HomeMy WebLinkAboutDocumentation_Regular_Tab 13C_4/13/2000 ati
VILLAGE OF TEQUESTA IIIE C
Post Office Box 3273 • 250 Tequesta Drive • Suite 300
4 +I Tequesta, Florida 33469-0273 • (561) 575-6200
4tkeFax: (561) 575-6203
A Co
VILLAGE OF TEQUESTA
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
FEBRUARY 24, 2000
I. CALL TO ORDER AND ROLL CALL
The Tequesta Village Council held a special meeting at the
Village Hall, 357 Tequesta Drive, Tequesta, Florida, on
Thursday, February 24, 2000. The meeting was called to
order at 7: 02 P.M. by Mayor Carl C. Hansen. A roll call
was taken by Betty Laur, Recording Secretary.
Councilmembers present were: Mayor Carl C. Hansen, Vice
Mayor Elizabeth A. Schauer, Councilmember Joseph N.
Capretta, and Councilmember Sharon Walker. Also in
attendance on behalf of the Village were: Village Manager
Thomas G. Bradford, Village Clerk Joann Manganiello, and
Acting Utility Director Tom Jensen, P.E. Councilmember
Basil Dalack was absent from the meeting.
Village Manager Bradford explained that in order to bring
the Village Councilmembers together, under Florida law a
Village Council meeting had to be called. The Village
Manager commented that following the presentation everyone
would be able to ask questions.
II . APPROVAL OF AGENDA
Vice Mayor Schauer made a motion to approve the Agenda as
submitted. Councilmember Walker seconded the motion. The
vote on the motion was:
Carl C. Hansen - for
Elizabeth A. Schauer - for
Joseph N. Capretta - for
Sharon Walker - for
Recycled Paper
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 2
The motion was therefore passed and adopted and the Agenda
was approved as submitted.
III. COMMUNICATION FROM CITIZENS
There were no communications from citizens .
IV. PRESENTATION AND OVERVIEW OF ENCON TEQUESTA PENINSULA
SEWERING PROJECT, PHASE I, INCLUDING QUESTION & ANSWER
SESSION
Village Manager Bradford introduced those present at the
head table: Tom Jensen, P.E. , Acting Utility Director and
an associate with Reese Macon & Associates, Inc. ; Paul
Brienza, P.E. , Director of Engineering for the Loxahatchee
River District; Jerry David, Shalloway, Foy, Rayman &
Newell, Inc. , the consulting engineers chosen by ENCON to
design the sewer system and chosen by Tequesta to design
the storm drainage improvements.
A slide presentation was given by Jerry David, covering the
infrastructure utility improvements of water, sewer, and
storm drainage within the Country Club on the Tequesta
peninsula. Approximately 4 months, February to June, 2000
was the estimated time for construction of Phase I for
North Fairway East and North Fairway West, where storm
drainage water and sewer lines were proposed to be
installed on both streets . 6-9 months, June 2000 to
January 2001, were estimated to complete construction on
West Fairview, East Fairview, Club Place, the south portion
of Golf View Drive, El Portal, the south portion of River
Drive, and Yacht Club Place et al. Mr. David reviewed the
typical excavation process for sewer installation, provided
a typical engineering drawing of what the contractor had
in the field in the Tequesta peninsula and explained that
everyone would be contacted by field representatives or the
contractor to determine the best location for their
laterals, showed proximity of water and sewer in Tequesta
Country Club, presented a typical drainage plan with
swales, a typical cross section drawing, roadway
improvements for Fairway East and Fairway West, and an
engineering drawing of 30" (HDPE) high density polyethelene
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 3
storm drain lines between homes . Mr. David explained that
down time without water should only be 1 to 1-1/2 hours
when connection to the new sewer line was done . There
would be no additional charge if a property required more
than one lateral, because the connection would involve one
single family residence . Mr. David described how swales
worked. Abandonment of a septic tank as required by the
Health Department was described as having the septic tank
pumped out, having the bottom broken up, and the tank
filled with sand.
Mr. David reviewed the Village of Tequesta' s infrastructure
utility improvement for the Tequesta peninsula, Phase I.
