Loading...
HomeMy WebLinkAboutDocumentation_Regular_Tab 21_5/8/2025 Agenda Item #21. Regular Council STAFF MEMO Meeting: Regular Council - May 08 2025 Staff Contact: Marjorie Craig, Utilities Director Department: Utilities immr Consider Approval of Holtz Consulting Work Authorization for WM#1 Tequesta Drive Water Main (WM) Replacement Project (WM#1) for a Total Not to Exceed $87,365 — Construction Engineering Inspection (CEI) Services During Construction The Village of Tequesta (Village) Utilities Department (UD) recommends approval of work authorization (WA) 19 with Holtz Consulting for"WM#1 Tequesta Drive Water Main Replacement" project (Project). The work authorization includes construction engineering inspection (CEI) phase services for a project to replace approximately 5,600 feet of existing asbestos cement (AC) potable water main, not to exceed $87,365. This project was 100% complete and was originally bid together with the WM#4 Country Club Dr S water main replacement project in November 2022. The bids for the combined project came in at 60% higher than the engineer's opinion of probable construction cost (OPC). Therefore, the WM#1 portion was deferred due to a lack of funding. Due to the implementation of the capital charge in 2023, we can now fund it as a pay-go project. Streets included in the Project: • El Portal Drive from Yacht Club Place to Country Club Drive • Tequesta Drive from County Club Drive to Pinetree Drive • Tequesta Drive from the Tequesta Bridge to Fiesta Drive This Project is part of the phased AC water main replacement program included in the "May 2020 Village of Tequesta Facilities Assessment Update," developed for the Village UD by Kimley-Horn. Attached is a map of the currently planned AC pipe replacement projects. At the March 3, 2025, Village Council workshop, the UD presented its updated financial projections, provided by the Village's Finance Department, which showed that implementing the 2023 capital charge as a part of the rate increase has allowed us to catch up financially in revenues. Based on this, the UD is prepared to proceed with two additional capital projects on a cash basis. The new recommended project schedule includes moving the SA Well 19 Replacement project and WM#1 Tequesta Dr. water main replacement forward this year, which were deferred in 2022 due to a lack of funding. The projected project schedule is outlined below: Finalize 100% Design: April 2025 Bid Project: Mid-May 2025 Award Project: July 2025 Issue Notice to Proceed: August 2025 Complete Project: March 2026 (pending supply chain) Holtz Consulting has a master agreement with the Village through the Consultant's Competitive Negotiations Act (CCNA), FS287.055, approved on September 10, 2020. The CCNA requires public agencies to select professional service firms based on qualifications. Please see the attached scope of services for more details. The work authorization will be funded by the Water Fund account for engineering services. Page 207 of 496 Agenda Item #21. WATER FUND - Account 401-412-663.632 Capital Improvement Architect & Engineering Services Budgeted amount: $8101000 Available amount: $326)289 Amount of this proposal: $ 875365 Amount of additional proposal elsewhere on this agenda (Well#19): $ 835000 Total Remaining: $1559924 Attachment: • Holtz Consulting work authorization#19 for CEI services for WM#1 for signature • Kimley-Horn map of Village UD AC pipe replacement program from the 2020 Village UD Facilities Assessment Plan • Holtz maps of Village UD AC pipe replacement program and WM#1 specifically from the 2024 FDEP SRF Village UD Facilities Plan This document and any attachments may be reproduced upon request in an alternative format by completing our Accessibility Feedback Form, sending an e-mail to the Village Clerk or calling 561- 768-0443. BUDGET INFORMATION:"" BUDGET AMOUNT $810,000 AMOUNT AVAILABLE EXPENDITURE AMOUNT: $326)289 $87)365 FUNDING SOURCES: 401-412-663.632 Capital IS THIS A PIGGYBACK: Improvement Architectural & Engineering El Yes ❑x N/A Services DID YOU OBTAIN 3 QUOTES? ❑ Yes ❑x N/A QUOTE 1 - BUSINESS NAME N/A QUOTE AMOUNT N/A QUOTE 2 - BUSINESS NAME N/A QUOTE AMOUNT N/A QUOTE 3 - BUSINESS NAME N/A QUOTE AMOUNT N/A COMMENTS/EXPLANATION ON SELECTIONCCNA approved continuing engineering consulting firm 1) 25.0410.Holtz - WA 19 WM#1 Teq. Dr-CEl-executed 02) AC Pipe Replacement Protects Figure- 2020 03) 2024 WM Project Exhibit- WM#1 Tequesta Dr Page 208 of 496 Agenda Item #21. VILLAGE OF TEQUESTA k CONSULTING SERVICES WORK AUTHORIZATION 1 DATE : 4/10/25 VILLAGE RFQ. NO. : UTIL 06-20 WORK AUTHORIZATION NO.19 FOR CONSULTING SERVICES PROJECT No. 2 1-UTL-67 1-01 G/L CODE: 401-411-663.671 HOLTZ CONSULTING PROJECT NO.: PROJECT TITLE: WM#1 Tequesta Dr. Water Main Replacement Project—Engineering Services During Construction The terms used in this work authorization with initial capital letters have the meaning stated in the 2020 request for qualifications documents and the master agreement for professional services referenced below. This Work Authorization, when executed, shall be incorporated in and shall become an integral part of the Agreement for Professional Services dated September 10, 2020, between the Village of Tequesta ("VILLAGE") and Holtz Consulting ("CONSULTANT"), hereafter referred to as the Agreement. I. PROJECT DESCRIPTION The project will include engineering services during construction for the WM#1 Tequesta Dr. Water Main Replacement Project , which consists of the installation of approximately 5,600 feet of potable water main to replace the existing asbestos cement (AC)pipe along the streets listed below: • E1 Portal Drive from Yacht Club Place to Tequesta Drive • Tequesta Drive from Country Club Drive to Pinetree Drive • Tequesta Drive from the Tequesta Bridge to Fiesta Drive The existing AC pipe was installed in the 1950's and 1960's and has reached the end of its useful life. Replacing the AC pipe will reduce the risk of failure and increase the resiliency of the Village's potable water distribution system. Included in the design will be the replacement of water services from the new water mains to the existing water meters, new fire hydrants, and the grouting/abandonment of the existing AC pipe after the new water mains are placed into service. WORK AUTHORIZATION NO. HCE-U21.19 1 of 4 Page 209 of 496 Agenda Item #21. II. SCOPE OF SERVICES The following is a description of the services to be provided under this Work Authorization. TASK 1 —ENGINEERING SERVICES DURING CONSTRUCTION CONSULTANT will provide engineering and inspection services during construction of the project. It is assumed that the construction contract will be eight (8) months from NTP to Final Completion with approximately 26 weeks of actual field construction. Under this task CONSULTANT will perform the following activities: • Administer the VILLAGE'S Construction Contract with the Contractor in accordance with the General Conditions of the Construction Contract. • Direct the preconstruction meeting with the VILLAGE, Contractor, and other interested parties and prepare meeting agenda and minutes. • Review and comment on shop drawings submitted by the Contractor. • Provide the Contractor with clarifications concerning questions about the Contract Documents and respond to RFI's. • Review and make the recommendations necessary for the approval or rejection of the Contractor's monthly payment applications. • Conduct bi-weekly progress meetings with the VILLAGE and Contractor. Prepare and distribute meeting minutes to all attendees. • Coordinate with customers regarding impacts due to the construction activities including interruptions of service. • Make general site inspections of the