HomeMy WebLinkAboutDocumentation_Regular_Tab 8I_8/10/2000 •
1L1 I J
Memorandum •
To: Joann Manganiello, Acting Village Manager/Village Clerk
From: Gary Preston, Director of Public Works & Recreation AP
Date: August 2, 2000
Subject: Village Council Agenda Item for August 10, 2000; Consideration To
Award a Change Order for Country Club Drive Street Light
Conduit Installation to Ric-Man International, Inc., in the Amount
of $64,693.50 Subject to Funds Being Appropriated for FY 2001,
Having a Total Proposed FY 2001 Budget Allocation of$81,076.
Please find attached, a Change Order in the amount of$64,693.50 from Ric-Man International,
Inc., for street light conduit installation on Country Club Drive. This Change Order would
increase the number of street lights on Country Club Drive from 15 to 58. The type of street
light proposed would be the Traditional Post Top Luminaire located on a fiberglass pole.
The proposed FY 2001 budget has funding available for installation and monthly street light
expenditures.
Please place this item on the August 10, 2000 Village Council Agenda for Councilmembers'
consideration.
GP/mk
Attachments
Agendal temGPMemoS&Ligh tCondu i tCClubDrive
RESOLUTION NO. 79-99/00
A RESOLUTION OF THE VILLAGE COUNCIL OF
THE VILLAGE OF TEQUESTA, PALM BEACH
COUNTY, FLORIDA, AWARDING A CHANGE ORDER
FOR COUNTRY CLUB DRIVE STREET LIGHT
CONDUIT INSTALLATION TO RIC-MAN
INTERNATIONAL, INC. , OF POMPANO BEACH,
FLORIDA, IN THE AMOUNT OF $64 , 693 . 50,
SUBJECT TO FUNDS BEING APPROPRIATED IN
FY 2001 BUDGET, HAVING A TOTAL PROPOSED
FY 2001 BUDGET ALLOCATION OF $81, 076 AND
AUTHORIZING THE ACTING VILLAGE MANAGER
TO EXECUTE THE CONTRACTUAL CHANGE ORDER
ON BEHALF OF THE VILLAGE.
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF TEQUESTA, PALM BEACH COUNTY,
FLORIDA, AS FOLLOWS:
Section 1 . A Contractual Change Order with Ric-Man
International, Inc . , of Pompano Beach, Florida, for
Country Club Drive Street Light Conduit Installation,
in the amount of $64, 693 . 50, attached hereto as
Exhibit "A" and incorporated by reference as part of
this Resolution, is hereby approved subject to funds
being appropriated for such in FY 2001, and the Acting
Village Manager is authorized to execute the
applicable contractual change order on behalf of the
Village of Tequesta.
THE FOREGOING RESOLUTION WAS OFFERED by Councilmember
, who moved its adoption. The
motion was seconded by Councilmember
, and upon being put to a vote, the
vote was as follows :
FOR ADOPTION AGAINST ADOPTION
The Mayor thereupon declared the Resolution duly
passed and adopted this loth day of August, A.D, 2000 .
MAYOR OF TEQUESTA
Joseph N. Capretta
ATTEST:
Joann Manganiello
Village Clerk
Resolution.CountryClubStreetLightRicMan(3)
Exhibit "A"
CHANGE ORDER 99-161.1
No. 4
PROJECT: Tequesta Country Club/Bermuda Terrace:Water Main Replacement&Drainage System Improvements-Phase I
DATE OF ISSUANCE: July 5.2000 . EI •ECTIVE DATE: Upon Village Approval
OWNER: Village of Tequesta
OWNER's Contract No. N/A
CONTRACTOR: Ric Man International,Inc. ENGINEER: Reese,Macon and Associates,Inc.
You are directed to make the following changes in the Contract Documents.
Description: Identify unit costs for items not in original contract.
Reason for Change Order: Installation of conduit/pull boxes for street lights;Country Club Drive.
Attachments:(list documents supporting change) Unit Cost breakdown as supplied by Ric Man International,Inc.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: 240 days
S 2,069,000.00 Ready for final payment: 270 days
days or dates
Net changes from previous Change Orders No. 1 to No. 3 Net change from previous Change Orders No.1 to No. 3
S 201,656.15 (Pending) 45
days
Contract Price prior to this Change Order Contract Times prior to this Change.Order
Substantial Completion: 285 Days
S 2,270,656.15(Pending C.O.#I/2&3 Approval) Ready for final payment: 315 Days
days or dates
Net Increase(decrease)of this Change Order Net Increase(decrease)of this Change Order
S 64,693.50 20 Days
days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: 305 Days
S 2,335,349.65 Ready for final payment: 335 Days
days or dates
Thomas C. Jensen,P.E. Joann Manganiello,Acting Rene Castillo ecre
RECOMMENDED: APPROVED:Village Manager ACCEPT .