Construction of gravity sewers for sewage collection to be
installed by ENCON would include the following activities:
1. Dewatering operation 24 hours a day
2 . Excavation
3 . 8" diameter PVC pipe
4 . 4 ' diameter manholes at 350 ' ± - centers in street
5. 4" diameter laterals to r/w line
6. Cleanout at r/w line
7 . Roadway restored to first lift of asphalt
Storm drainage under the Village of Tequesta' s
infrastructure utility improvement program for Tequesta
peninsula - Phase I, would involve the following items :
Storm Drainage:
1 . Dewatering operation as required
2 . Excavation
3 . 18" - 42" diameter pipe
4 . Catch basins
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 4
5. Driveways and swales
6. Outfalls to lakes
Water Distribution System:
1. 6" - 8" - 10" diameter PVC pipe approximately 3'-5 '
from edge of pavement
2 . Gate valves
3. Fire hydrants
4 . Service lines
The sequence of operation for Phase I of the Village' s
infrastructure utility improvement program starting at the
end of February, 2000 was described:
1. Work has started on Fairway North East and West.
2 . Four (4) months later work will begin on the
southern end of the project:
(1) River Drive (South of Club Place)
(2) Golfview Drive (South of Club Place)
(3) Pine Tree Place
(4) Yacht Club Place
(5) El Portal Drive
(6) Fairview West
(7) Fairview East
(8) Palmetto Way
(9) Fair Place
3 . The sewer contractor starts construction - The
contractor completes his work and finishes with one
lift of asphalt.
4 . After sewer is installed the water and storm
drainage contractor will begin by installing the
drainage system. This work will begin in North
Fairway East and West. Once that is complete he
will start replacing the existing water main,
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 5
service lines, and hydrants . Once the water line
is cleared by the Health Department the contractor
will reconnect the water services to the existing
meters .
5. After all the utilities have been checked and
certified the contractor will place a second or
final lift of asphalt. (Approximately one week)
6. Total Phase I project should be completed within 8
months from date of commencement .
Phase II was announced to commence soon after, and to
consist of water, sewer, and storm improvements in the
balance of the Tequesta Country Club.
Mr. David called for questions from the audience.
A member of the audience pointed out that under this
proposal the new road surface provided by ENCON at the
entrances would be torn up with construction equipment
coming in to do the work further west, and suggested that
the final surface coat of asphalt be applied after all the
work was finished, which Mr. David stated was a good point
worth considering, and that he believed it could be worked
out.
Another question was during phase 2 how testing and
monitoring of possible salt water intrusion was planned
for, as well as ground settling. Mr. David responded there
was now a monitoring well located in Bermuda Terrace and
another had just been installed. In one of these wells,
which went down 100 ' , only clean water had been found.
Chlorides were negligible. Mr. David reported that in the
other well, chlorides had been 15, 000 milligrams per liter
at 100' , saltwater at 65' , with clean water down to 65 ' .
Since dewatering would only go down 13 ' - 15' , only clean
water would be involved, and all hydrological studies that
had been done showed there would be negligible impact of
salt water intrusion. Mr. David explained the location of
the monitoring well and lift stations, and how water would
flow. Mr. Amy questioned whether a lift station would be
installed at a certain location, to which Mr. David
responded if one was required by South Florida Water
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 6
Management District it would be installed, but SFWMD might
instead required three shallow monitoring wells. Mr. Amy
explained that his question had been asked with the intent
of relieving concerns of residents living along the river
regarding salt water intrusion. Village Manager Bradford
clarified for those who could not hear that Mr. Amy was a
retired hydrologic geologist who had been suggesting that
monitoring wells to record the amount of chlorides or salt
in the water to address the issue of salt water intrusion
also be installed northward along River Drive to make sure
that area was monitored as well. Another question was that
since homes along River Drive were large, what would happen
if homes were damaged as a result of the ground settling.
Mr. David responded that the contractor would warranty his
work for a year and that the whole project had been
videoed. Mr. David commented a house had never been
damaged during sewer installations by his company, and that
would have to be addressed on an individual basis, but it
was not expected to happen.
