HomeMy WebLinkAboutDocumentation_Regular_Tab 8J_8/10/2000 Memorandum
To: Joann Manganiello, Acting Village Manager/Village Clerk
From: Gary Preston, Director of Public Works & Recreation A
Date: August 2, 2000
Subject: Village Council Agenda Item for August 10, 2000; Consideration To
Award a Change Order for Country Club Community Interior Area
(Phase I) Street Light Conduit Installation to Ric-Man International,
Inc., in the Amount of $123,920, Subject to Funds Being
Appropriated for FY 2001, Having a Total Proposed FY 2001 Budget
Allocation of$160,550.
Please find attached, a Change Order in the amount of $123,920 from Ric-Man International,
Inc., for street light conduit installation in the Country Club Community (Phase I). This
Change Order would increase the number of street lights in Phase I from 24 to 108. The type
of street light proposed would be the Traditional Post Top Luminaire located on a fiberglass
pole.
The proposed FY 2001 budget has funding available for installation and monthly street light
expenditures.
Please place this item on the August 10, 2000 Village Council Agenda for Councilmembers'
consideration.
GP/mk
Attachments
Agendal temGPMemoCClubinterior
r
RESOLUTION NO. 80-99/00
A RESOLUTION OF THE VILLAGE COUNCIL OF
THE VILLAGE OF TEQUESTA, PALM BEACH
COUNTY, FLORIDA, AWARDING A CHANGE ORDER
FOR COUNTRY CLUB COMMUNITY INTERIOR AREA
(PHASE I) STREET LIGHT CONDUIT
INSTALLATION TO RIC-MAN INTERNATIONAL,
INC. , OF POMPANO BEACH, FLORIDA, IN THE
AMOUNT OF $123 , 920 , SUBJECT TO FUNDS
BEING APPROPRIATED IN FY 2001 BUDGET,
HAVING A TOTAL PROPOSED FY 2001 BUDGET
ALLOCATION OF $160, 550 , AND AUTHORIZING
THE ACTING VILLAGE MANAGER TO EXECUTE
THE CONTRACTUAL CHANGE ORDER ON BEHALF
OF THE VILLAGE .
NOW, THEREFORE, BE IT RESOLVED BY THE VILLAGE COUNCIL
OF THE VILLAGE OF TEQUESTA, PALM BEACH COUNTY,
FLORIDA, AS FOLLOWS :
Section 1. A Contractual Change Order with Ric-Man
International , Inc . , of Pompano Beach, Florida, for
Country Club Community Interior Area (Phase I) Street
Light Conduit Installation, in the amount of $123 , 920,
attached hereto as Exhibit "A" and incorporated by
reference as part of this Resolution, is hereby
approved subject to funds being appropriated for such
in FY 2001, and the Acting Village Manager is
authorized to execute the applicable contractual
change order on behalf of the Village of Tequesta .
THE FOREGOING RESOLUTION WAS OFFERED by Councilmember
, who moved its adoption. The
motion was seconded by Councilmember
, and upon being put to a vote, the
vote was as follows :
r
FOR ADOPTION AGAINST ADOPTION
The Mayor thereupon declared the Resolution duly
passed and adopted this 10th day of August, A.D, 2000 .
MAYOR OF TEQUESTA
Joseph N. Capretta
ATTEST:
Joann Manganiello
Village Clerk
Resolution.Ric-ManCC1ubInterior
•
Exhibit "A"
CHANGE ORDER 99-161.1
No. 3
PROJECT: Tequesta Country Club/Bermuda Terrace:Water Main Replacement&Drainage System Improvements-Phase I
DATE OF ISSUANCE: July 5,2000 E11.ECTIVE DATE: Upon Village Approval
OWNER: Village of Tequesta
OWNER's Contract No. N/A
CONTRACTOR: Ric Man International,Inc. ENGINEER: Reese,Macon and Associates,Inc.
You are directed to make the following changes in the Contract Documents.
Description: Identify unit costs for items not in original contract.
Reason for Change Order: Installation of conduit/pull boxes for street lights:Country Club interior area(Phase I).
Attachments:(list documents supporting change) Unit Cost breakdown as supplied by Ric Man International,Inc.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: 240 days
S 2,069,000.00 Ready for final payment: 270 days .
days or dates
Net changes from previous Change Orders No. 1 to No.2 Net change from previous Change Orders No.1 to No. 2
S 77,736.15 (Pending) 15
days
Contract Price prior to this Change Order Contract Times prior to this Change Order
Substantial Completion: 255 Days
S 2,146,736.15 (Pending C.O.#1/2 Approval) Ready for final payment: 285 Days
days or dates
Net Increase(de ase)of this Change Order Net Increase(de e)of this Change Order
S 123,920.00 30 Days
days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: 285 Days
S 2,270,656.15 Ready for final payment: 315 Days
days or dates
Thomas C. Jensen,P.E. Joann Manganiello,Acting Rene Cas • retary
RECOMMEND APPROVED:Village Manager ACCEP
By: By: By:
Owner(Authorized Signature) Contract uth ed Sign ture)
7.24-a 7 3i Ga
Date: Date: Date:
Reese,Macon&Associates,Inc. Village of Tequesta Ric an International,Inc.
