MEMORANDUM
TO: Thomas G. Bradford, Village Manager FROM: Thomas C. Hall, Water System Manager 41- -DATE: July 30, 1996
SUBJECT: Roofing Contract Award, Council Agenda Item
On June 27, 1996, RFQ's were sent to four local roofing contractor regarding
repairs to the Annex Building and the Water Treatment Plant. These companies were
Jupiter Roofing & Sheet Metal, Worley Roofing, Inc., Harold Turner Roofing, Inc. and
Tucker Roofing Services. Only two responded and their quotes were as follows:
Company Annex Building Water Plant Total
Worley Roofing $20,165 $ 6,987 $27,152.00
Harold Turner Roofing $22,160 $ 8,300 $30,460.00
In light of the above, we are seeking Village Council approval for contract award
to Worley Roofing in the amount of $27,152.00. Funding will be provided by the Water
Enterprise Fund, Renewal and Replacement Account, Buildings and Renovations having
a budget allocation of $27,200.
Please place this important item on the August 8th Agenda for approval.
TCH/mk
Attachs.
FILE COPY
REQUEST FOR
Village of Tequesta Water Dept. QUOTATION
357 Tequesta Drive
Tequesta Fl. 33469-0474 561-575-6234
The following number must appear on all
quotations and related correspondence.
REQUEST FOR QUOTATION: 04-95/96 REQUEST DATE: June 27, 1996
ADDRESS CORRESPONDENCE TO:
TO: Name Thomas Hall
Jupiter Roofing & Sheet Metal Tequesta Water Department
149 Jupiter St. PO Box 3474
Jupiter, Florida Tequesta Fl. 33469
33458 PHONE 561-575-6234
FAX* 561-575-6239
REQUIREMENTS:
!Reply Required By 5:00pm July 15, 1996 Terms Net 30 Days
Earliest Shipment F.O.B.
.JOB LOCATION 901 N. Old Dixie Ship Via
ITEM QTY DESCRIPTION COMMENT
Furnish labor and materials to do the followino:
1 'Cut out and remove approximately 400 square feet of existing roof and insulation near front
door entry area.
2 Replace damaged insulation with new, hot mopped to concrete. Hot mop one#43 base sheet
and then three fiberglass felts on new area.
3 Remove existing 3x3 eaves drip and install new, hot mop two fiberglass felts on
eave flashing.
4 Prime entire roof surface with roof primer and install one layer of SBS granule surface
modified membrane set in hot asphalt.
5 Provide a Five (5)year guarantee against leaks.
6 Upon issuance of Purchase Order, work will commence within 10 days.
-- 27-Jun-96
- DATE
FILE COPY
REQUEST FOR
Village of Tequesta Water Dept. QUOTATION
357 Tequesta Drive
Tequesta Fl. 33469-0474 561-575-6234
The following number must appear on all
quotations and related correspondence.
REQUEST FOR QUOTATION: 05-95/96 REQUEST DATE: June 27, 1996
ADDRESS CORRESPONDENCE TO:
TO: Name Thomas Hall
Jupiter Roofing & Sheet Metal Tequesta Water Department
149 Jupiter Street PO Box 3474
Jupiter, Florida Tequesta Fl. 33469
33458 PHONE 561-575-6234
FAX# 561-575-6239
REQUIREMENTS:
Reply Required By 5:00pm July 15, 1996 Terms Net 30 Days
Earliest Shipment F.O.B.
JOB LOCATION 357 Tequesta Dr. Ship Via
Annex Building
ITEM QTY DESCRIPTION COMMENT
Furnish tabor and materials to do the following:
1 Remove existing tar and gravel roof and haul away debris for proper disposal.
2 Install a 1.5" I.S.O. insulation over lightweight deck with screws and plates.
3 Hot mop one #43 base sheet over insulation.
4 Install a 1/8"tapered insulation system over base sheet set in hot asphalt.
5 Hot mop one#43 base sheet over the tapered insulation system.
6 Fabricate and install .040 aluminum eaves drip to lock on the existing eave cleat.
7 Hot mop three (3) fiberglass felts over the base sheet and flash in for curbs and vents.
8 Coat entire surface with fibered aluminum roof coat.
9 Provide a five year guarantee against leaks.
NOTE NC unit will be removed from roof by others. Existing roof has little or no positive drainage.
The_new roof must provide positive drainage.
Addition- information may be obtained from the Building Official at 575-6220
Cry(,,
.'- 27-Jun-96
DATE