Pert Town stated she lived near Bermuda Terrace in Country
Club Point on Starboard, and asked whether that area would
be sewered with Bermuda Terrace, to which Mr. David
responded affirmatively and explained that was in this
phase of the work.
A member of the audience pointed out that Fairview East and
West were mislabeled on a slide. A member of the audience
asked where lift stations were located and whether if
residents were gone over the summer the project could
proceed without their supervision. Mr. David responded no
lift stations were planned to be added in Phase I.
Locations of existing lift stations were pointed out on one
of the slides . Village Manager Bradford clarified that
the lift station locations were : where Point Drive
intersected River Drive at its northernmost intersection;
at the southeast corner of the intersection at Golfview
Drive and Fairway North; and just off of and adjacent to
Country Club Drive right next to and north of Mr. Joe
Hall' s property which abuts the maintenance shed of the
Tequesta Country Club.
A member of the audience questioned where residents could
find the engineering drawings for the storm drainage
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 7
system. Mr. Bradford responded that the drawings would be
kept at the Utilities Director' s office at 136 Bridge Road.
A woman in the audience commented a new paver driveway had
been installed on her property two years ago and questioned
what would happen to it, to which Mr. David responded that
after the meeting Tom Jensen could meet with her to show
her the location of her property on the plans and how it
would be affected; but in general, some driveways might be
affected and some might not; and the contractor was
required to replace any affected driveways equal to or in
better condition than they had been. Village Manager
Bradford commented that on any private property affected
in both the ENCON and Village contracts, the contractor was
required to replace anything damaged and that replacement
was to be equal to or better than existing. Village
Manager Bradford explained where private property was
located and where right-of-way was located. Mr. Bradford
explained that items located in right-of-ways such as
irrigation systems, mail boxes, lamp posts, etc. , were all
addressed in the plans; however, if a resident had minor
hedges or other landscaping they needed to move that before
the work began. Village Manager Bradford explained that
what would happed to driveways was different with different
properties and residents would actually have to view the
plans to find out whether their driveways were affected.
In some cases driveways would be cut to place lines
underneath, and in some cases jack and bore equipment would
be used to tunnel under driveways, which would be a
decision made on-site by the contractor when viewing
existing conditions .
A resident commented he had installed an $18, 000 french
drain and asked if it would be affected. The response was
that all existing conditions for the project had been
videoed, and both contractors were required to restore to
equal or better condition whether on private property or
in the right-of-way. Another resident suggested that the
construction people would be having a meeting to discuss
what they were going to do in each area, and perhaps
residents could attend; to which Mr. David responded daily
meetings were held with ENCON to take care of any
complaints, that homeowners would be contacted with regard
to location of the laterals, that he had no problems if
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 8
homeowners wanted to attend the meetings, and after the
meeting could give the resident the field contact' s phone
number.
Pert Town asked whether ENCON could keep their web site
updated representative Paul Brienza responded the next
week' s schedule was already on the web site and plans were
to provide updates every Wednesday or Thursday.
It was clarified for another homeowner it was the
responsibility of the homeowner to have the septic tank
broken up. Mr. Brienza stated that was a Health Department
regulation.
The web site address for ENCON was announced:
www.loxahatcheeriver.orq.
A resident asked what would happen to large trees in the
right-of-way. Village Manager Bradford responded that the
sewer system ran down the middle of the road, off of which
laterals would run from the sewer lines to the homes . The
water line would be installed 3'-5' off the pavement. Each
homeowner would be consulted as to the best location for
the laterals, so there would be possibly be an opportunity
to dodge trees; however, in some cases that might not be
possible. Mr. Bradford explained that the whole project
had been planned with best efforts not to affect trees if
at all possible.
A resident questioned when homeowners would have access in
and out during the construction. Mr. David responded that
there would be no access during the day when the contractor
was working in front of a home but that the contractor was
supposed to assure access after his work for the day was
completed. Under emergency conditions the contractor was
to close down and allow emergency vehicles to go through.
Village Manager Bradford explained that Tequesta' s
ordinance allowed construction from 7 a.m. to 6 p.m. Monday
through Saturday. Village Manager Bradford recommended
each resident establish a line of communication with the
field supervisor to find out which day the work would be
in front of their home and when they would or would not
have access .
