HomeMy WebLinkAboutDocumentation_Regular_Tab 11G_7/25/1996 MEMORANDUM
TO: Thomas G. Bradford, Village Manager
FROM: Gary Preston, Director of Public Works A•P.
DATE: July 18, 1996
SUBJECT: Village Council Agenda Item for July 25, 1996;
Consideration to Award Dover Ditch Maintenance
Dredging and Related Drainage Improvements to
AKA Services, Inc., in the amount of $88,260.
Please find attached, the following support documents for Councilmembers' review for
the above referenced agenda item:
• A letter dated July 16, 1996 from Allan F. Oslund, Gee & Jenson Project
Manager, recommending contract award to AKA Services, Inc.
• Bid tabulation sheet
• Contractor's Unit Price Bid Schedule
The Village Council allocated $110,000 in the FY 1996 Capital Improvement Budget
for Dover Ditch Improvements. This amount included $11,000 for engineering
services and $99,000 for dredging, bank stabilization, permits and related drainage
work.
Please place this item on the July 25, 1996 Village Council Meeting Agenda for
Councilmembers' consideration.
GP/mk
Attachs.
GEE &JENSON
Engineers-Architects-Planners.Inc
One Harvard Circle
West Palm Beach.FL 33409
Telephone(407)683-3301
July 16, 1996 Fax(407)686-7446
Gary Preston
Village Tequesta
P.O. Box 3273
Tequesta, FL 33469
Re: Dover Ditch Maintenance Dredging.
Recommendation to Award Contract •
Dear Gary: . .
Please find enclosed one copy of Exhibit "A" (Bid Tabulation) for each of the
bidders to the above referenced project. The apparent low bidder was AKA
Services, Inc., with a lump sum bid of$76,750.
We have reviewed and checked the bids as submitted and would recommend
awarding this contract to AKA Services, Inc. for the above referenced amount.
In addition to this award, we would recommend a 15% contingency be added to
cover the cost for unknown utility services and replacement of the storm pipe
crossing Seabrook road at Dover Ditch, this would bring the total contract price
to $88,260.
If you have any questions regarding this matter or need additional information,
please do not hesitate to call.
Very truly yours
Allan F. Oslund, PLS
Project Manager
AFO/tic
96004.03
cc Tom Bradford
Mitch Thomas
D:\AFO\PRESTON2.DOC
BID TABULATION
GEE&JENSON Project Name:Village of Tequesta Bid Date/Time:July 16,1996/2:00 PM Owner: Village of Tequesta.
UNQNEU"s•A"artICT$- Dover Ditch
"uwH11"" Project No:96-004.02 Conducted By:Gee&Jenson Owner No.:
Opening Location:Tequesta Village Proj.Arch/Eng:
Hall
z:i�%rICNY�i`%`•#iEi�>i�i<r F:i'ift:E::::: '•>E` E: ';'C3'�` '»i>3;•11f1r3ttJ 11 /1
r
2;';isisi'.;i:::::: ::::::':::::::r :::£::::>::::::i:::;::.';:i `:%":;>: : ;:i:::: :::::::::';:i:::::::: $?:::::::: :::::::::::'i::i::;;;:�i:: :;:;: ;: ;:%;: $;: :;;:;; ;;•r„>:::::;:;;.:;:;::;::;:::;:i::::::::: :;:<:iS';••:;.>:::.»>::.:::>:::`;:::::.>:,::.::.::.;::;:::<;;::;`{::: ;:i;::;:;i;::;:::;:;;.;::;::;::;::i::ii:::::;::::::::::i::i::i::i::i:::;::�:�
<:>>;<:»>:�>'�>::`::;:�>:::::
::{•i:;::i;•:;•ii�}>:.:;.>:.>:.:::;.::.>:.:>:<•>:•::.::.>:.:>::.::.>:..�ii:.i:.iiii.iiii:G•i;•::.;.:::•:::•:�:.:�:.>:.:;.>:.:::•>:.::.;:<:::>:•i:.i:.i:.:{-i:;•:;•i:L;•i;•:i::::C;:.>:.>::•>:.i;.i;•ii:•::>:.>:.c•;>::>:.::ry>:.::.::.>>:.::'
