HomeMy WebLinkAboutDocumentation_Regular_Tab 12_12/11/2025 Agenda Item #12. Regular Council A-1 STAFF MEMO Meeting: Regular Council - Dec 11 2025 Staff Contact: Allyson Felsburg Department: Utilities Consider Approval of a Proposal to Drill a Surficial Aquifer Test Well by Florida Design Drilling, LLC, through the Piggyback Agreement, for a Total Not to Exceed $44,480.00 SUMMARY: A The Utilities Department (UD) recommends approval of a Proposal to drill a Surficial Aquifer (SA) test well on the water treatment plant (WTP) site by Florida Design Drilling, LLC (FDD), through the piggyback agreement that was approved at the October 9th, 2025, Council Meeting, for a total not to exceed $44,480.00. Funds for this purchase will come from the Water Fund Capital Improvements Other Than Buildings account (401-412-663.600). At the November 3, 2025, Council Workshop the UD presented its' current and planned projects for FY26, including the transition from drilling a replacement well for SA19 to drilling a new SA well, Well 28. Well 28's current permitted location is between two residential properties and the FEC railroad that runs adjacent to N Old Dixie Hwy. The UD recognizes that this location is not favorable and is, instead, pursuing the feasibility of relocating the permitted location of the well to the northwest corner of the water treatment plant. While this revised location would provide easier access for staff and maintain sound abatement of the railway for residents there are certain requirements that must be met before formally requesting the relocation to South Florida Water Management District (SFWMD). The first requirement is assessment of the aquifer in the proposed location to ensure adequate quantity and quality of water. This assessment is performed via a test well that must be drilled by a certified well contractor. If water quality and production capability of the test well are favorable the UD will proceed with formal request for relocation of the permitted well site. Following regulatory approval, the UD will begin the process of design and competitive procurement of well construction services. The proposed timeline for this project, assuming the test well is successful, is as follows: Drill & test well at WTP: 1/20/26 — 2/27/26 Request regulatory approval for relocation of site: 3/2/26-4/1/26 Complete design of potable supply well: 7/31/26 Competitively bid well construction services: 8/3/26-10/8/26 Complete well construction: 11/30/27 This proposal is provided in accordance with the current piggyback agreement with FDD. The full piggyback agreement can be viewed by contacting the Utilities Department. Page 251 of 630 Agenda Item #12. WATER FUND CAPITAL IMPROVEMENTS OTHER THAN BUILDINGS- Account 401-412-663.600 Budgeted amount: $ 171007000 Available amount: $ 13,1007000 Amount of this proposal: $ 447480 Total Remaining: $ 170557520 This document and any attachments may be reproduced upon request in an alternative format by completing our Accessibility Feedback Form, sending an e-mail to the Village Clerk or calling 561- 768-0443. BUDGET INFORMATION: BUDGET AMOUNT AMOUNT AVAILABLE EXPENDITURE AMOUNT: $171007000 $1311 00,000 $44)480 FUNDING SOURCES: 401-412-663.600 Water IS THIS A PIGGYBACK: Fund Capitol Imp. Other then Bldgs. ❑ Yes M N/A DID YOU OBTAIN 3 QUOTES? ❑ Yes M N/A QUOTE 1 - BUSINESS NAME N/A QUOTE AMOUNT N/A QUOTE 2 - BUSINESS NAME N/A QUOTE AMOUNT N/A QUOTE 3 - BUSINESS NAME N/A QUOTE AMOUNT N/A COMMENTS/EXPLANATION ON SELECTION Approval of Proposal &TTACHMENTS 1) VOT Well 28 Test Well Proposal - Signed Page 252 of 630 Agenda Item #12. W\ FL RIDA DI ILUIMG November 14,2025 Allyson Felsburg Deputy Utilities Director The Village of Tequesta 901 N Old Dixie Hwy Tequesta FL,33469 afelsburg@tequesta.org Subject: Village of Tequesta Test Well at Site#28(R) Florida Design Drilling LLC(FDD)is pleased to offer this estimate to furnish all labor,equipment,and materials to perform well rehabilitation services identified below. The price below is derived from Broward County Water&Wastewater Piggyback Bid PNC212773313 1. The proposed work includes the following scope of work provided by JLA Geosciences, Inc.: The Village of Tequesta(Village)has a proposed public water supply well site that is west of the Florida East Coast (FEC)railroad owned for the railroad tracks. FEC is west of Old Dixie Highway and the Village water plant. The Village would like to consider moving the proposed well site 28 to the water treatment plant site and to evaluate the hydrogeology and water quality there,we request a proposal from Florida Drilling to drill at test well. It understood that you can utilize the pricing in the existing piggyback contract to price and perform the tasks below. Please provide your estimated available dates and pricing on a unit price basis. 1. Mobilize to a location at the Village water plant site with a drilling rig and support equipment. 2. Drill a borehole using the mud rotary method to a depth of approximately 130 feet,circulate to clear the hole of cuttings. FDD will be drilling to 150 feet,so the logging tool has room for the 130-foot interval. 3. Log the borehole using a geophysical logger including,caliper,gamma and dual induction(or short,long normal resistivity if DIL is not available). 4. Install a 2-inch diameter temporary well that includes 10 feet of slotted screen(0.020"or 0.030"slot or other approved slot)and pipe to land surface. Initial depth will be based on geology and geophysical log. 5. Install gravel pack and develop the well in interval#1 until it produces clear water for sampling. JLA will obtain the samples for field analysis. 6. After sampling,pull up the 2-inch diameter well to the next interval(#2)decided by the logging. Develop as per interval#1 and JLA will sample. 7. After sampling interval#2,pull up to interval#3,develop and sample as per intervals#1 and#2. 8. Based on the results,we may need to pull up and do a 41h interval. 9. After interval testing,remove the 2-inch diameter well,redrill the hole to the depth recommended by JLA based on sample results,and complete a monitor well at the JLA recommended depth using the well materials used for the test well provided they are in good condition. Gravel pack and cement the well in place.Develop the well. Leave the well casing 30 inches above grade. Install a lockable, sealing cap. 10. Prior cement hardening,install a protective casing outside the stickup casing that extends 30 inches above grade and 24 inches below ground. 7733 Hooper Road,West Palm Beach,FL 33411 www.FLDrilling.com Phone:561-844-2966 Florida Water Well Contractor#11148 Page 253 of 630 Agenda Item #12. W\ FL RIDA DRILLING Description Qty Unit Price Extended Line Item 24-Well Rehabilitation,Drill New Well 12 LF $3,540.00 $42,480.00 Line Item 70-Miscellaneous,Project Manager 10 HR $200.00 $200.00 Total $44,480.00 If you have any questions,please feel free to contact me at any time. Digitally signed by Jeremy Jeremy Al l en Allen Date:2025.11.17 09:27:11 Approved By: -05'00' Sincerely, Jeremy Allen,Village Manager Date: See Digital Signature Date Miguel Lequerica—Project Manager Florida Design Drilling LLC 954.234.0939 miguelgfldrilling.com 7733 Hooper Road,West Palm Beach,FL 33411 www.FLDrilling.com Phone:561-844-2966 Florida Water Well Contractor#11148 Page 254 of 630