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 9
A resident questioned which side of the street water mains
would be installed, to which Mr. David responded that plans
could be viewed following the meeting.
A resident questioned whether the construction company or
the Village could negotiate with a specific company for a
good price for the residents to have their septic tanks
pumped and abandoned. Paul Brienza responded yes, and that
was a definite advantage for residents to group together
to find a company both to take care of the septic tanks and
a plumber, so that they could get a better price.
Councilmember Capretta commented his sewer had already been
done and had been part of 24 sewers installed earlier which
had taken 4-5 months . Mr. Capretta explained where this was
located in case anyone wanted to drive by. Mr. Capretta
expressed his opinion that it had helped to talk with the
foreman who helped residents get in and out, and to show
him where the laterals were desired, and the whole job had
worked out better than he had expected. Councilmember
Capretta commented that the residents would have to get a
plumber who then would get a company to take care of the
septic tank. Mr. Capretta explained that when the project
was completed there would be a white stand pipe in the
front yard. A one-year period to hook up would be given
by ENCON, and notice of this would be sent out to residents
by ENCON after Health Department approval had been
obtained. A list of acceptable plumbers would also be
included. Mr. Capretta reported he had consulted Jupiter
Plumbing, but that they did not want to participate;
another plumber had quoted $4, 100 to do the hookup, while
another had quoted $2, 406 to a group of residents;
therefore, Mr. Capretta recommended a half dozen or more
residents band together in order to get a good price . A
resident asked whether the contractor or Village should do
the negotiations, to which Councilmember Capretta responded
ENCON did not want to do it. Mrs . Hansen reported that the
HOA was currently looking into that. Sandy McKee announced
that three liaison people had been appointed and their
names and phone numbers would be listed in the next HOA
newsletter.
A woman asked if a monitoring well was needed on the north
end, to which Mr. Bradford responded no. The same resident
asked when access would be available on a regular basis to
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 10
Country Club Drive from Fairway North. Mr. David responded
specifications required at least one access must be open
for everybody and he expected that access to be open early
next week.
A new resident of one month who lived at the corner of
North Place and Fairway North commented her house had
vibrated the previous day during construction work and
asked what provisions were being made for that and what
would happen to the trees in her right-of-way, and how her
swale would be finished off. Mr. David advised the
resident to contact Jerry Woodburn, field representative
from Shalloway, or the superintendent, Mike with Kampius,
who would both be available during the day at the jobsite
regarding the vibration. Mr. David responded regarding the
trees and the swale that this was an area with bad drainage
and swales were needed to alleviate the drainage problem
and best efforts would be made not to disturb trees.
Village Manager Bradford commented the Village had been
able to go around trees in swales in the past . Another
resident commented the water line and swale would both be
on his property and he was concerned with his trees. Mr.
Bradford commented trees might be relocated if necessary,
but the contractor would make that decision and would do
his best to avoid the trees in the right-of-way.
A resident questioned whether ENCON had limited the
selection of contractors for the project. Mr. David
responded that the contractors for ENCON and for the
Village had been selected by competitive bid and the lowest
bidder got the job. The resident clarified he was
referring to the list of contractors to do hookups. Mr.
David stated that was a recommended list. Village Manager
Bradford explained there had been a long lawsuit between
the Village and ENCON over the sewers, which had ended in
mediation and a settlement agreement. The settlement
agreement contained provision that ENCON would be required
to provide a list of pre-certified plumbing contractors and
would be doing that; however, a resident was not required
to use a contractor listed and if qualified could do the
work themselves .
A resident commented on the costs to residents and wanted
to know what ENCON was contributing. Village Manager
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 11
Bradford explained that ENCON was paying 10% of the costs .
Paul Brienza commented this should be addressed by the
ENCON governing board. Mr. David commented ENCON would be
sending out something in the mail listing costs . Village
Manager Bradford explained ENCON was doing other things-
that there was a cap on the assessment, and that financing
was offered over 20 years with an interest rate that could
not exceed 5.75% for that work in this Phase I.
A resident questioned whether the diesel powered pumps used
for dewatering would be moved as the trenches were dug, to
which Mr. David responded they would move down the road as
work progressed.