By: By: By: (i
Owner(Authorized Signature) Contract° ized Signature)
7i -
O O
Date: Date: Date: 7 d/
Reese,Macon&Associates,Inc. Village of Tequesta Ric Man International,Inc.
tcj chordteg4/99-161.1
CHANGE ORDER No.4
Tequesta Country Club/Bermuda Terrace
Water Main Replacement& Drainage system Improvements
Phase I
VILLAGE OF TEQUESTA
TEQUESTA COUNTRY CLUB/BERMUDA TERRACE
WATER MAIN REPLACEMENT AND
DRAINAGE SYSTEM IMPROVEMENTS
UNIT PRICE BID SCHEDULE W/
RIC MAN'S UNIT COSTS
•
I. STREET LIGHT CONDUIT
A. COUNTRY CLUB DRIVE
1. PVC Conduit*
a. 2" 4,300 LF $ 5.50 $23,650.00
2. Pull Boxes* 77 Ea. $ 80.50 $ 6,198.50
3. Directional Bore (HDPE/PVC)
a. Country Club Drive
(60 LF Ea.) 18 Ea. $661.25 $11,902.50
4. Crossings (Tunneling)
a. Roadway (40 LF Ea.) 3 Ea. $460.00 $ 1,380.00
b. Driveway (15 LF Ea.) 60 Ea. $287.50 $17,250.00
4. Sod. 750 SY $ 5.75 $ 4,312.50
TOTAL $64,693.50
* Installation only, material supplied by FPL.
tcjchgordteq4/99-161.1
CHANGE ORDER 99-161.1
No. 4
PROJECT: Tequesta Country Club/Bermuda Terrace:Water Main Replacement&Drainage System Improvements-Phase I
DATE OF ISSUANCE: July 5,2000 EFFECTIVE DATE: Upon Village Approval
OWNER: Village of Tequesta
OWNER's Contract No. N/A
CONTRACTOR: Ric Man International,Inc. ENGINEER: Reese,Macon and Associates,Inc.
You are directed to make the following changes in the Contract Documents.
Description: Identify unit costs for items not in original contract.
Reason for Change Order: Installation of conduit/pull boxes for street lights;Country Club Drive.
Attachments:(list documents supporting change) Unit Cost breakdown as supplied by Ric Man International,Inc.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: 240 days
5; 2,069,000.00 Ready for final payment: 270 days
days or dates
Net changes from previous Change Orders No. 1 to No. 3 Net change from previous Change Orders No.1 to No. 3
$ 201,656.15 (Pending) 45
days
Contract Price prior to this Change Order Contract Times prior to this Change Order
Substantial Completion: 285 Days
$ 2,270,656.15(Pending C.O.#1/2&3 Approval) Ready for final payment: 315 Days
days or dates
Net Increase(decrease)of this Change Order Net Increase(decrease)of this Change Order
$ 64,693.50 20 Days
days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: 305 Days
$ 2,335,349.65 Ready for final payment: 335 Days
days or dates
Thomas C. Jensen,P.E. Joann Manganiello,Acting Rene Castillo, ecr
RECOMMENDED: APPROVED:Village Manager ACCEPTE .
By: /� By: By:
Own (ASignature) Contractor u ed i re)
Date: ________
7'Z!i-!/!, Date:
� /6rl Date: 7 j/ G
Reese, . o 1 : Associates,Inc. Village of T quest Ric Man Interns oval,Inc.
tcj chordteg4/99-161.1
•
CHANGE ORDER No.4
Tequesta Country Club/Bermuda Terrace
Water Main Replacement & Drainage system Improvements
Phase I
VILLAGE OF TEQUESTA
TEQUESTA COUNTRY CLUB/BERMUDA TERRACE
WATER MAIN REPLACEMENT AND
DRAINAGE SYSTEM IMPROVEMENTS
UNIT PRICE BID SCHEDULE W/
RIC MAN'S UNIT COSTS
I. STREET LIGHT CONDUIT
A. COUNTRY CLUB DRIVE
1. PVC Conduit*
a. 2" 4,300 LF $ 5.50 $23,650.00
2. Pull Boxes* 77 Ea. $ 80.50
$ 6,198.50
3. Directional Bore (HDPE/PVC)
a. Country Club Drive
(60 LF Ea.) 18 Ea. $661.25 $11,902.50
4. Crossings (Tunneling)
a. Roadway(40 LF Ea.) 3 Ea. $460.00 $ 1,380.00
b. Driveway (15 LF Ea.) 60 Ea. $287.50 $17,250.00
4. Sod 750 SY $ 5.75 $ 4,312.50
TOTAL $64,693.50
* Installation only, material supplied by FPL.
tcjchgordteg4/99-161.1