tcj chgordteg3/99-161.1
CHANGE ORDER No.3
Tequesta Country Club/Bermuda Terrace
Water Main Replacement &Drainage system Improvements
Phase I
VILLAGE OF TEQUESTA
TEQUESTA COUNTRY CLUB/BERMUDA TERRACE
WATER MAIN REPLACEMENT AND
DRAINAGE SYSTEM IMPROVEMENTS
UNIT PRICE BID SCHEDULE W/
RIC MAN'S UNIT COSTS
I. STREET LIGHT CONDUIT
A. COUNTRY CLUB INTERIOR AREA (PHASE I),
1. PVC Conduit*
a. 2" 11,700 LF $ 5.50 $64,350.00
2. Pull Boxes* 190 Ea. $ 80.50 S15,295.00
3. Crossings (Tunneling)
a. Roadway (40 LF Ea.) 60 Ea. $460.00 $27,600.00
b. Driveway (15 LF Ea.) 34 Ea. $287.50 $ 9,775.00
4. Sod 1,200 SY $ 5.75 S 6,900.00
• . . TOTAL $123,920.00
* Installation only, material supplied by FPL.
Includes Tequesta Circle and Golf Club Circle.
tcj chgordteg3/99-161.1
CHANGE ORDER 99-161.1
No. 3
PROJECT: Tequesta Country Club/Bermuda Terrace:Water Main Replacement&Drainage System Improvements-Phase I
DATE OF ISSUANCE: July 5,2000 EFI bCTIVE DATE: Upon Village Approval
OWNER: Village of Tequesta
OWNER's Contract No. N/A
CONTRACTOR: Ric Man International,Inc. ENGINEER: Reese,Macon and Associates,Inc.
You are directed to make the following changes in the Contract Documents.
Description: Identify unit costs for items not in original contract.
Reason for Change Order: Installation of conduit/pull boxes for street lights;Country Club interior area(Phase I).
Attachments:(list documents supporting change) Unit Cost breakdown as supplied by Ric Man International,Inc.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times
Substantial Completion: 240 days
$ 2,069,000.00 Ready for final payment: 270 days
days or dates
Net changes from previous Change Orders No. 1 to No.2 Net change from previous Change Orders No.1 to No. 2
5 77,736.15 (Pending) 15
days
Contract Price prior to this Change Order Contract Times prior to this Change Order
Substantial Completion: 255 Days
5 2,146,736.15 (Pending C.O.#1/2 Approval) Ready for final payment: 285 Days
days or dates
Net Increase(diXase)of this Change Order Net Increase(de e)of this Change Order
$ 123,920.00 30 Days
days
Contract Price with all approved Change Orders Contract Times with all approved Change Orders
Substantial Completion: 285 Days
$ 2270.656.15 Ready for final payment: 315 Days
days or dates
Thomas C. Jensen,P.E. Joann Manganiello,Acting Rene Castillo ecre
RECOMMENDED: APPROVED:Village Manager ACCEPT
By: B O By.
Owner(Authorized Signatur Contractor ' e ign re)
Date: 7
Date: �l ��6�/'O Date:
Reese,Macon&Associates,Inc. Village of Tequesta Ric Man International,Inc.
tcj chgordteg3/99-161.I
CHANGE ORDER No.3
Tequesta Country Club/Bermuda Terrace
Water Main Replacement & Drainage system Improvements
Phase I -
VILLAGE OF TEQUESTA
TEQUESTA COUNTRY CLUB/BERMUDA TERRACE
WATER MAIN REPLACEMENT AND
DRAINAGE SYSTEM IMPROVEMENTS
UNIT PRICE BID SCHEDULE W/
RIC MAN'S UNIT COSTS
I. STREET LIGHT CONDUIT
A. COUNTRY CLUB INTERIOR AREA (PHASE I),
1. PVC Conduit*
a. 2" 11,700 LF $ 5.50 $64,350.00
2. Pull Boxes* 190 Ea. $ 80.50 $15,295.00
3. Crossings (Tunneling)
a. Roadway (40 LF Ea.) 60 Ea. $460.00 $27,600.00
b. Driveway (15 LF Ea.) 34 Ea. $287.50 $ 9,775.00
4. Sod 1,200 SY $ 5.75 $ 6,900.00
TOTAL $123,920.00
* Installation only, material supplied by FPL.
Includes Tequesta Circle and Golf Club Circle.
tcjchgordteg3/99-161.1