Vi Lamanden commented that jack and bore meant the sewer
pipe would be capped and put under the driveway, that she
had had experience with four sewer projects in New Jersey,
and there was a very good chance residents could save items
they did not want to lose. Mrs. Lamanden questioned
whether the flow of the sewers was to the northeast, to
which Mr. David responded by describing the flow and
referring to slide number two. Mrs . Lamanden inquired if
there was a treatment plant for sewage and was told it was
on Jupiter Park Drive.
A resident commented it was hard to determine how much this
would cost. Mr. David explained that ENCON was sending out
a list of costs, but that the final cost was not known
until all construction was completed. Mr. David advised
the resident to address any specific concerns to Paul
Brienza by phoning him at his office number 747-5700.
Mr. David was asked to explain when sewer and water would
go into Bermuda Terrace. Mr. David pointed out on a map
where work would begin and how it would proceed. Mr. David
estimated 1-1/2 months to put in the sewer and after that
the stormwater and water improvements would be made. Paul
Brienza commented that the sewer work would start at
Windward and Country Club Drive. The location of the lift
station was pointed out between Gulfstream Court and
Pinetree.
A resident questioned what impact and restrictions on water
pumps in yards was anticipated during construction. Mr.
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 12
David responded that an analysis of water wells indicated
there was 100 ' of clean water, so no detrimental effect was
anticipated. The resident wanted to know if there would
be a requirement to hook up the irrigation system to
something else and whether there would be extra hookup
fees, to which Mr. David responded no and that there would
be no extra fees involved.
A resident reported she had a septic tank and a dry well
and questioned whether the dry well would have to be
connected to the sewer, to which Paul Brienza responded the
Health Department did not waive that so it would have to
be connected also.
A man asked whether driveways would be replaced on Fairway
East and Fairway West, to which Tom Jensen responded in
some areas driveways would be replaced from right-of-way
to edge of pavement.
A resident asked whether it was possible to get underground
utilities installed at the time of construction, to which
Village Manager Bradford responded that a sample survey had
been done by the Tequesta Country Club Community
Association asking residents whether they would be
interested in underground utilities, sidewalks, and
streetlights. 67% had said no to underground utilities,
and to sidewalks, but the majority had been in favor of
streetlights . Mr. Bradford expressed his opinion that the
reason people had rejected the proposal was that it would
cost $8, 000 per home based upon an FPL quote.
A resident questioned whether when the project was complete
there would be any way the people could know the river was
cleared up and that the project had been good. Village
Manager Bradford responded that the governing board of
ENCON would have to be accountable to the answer since
Tequesta had argued in court for years there would be no
negligible change. ENCON had not said there would be a
change, but that their position was that any effort to
reduce known pollutants would be beneficial to the river,
and they did ongoing monitoring with quarterly or monthly
reports which could be obtained to get before and after
pollution figures .
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 13
Sandy McKee commented that the literature sent out to
homeowners stated the contractor was not required to
replace specimen landscape materials in the right-of-way,
and requested clarification regarding such materials, which
were usually described by landscapers as expensive or
exotic plants . Paul Brienza commented that a resident
should make an effort to remove any plants they wanted to
keep, although the contractor would make an effort to work
around such plants and there would be some areas that this
would not be a problem. Tom Jensen commented that in the
Village contract with Ric-Man nothing required him to
replace such plants in drainage easements between houses;
therefore, they should be moved at the homeowner' s expense.
Village Manager Bradford clarified that in the right-of-way
the contractors were required to replace equal to or better
than existing.
A resident questioned how to coordinate ahead of time
regarding a large tree in his right-of-way since he would
be out of town during construction. Mr. Jensen responded
if it was a tree the resident did not want to keep, the
contractor would remove it.
A resident questioned whether the contractor would take
into consideration if a water connection was now at the
side of a house instead of in front, to which Mr. David
responded yes, that the resident should get together with
the contractor to decide the most advantageous place for
the sewer line.
A resident questioned whether shrubs would be saved on
right-of-ways next to properties. Tom Jensen responded
some plants could not be replanted, but that the contractor
would work with the resident every way possible to save his
plants.
