HomeMy WebLinkAboutPresentation_Regular_12/12/2024 (4)December 12, 2024 1 Presentation to Village of Tequesta Replacement Project SE County Line Bridge
PROJECT LOCATION AND OVERVIEW 2
HISTORY OF BRIDGE 3 Design Complete. Bidding expected in April 2025.2024: •Replacement project entered the conceptual and planning phases.2022: •term infrastructure planning.-need to
replace the bridge as part of its longthe Florida Department of Transportation and Martin County identified the Due to aging infrastructure and increased traffic, Recent Years: •Originally
constructed.1974: •
PROPOSED IMPROVEMENTS 4 sidewalk on the new bridge.foot raised -Adjacent pedestrian bridge to be removed and replaced with 6•enhance safety.foot shoulders to improve vehicle flow and
-foot travel lanes with 6-New 12•Complete bridge replacement up to current standards. •
PROPOSED IMPROVEMENTS 5 Existing Bridge
PROPOSED IMPROVEMENTS 6 BEFOREBEFORE
PROPOSED IMPROVEMENTS 7 AFTERAFTER
PROPOSED IMPROVEMENTS 8 AFTER BEFORE
CONSTRUCTION IMPACTS 9 safety throughout the project.have immediate access, maintaining rapid response times and community First responder staging area will be set up to ensure that
emergency services •the closure area.Detours for local traffic will be established to redirect vehicles smoothly around •completion of the work.Full road closure during bridge construction
to allow for efficient and safe •utility relocations.Intermittent lane closures for Loxahatchee River District and Village of Tequesta •
CONSTRUCTION IMPACTS LOCATION AND AFFECTED SERVICE AREA EMERGENCY RESPONSE PLAN 10
CONSTRUCTION IMPACTS Temporary station will be staffed 24/7 and will remain in place until bridge is reopened.•This will be in addition to Station 36 and will house a crew of 5 including
2 apparatus.•Multiple locations are being actively researched and assessed.•Mitigation plan is to place a temporary fire station on the west side of the closure.•and lack of alternative
access.Emergency response times to areas west of the bridge will be impacted due to detour •Station 36 is situated on the east side of the closure.•EMERGENCY RESPONSE PLAN 11
CONSTRUCTION IMPACTS 12
PROJECT SCHEDULE 13 Fall 2026Estimated End Construction: Spring 2025Estimated Begin Construction: Bridge Construction with Road Closure:Spring 2025Estimated Begin Construction: Utility
Relocation with Intermittent Lane Closure:
www.martin.fl.us/county 14 5666-(772) 288 Hotline: CONTACT INFORMATION d bridge-line-
Thank You! 15 Questions?