : Fax Ad to Paper
9) 02/11/94: Contract Documents complete for Bidding
10) 02/13/94 : First Ad appears
11) 02/20/94 : Second Ad appears
12 ) 03/08/94 : Pre-Bid Conference
13) 03/29/94 : Bid Opening
14) 03/30/94: Bid Evaluation Commences
15) 04/08/94 : Bid Award Recommendation
16) 04/14/94 : Village Council Consideration of Staff
Recommendation. No Award at this Time.
17 ) 04/15/94 : PBC Staff review of VOT Proposal Commences
18) 04/29/94: PBC Staff Recommendation on Village of
Tequesta Proposal complete for Board of County
Commissioners .
19) 05/03/94 : Board of County Commissioners approval of
Village of Tequesta Proposal
20) 05/04/94 : Commencement of drafting Interlocal Agreement
between Palm Beach County and Village of
Tequesta
21) 05/20/94 : Interlocal Agreement Complete
22) 05/26/94 : Village Council. Approves Interlocal Agreement
23) 05/31/94: Board of County Commissioners approves
Interlocal Agreement
24) 06/09/94 : Village Council Bid Award
25) 06/10/94 : Notice of Award
26) 06/27/94: Contractor Compliance with Notice of Award
27) 07/01/94: Notice to Proceed
28) 07/15/94 : Pre-Construction Conference
29) 08/01/94: Construction Commences
30) 04/01/95 : Construction Complete