A woman commented she had a septic tank in back of the
house, one on the north side, and the meter on the south
side, and questioned how that would impact the
installation, to which Paul Brienza responded that would
be a longer run, that the contractor needed to make sure
the lateral was at the right level, and that two service
lines might be required.
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 14
A woman commented she lived near the end of Yacht Club
Place and would not be in residence June through September.
Mr. David provided one of his cards and asked that she
call.
A resident stated sewer, water, and swale were all required
at his house and questioned whether the work would be
coordinated or whether his property would be torn up for
four months . Mr. David explained that two contractors
could not work in the same area at the same time, and the
sequence of work had been agreed upon by all parties. Mr.
David referred to slide 1 again, and indicated that the
sewer contractor would do the dewatering and installation
and then put down the first lift of asphalt; then the
second contractor would come in after the sewer contractor
was out and the sewer certified. The same second
contractor would install the swales and the second asphalt
surface. Mr. David explained that sewers required more
dewatering than was required for the water main.
A resident questioned whether anyone had called the School
Board regarding school busses that came twice each day.
Mr. David reported this had been scheduled for discussion
at the preconstruction meeting, but the School Board did
not show up, so they would be contacted.
VI Lamanden questioned whether billing would be done at
completion. Paul Brienza responded residents would have
an option to pay in full or over 20 years . Mrs. Lamanden
requested another option of paying in equal installments
over 5 years . Mr. Brienza promised to check on that, and
explained that it was now set up to either pay in full or
over 20 years . Mayor Hansen commented that the mediation
agreement had stated there was no prepayment penalty so the
remainder could be paid at any time during the 20 years.
A resident questioned whether on properties with two septic
tanks, where it was difficult to run the laterals, was it
possible to tap into a neighbor' s lateral. Mr. David
responded that a double lateral or two singles could be
used. Paul Brienza commented that two could be twined
together.
A resident questioned how to find out where a septic was
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 15
located. Paul Brienza responded he would be glad to send
someone out to locate the tank, and advised the resident
to call his office. Village Manager Bradford announced the
phone number for Mr. Brienza was 747-5700 .
Vincent Amy commented it appeared he would not be in town
when construction started at his house, and questioned how
to make provision for the location of the lateral line.
Paul Brienza advised that should be done now so it would
be in the record. Mr. Amy expressed concern where to park
vehicles if there was not access to homes in the evening.
Mr. David responded every possible effort would be made to
allow access every night during construction. Mayor Hansen
reported he had asked the ENCON supervisor how many days
he would not have access to his home and the reply had been
in most cases only one day, to two days maximum. A
resident questioned whether the police department could
make provisions for residents to park at the entrance.
Village Manager Bradford advised residents to park as close
to their houses as possible, which was verified by Paul
Brienza. Mr. Brienza this contractor could work on one
side of the road and let residents by to get to their
houses on the other side of the road.
Mr. Amy questioned whether the $500 subsidy for a home
built before 1981 was factored into the regional facility
connection charge cost on the table of summary of costs
provided by ENCON. Mr. Brienza responded the $500 was
factored in. Mr. Amy questioned when he would receive a
bill from ENCON for the connection fee, which Mr. Brienza
explained would be paid at the time the resident connected,
and the assessment would come later. Mr. Amy quoted a
footnote in the summary of costs and stated it was his
understanding sewer costs were capped at $8, 000 which Mr.
Brienza verified. Mr. Amy questioned whether the cost of
litigation costs be included in the assessment. Mr.
Brienza responded that he believed the litigation costs
would be included but that was a decision for the Board of
ENCON. Mr. Amy stated residents and taxpayers of the area
should know how their money was spent and requested a
breakdown of the construction costs, litigation costs, etc.
used to make up the assessment. Mr. Brienza agreed.
Village Manager Bradford stated when it was time to do the
formal assessment there would be an ad in the paper, and
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 16
a public hearing, and public records. ENCON then would
make available all the different costs so everyone could
see exactly what they were being assessed by ENCON. The
Village Manager explained that there would be no assessment
to the residents for the improvements being done by the
Village since those would be paid for out of the Capital
budget. Mr. Bradford explained what would be covered in
Phase I, and what would be covered in Phase II. Eight
months was estimated to complete Phase I. Phase II could
begin right after that but it would also contain
improvements of sewer, water, and drainage, which had all
not yet been designed or permitted. A resident commented
he understood the west end of River Drive might not be
suitable for a gravity sewer system, to which Mr. David
responded nothing had been determined at this point.