work such including periodic visits to the site to evaluate the Contractor's compliance with Contract Documents (Approximately 26 weeks of actual construction and an average of 16 hours per week for the Construction Inspector and 2 hours per week by the Engineer of Record) to monitor progress. It is assumed that the construction contract will have a duration of six months. • Verify that the work has progressed to the substantial completion point in accordance with the Contract Documents. The CONSULTANT will prepare a punch list of items remaining to be completed which will be attached to the Certificate of Substantial Completion. • Verify that the work items identified on the substantial completion punch list are addressed and all other Work identified as being incomplete have been completed in accordance with WORK AUTHORIZATION NO. HCE-U21.19 2 of 4 Page 210 of 496 Agenda Item #21. the Contract Documents. CONSULTANT will ensure the final punch list is satisfactorily completed prior to approval of the Contractor's Final Payment Request. • Review Record Drawings submitted by the Contractor with each Pay Request and at completion of the project. • Prepare final documentation for Contract close-out. III. DELIVERABLES Task 1 - Deliverables: 1. PDF copy of all Contractor Submittals. 2. PDF copy and two hard copies of Contractor Pay Requests with recommendation for payment. 3. PDF copy of all meeting agendas and minutes. 4. PDF copy of the Substantial Completion Punchlist. 5. PDF copy of the Certificate of Substantial Completion. IV. SCHEDULE Upon receipt of Notice-To-Proceed the CONSULTANT will complete the services identified in this Work Authorization within the schedule outlined in Table 1. Table 1 Schedule Cumulative Time to Complete Time to (Calendar Days) Complete A ti it (Calendar Days) 1. Services During Construction Throughout Construction 248 Contract Duration(approx. 8 months) WORK AUTHORIZATION NO. HCE-U21.19 3 of 4 Page 211 of 496 Agenda Item #21. V. COMPENSATION AND PAYMENT The CONSULTANT will perform the tasks as outlined in the scope of services on a time and expense basis,not to exceed$87,365 and will invoice in accordance with our approved billing rates. Invoices for worked performed will be submitted by CONSULTANT monthly for approval by VILLAGE. Table 2 Budget Summary Description Total 1. Engineering Services During Construction $871365 TOTAL $879365 VI. ASSUMPTIONS 1. It is assumed that the construction contract will be eight (8) months from NTP to Final Completion with approximately 26 weeks of actual field construction. VII. AGREEMENT REFERENCE The work authorized under this Work Authorization shall be performed under the terms and conditions described within the Professional Services Agreement dated September 10, 2020,by and between the Village of Tequesta ("VILLAGE") and Holtz Consulting ("CONSULTANT"). Compensation shall not exceed the hourly rates currently in effect under this Agreement. HOLTZ CONSULTING VILLAGE OF TEQUESTA By: By: Molly Young, Mayor Print Name: Stephen Fowler, PE, CGC Title: Vice President Date: WORK AUTHORIZATION NO. HCE-U21.19 4 of 4 Page 212 of 496 Agenda Item #21. Attachment A: Village of Tequesta-WM#1 Tequesta Drive Water Main Replacement Project-Services During Construction � � G C G' R •m � R .S MCA R C C .fir C O C .w .r v' C v' v. U Q� Q10, s: ti Q /] Cn .y.V� H Rate $190 $1801 $150 $105 $110 $135 $95 $70 -- Task Item Hours Fees Pre-Construction Meeting Agenda,Attend and Minutes 1 2 1 $585.00 Administer Construction Contract with Contractor and Coordinate with Owner 8 16 6 $4,340.00 Review Submittals 1 8 8 $2,230.00 Respond to RFIs 1 3 $640.00 Review Pay Requests Assume 7 1 1 7 1 $1,240.00 Review CO Issues and Issue COs 1 2 $490.00 1.Engineering Services Attend Bi-weeklyProgress Meetings and Prep Minutes Assume 12) 12 18 12 $6,120.00 During Construction Coordination of Notifications to Residents and Businesses 20 $1,900.00 $87,365.00 General Inspections Const.Mgr/Inspector 16 hrs/week for 26 weeks 208 208 $47,840.00 Construction Mana ement/Corres ondence/Coordination 20 40 $9,800.00 General Inspections PM 2 his/week for 26 weeks 52 $7,800.00 Closeout of Permits 2 2 $680.00 Monitor Punchlist Through Final Completion 6 10 $1,850.00 Prep and Warrant Walkthrou h and Punchlist(HCE) 2 2 $490.00 Review Contractor Record Drawings 2 2 2 $870.00 Contract Closeout Activities 1 2 $490.00 Subconsultant 50 0 162 8 0 208 255 6 $0.00 HCE Total $87,365.00 *Proposal is based on a 8 month construction contract(26 weeks active construction). Onsite services are based on the assumption that $87,365.00 the project will be completed under the schedule for these services.In the event that the Contractor does not complete construction activities in their contractual schedule,an amendment maybe required for extended construction services. Page 213 of 496 Agenda Item#21. x o z (n (n n, x d Q o � a w w o z z z V D J z z O Q Q w Q m U o U- w (n W W z O J O � z X ~ O w w � 0 Q .� Q 0 U W W = 0 (� N Ln CO I� o0 o-) O N Ln U z J w J � J LLJ O O I I I I Q Q > a cn J ❑ ❑ ❑ ❑ wz ❑ � � I I I LL Q U � Q H'NPy O O�X(E HAG b ❑ •0\0 b z � 1 J Q m • O �� H J W J Q Q J / MaaP P� W W z W wz U • b b 1O p V1 F0 z�LLw w b rc STATE ROAD 707(Aix) rn a a 0 d z � z w U Li w < Q w z O10N2IV J za = wao ¢m •)�,• •� • eAa aono Q zu) O G (n LLJ O b A�NN ( 7 LL w LL LU N3�ly NbIONI f^ �w 1ERWAY LLJv) WA r" �Il 0 p Q , lH'(FACOASTP � x - t t t, t ❑ II ��m.0 w t ;w CO ACpAS'(N-WP�a•N PY b` t L s t 6�6py Nni Q O • �Ft a_U eR� a $ `I `0 9r �1 U cD O O °•r w N t �•�t �� D-O a a a O m LLJ ry / Q t I Jd t 8 6 10 _ ❑ O Ll / ..'may, e° `� "• � � �� � t�� ��B .a6� s t ��y � �� ❑�F M a <• c� F- of M a mom„ O wa�c F- o w(0 K srea g am0'0 O a ��g O 0, O v) n Q d O x 011, z 6 � 'w`�•w fir`` r �� O o � ❑ t _ �� z (o 3mwsr FpP�' 0O ON Op 0 •, p 6 Qj 7ffr a d„ w14- zoir w(n w Lr) T3 t Yrm� x CN 3: 2 3� • - �saNwisr.•l • a• 4`6 " O w o e s O o ' m 3 Q $ \ M1of z w g 0 z au1'sa;o!oossy puo woH—Ralw!N o;,!}!I!go!I}noy}iM aq Iloys au1'sa}o!aossy puo woH—,(alwiN,(q uogo}dopo puo uoi}ozuoy}no ua}}um}noy}im}uawnaop siy}u uoilai jadoidwi puo;o asnaa-pajodajd s M}i yaiym io}}uaila puo asodind ai}iaads ay}io}Rluo Papua}ui s as;o}uawn�}sui,u aiay pa}uasaid su6isap puo s}daauoa ay}y}im gay}a6o}}uawnaop siyl 6n^P NV�d ONISVHd 1N3 W30VHd3i1 3dld OV lOn\OVO\dSM 21:.06\saa!—S as!W 10A—910L600b0\1!^!3—BdM\:N wdbl bS SO OZOZ'Ol I!udV ilOIHX3 NV-ld 311S:}nOXDo SdVW NOUnOl iSIO a31VM V1S3f1031 jO 3ov��IA:}aS}aay5 oy}uowo5`II!9L ou0:/�g pa}}old Page 214 of 496 Agenda Item#21. N � Q O M � rucu ra N r 0_ O ca O >1 CD O M N M lzl- LO CO r-- 00 MO N M I � > O N u U •� fp N O � � � � � � � � � � � � � � � � � ru � mCO Z cn U ) I 1 1 �o J Q I I 1 1 z w� w D Z� 0o w w"t �'MO Z o J Z LL wll�;=- 1 Q1 UWc(D Cn 00 � wwww rL Cn / cn n = o w a� 0 `. m V Ln 0 0 2 a� N O ay F- � � Uz LU W dec a�N.Ny m Q S�Fe � � a a W 4 J cn U) Z � a� r-, W cn w ��_ a Q�o �. ♦, a a o o �— U ---------� O a� z U z Q / j OI / •L 'I ry H ♦ v LUZ ra OO 1 � [2 WSW O I / ~ U a) 0 1 LLWQ O M-0 o, H J ru l ----� l a N J W J a O W CL O V LL Z 00 ry O Q i LO O V .� W ^, i � � � Qz _ Q � 1 a) _ U J L L a N O J U U 0 � N � > 0 U L � U z z Page 21 of 49 Agenda Item #21. 0 0 X CL M 0 CU > will OLV Shay PI 'Westwood Ave 0 CL 41 (n 0 1- N Dover Rd M ,)e je Beacon St (n Church Rd > Dover Rd < > < 10 ptiver Terrace Dr 0 Franklin Rd < Pineview Rd CL Windsor Rd W > Windsor Rd E rn Riverside on Loxahatchee 01 'OV 0 3 Riverside Drive 3 =r CL OD (D C Park > > 0 < (D < Q Esrl Community Maps Contributors,FDEP, OpenStreetMap, Microsoft,Esri, TomTom,Garmin,SafeGraph,GeoTechnologies, Inc,METI/NASA, USGS,EPA, NPS,US Census Bureau,USDA,USFWS Page 1 of 15 0 450 900 Feet Vil l age of Te uesta WM-1 Page 216 of 496