AKA Construction $76,750.00 X X X X X
Russell Trucking $96,150.00 X X X X X
Construction Technology $104,940.00 X X X X X
Rosso Paving $134,740.50 X X X X X
Premier Dredge&Marine $138,166.00 X X X X X
EXHIBIT A
DOVER DITCH MAINTENANCE DREDGING
VILLAGE OF TEQUESTA
UNIT PRICE BID SCHEDULE
Item Estimated Estimated
No. Description Quantity Unit Unit Price Amount
1 . Mobilization 1 LS 3, 000 . on
3.000 .oc
2. Clearing & Grubbing 2.4 AC 2. SOO . oo (1,000 . 00
3. Excavation . 4,200 CY - LS 3. 25 13.& so. oo
4. Embankment 1 ,250 CY LS 2 2. 500. 00
5. 4" Coquina base 3,950 SY 3 1
6. Sod 9,500 SY Z . 30 Z� ,�.Sv, ao '
7. Floating Turbidity Barrier 100 LF 15 1 . oo. oo
8. Mangrove staking 100 LF Z zoa. ov
9. 8" Filter Point Fabriform 225 SY Z 161200. 00'i
TOTAL ESTIMATED AMOUNT $ ?(o , 750. ov
NOTE: CONTRACTOR SHALL PROVIDE CONSTRUCTION SURVEYING.
PAY ITEM NOTES:
1. Embankment shall include final grading for preparation of sod.•
2. Contractor shall use existing sod type within the 15 ft. maintenance area and
outside of the Dover Ditch right-of-way. In areas where sod does not exist,
Bahia sod shall be used. Ditch side slopes (2:1) shall be Bahia sod and shall be
in accordance with Section 575 of the F.D.O.T. Specifications.
9600402 BFU-4
l`
EXHIBIT A
/ . DOVER DITCH MAINTENANCE DREDGING
VILLAGE OF TEQUESTA
UNIT PRICE BID SCHEDULE
Item Estimated Estimated
No. Description Quantity Unit Unit Price __A—munt
1 . Mobilization 1 LS 7, 900,ce 7 gc .oO
2. Clearing & Grubbing 2.4 AC /o c7,00 247 cxx�,no
3. Excavation " 4,200 CY LS
3, SO /4 7c0;co
4. Embankment 1 ,250 CY LS ,Soo 6 2S0,06
5. 4" Coquina base 3,950 SY 67, 00 Z3, 700.op
6. Sod
9,500 SY /, 70 /6., !5 O,00
7. Floating Turbidity Barrier 100 LF /O,ov
/, O0U'cc
8. Mangrove staking 100 LF 2 . CO 2CZo,0o
9. 8" Filter Point Fabriform 225 SY /O, 00 2 25-0.00
TOTAL ESTIMATED AMOUNT $ WJ /3 0. CO
NOTE: CONTRACTOR SHALL PROVIDE CONSTRUCTION SURVEYING.
PAY ITEM NOTES:
1. Embankment shall include final grading for preparation of sod.
2. Contractor shall use existing sod type within the 15 ft. maintenance area and
outside of the Dover Ditch right-of-way. In areas where sod does not exist,
Bahia sod shall be used. Ditch side slopes (2:1) shall be Bahia sod and shall be
•
in accordance with Section 575 of the F.D.O.T. Specifications.
9600402 BFU-4
•
•
EXHIBIT A
DOVER DITCH MAINTENANCE DREDGING
• VILLAGE OF TEQUESTA •
UNIT PRICE BID SCHEDULE
Item Estimated Estimated.
No. Description Quantity Unit Unit Price Amount
1 . Mobilization 1 LS 1.5,600.00 15,600.00 —
2. Clearing & Grubbing 2.4 AC 4,500.00 10,800.00 -
3. Excavation 4,200 CY - LS 28,400.00 28,400.00
4. Embankment 1 ,250 CY LS . 4,000.00 4,000.00
5. 4" Coquina base 3,950 SY 3.20 12,640.00
6. Sod 9,500 SY. 2.50 23,750.00
7. Floating Turbidity Barrier 100 LF 8.00 800.00
8. Mangrove staking 100 LF 4.00 400.00
9. 8" Filter Point Fabriform 225 SY 38.00 8,550.00•
TOTAL ESTIMATED AMOUNT $ 104,940.00
One hundred four thousand, nine hundred, forty and 00/100 DOLLARS
NOTE: CONTRACTOR SHALL PROVIDE CONSTRUCTION SURVEYING.
PAY ITEM NOTES:
1. Embankment shall include final grading for preparation of sod.
2. Contractor shall use existing sod type within the 15 ft. maintenance area and
outside of the Dover Ditch right-of-way. In areas where sod does not exist,
Bahia sod shall be used. Ditch side slopes (2:1) shall be Bahia sod and shall be
in accordance with Section 575 of the F.D.O.T. Specifications.
9600402 BFU-4
•
EXHIBIT A
DOVER DITCH MAINTENANCE DREDGING
VILLAGE OF TEQUESTA
UNIT PRICE BID SCHEDULE
Item
Estimated
�_
Des riation Estimated
àjjjj
illUnit Pri
1 • Mobilization ---c Amoun
2. CI 11111111111111131611111a s 4 a so . Oo
earn• & Grubbin• I
2.4 AC , 0 S-0.00
3. Excavation Sy Loo,Od I
4,200 CY
4. Embankment 20 322,00
1,250 CY IEIII
5. 4" Coquina base IIIIIII-' y SyO.On�
3,950 MI' ki.SO • n l?
6. Sod SQ O I.
9,500 Mill. 2.S0 - 23 nSO.o0
111111 Floating Turbidity Barrier
8. Mangrove100 1E11� 3.00 4 300:00
staking 100 1E11
3.60 a 360.00
9. 8" Filter Point Fabriform
1111M111111 3 ,to 4' 9,89il So
TOTAL ESTIMATED AMOUNT
$ 13y,r)y0 .
NOTE: CONTRACTOR SHALL PROVIDE CONSTRUCTION SURVEYING.
PAY ITEM NOTES:
1. Embankment shall include final grading for preparation of sod.
2. Contractor shall use existing sod type within the 15 ft. maintenance area and
outside of the Dover Ditch right-of-way. In areas where sod does not exist,
Bahia sod shall be used. Ditch side slopes (2:1) shall be Bahia sod and shall be
in accordance with Section 575 of the F.D.O.T. Specifications.
•
9600402
BFU-4
•
EXHIBIT A
DOVER DITCH MAINTENANCE DREDGING
VILLAGE OF TEQUESTA
UNIT PRICE BID SCHEDULE
Item Estimated Estimated
tt No. Description Quantity Unit Unit Price Amount
1 . Mobilization 1 LS 141800.c° 14,Sob.oc
2. Clearing & Grubbing 2.4 AC 1 '�aooA 3,a,ggo,
3. Excavation 4,200 CY LS N � oao,oc
4. Embankment 1,250 CY LS N f A �i,glab.oc
5. 4" Coquina base 3,950 SY 6. 5 o 025, G7S.44
6. Sod 9,500 SY I .SS 14rIa5,cc
7. Floating Turbidity Barrier 100 LF 6, oo (000.oc
8. Mangrove staking 100 LF 4.0 0 40 o,oc
9. 8" Filter Point Fabriform 225 SY 7�.0o I bao.o.oc
TOTAL ESTIMATED AMOUNT . . Q9, 1 G6.4a
one hu.nc�re.ci �✓'+y �eic�ll't -f-�o��Sc�rlor�� Inu‘v S,rc4"1 - S j0c,ll.a2,
NOTE: CONTRACTOR SHALL PROVIDE CONSTRUCTION SURVEYING.
PAY ITEM NOTES:
1. Embankment shall include final grading for preparation of sod.
2. Contractor shall use existing sod type within the 15 ft. maintenance area and
outside of the Dover Ditch right-of-way. In areas where sod does not exist,
Bahia sod shall be used. Ditch side slopes (2:1) shall be Bahia sod and shall be
in accordance with Section 575 of the F.D.O.T. Specifications.
•
9600402 BFU-4