A resident commented he had heard Phase I would be
completed in five months. Mr. David explained that
sewering was a 6-month project, but the water improvements
were being done as soon as it was finished, which was why
eight months was allotted. The resident commented that
Phase II sewering would not start until Ric-Man was out,
to which Mr. David replied that was probably a correct
statement, but he was very uneasy about answering that kind
of question since none of that work had yet been
coordinated. Pert Town questioned why in Phase I only one-
half of Fairway North would be done, to which Mr. David
responded that the sewer split at that location. Ms. Town
questioned whether the other half would be started in
October, to which Mr. David responded he did not know.
Village Manager Bradford explained portions still had to
be designed and permitted, and the biggest issue for the
remaining area was the impact of dewatering of salt water
intrusion. Mr. Bradford commented that the agreement the
Village had with ENCON stated gravity sewers were the
preferred method of sewering throughout Tequesta; however,
it was recognized that in certain circumstances they may
not be able to install gravity sewers . Tequesta' s job was
to be a watchdog to see that ENCON did their best to
provide gravity sewers, but if they could not they might
have to decide to go to low pressure .
A resident questioned whether any arrangements had been
made with the post office because most mail boxes were in
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24, 2000
PAGE 17
the swale area. Mr. David explained that a representative
from the post office had attended the post construction
meeting and everything possible would be done to assure no
interruptions in service. Paul Brienza commented that
usually mailboxes were temporarily relocated.
A resident commented he had called ENCON to see why the
other portion of Fairway North was not included in Phase
I, he had been told there was a storm drain coming across
the river at that point. Mr. Brienza responded that one
of the reasons the sewer split there was because of the
storm drain.
A resident commented the residents would not get any
benefit out of this system until the project was completed.
Village Manager Bradford responded that was not correct
since the homes in Phase I did not require a lift station
to be constructed in order to be served with sewer, so once
they were done, and homeowners had received the letter
notifying them they had one year to hook up, they could go
ahead and hook up and take advantage of the new system.
Mr. Brienza commented ENCON planned to redo the lift
station at the corner of Tequesta Drive and Country Club
Drive probably in April, which was the principal lift
station that fed the whole area.
A resident questioned whether someone from the Village
could come to the homes where the storm drain would be torn
up to see what trees really needed to be moved. Tom Jensen
responded that the resident should call him regarding this
matter.
Joe Hall questioned whether the plans showed property
survey lines between neighbors, to which Mr. David
responded the plat had been laid over an aerial to
determine the property lines rather than resurveying. Mr.
Hall questioned whether a homeowner would be safe if his
sewer line was placed right inside what he believed to be
his property line. Mr. David responded by indicating on
a slide where the property lines were, and that the answer
to Mr. Hall' s question was yes .
Mayor Hansen thanked everyone for coming to the meeting and
commented that the next four months would be difficult for
SPECIAL VILLAGE COUNCIL
MEETING MINUTES
February 24 , 2000
PAGE 18
everyone; however, best efforts had been made to coordinate
the project. Mayor Hansen advised that damage from
Hurricane Irene had resulted in FEMA money to the Village
if the work was done within 12 months; therefore, it was
very important to get the project done within the next
twelve months .
V. ANY OTHER MATTERS
There were no other matters to come before the Village
Council.
VI . ADJOURNMENT
Vice Mayor Schauer moved that the meeting be adjourned.
Councilmember Walker seconded the motion. The vote on the
motion was:
Carl C. Hansen - for
Elizabeth A. Schauer - for
Joseph N. Capretta - for
Sharon Walker - for
The motion was therefore passed and adopted and the
meeting was adjourned at 9:00 p.m.
Respectfully submitted,
Betty Laur
Recording Secretary
ATTEST:
Joann Manganiello
Village Clerk
DATE APPROVED: