Estimate
ADDRESS SHIP TO ESTIMATE 10766
DOUG CHAMBERS Mr.Doug Chambers DATE 02/09/2026
VILLAGE OF TEQUESTA Constitution Park-Dover Road
357 Tequesta Drive Emergency Asphalt Road&Apron Repair&
Tequesta,FL 33469 Mill&Pave 25 ft in Each Direction from Edge of Repair
pbc annual contract 2022-063
ACTIVITY DESCRIPTION CITY RATE AMOUNT
63-002 EMERGENCY RESPONSE(6 HOURS TO24 HOURS)PER 1 1,000.00 1,000.00
EACH
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 804 2.00 1,608.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 130 10.00 1,300.00
63-009 FINISH EXISTING ROCK BASE PER SY 226 7.50 1,695.00
63-010 FINISH GRADING PER SY 226 3.50 791.00
63-013 8"BASE INCL PRIME COAT PER SY 452 20.00 9,040.00
63-019 MILL EXISTINGASPHALT PAVEMENT(<5000 SY)PER 1/2 1.75 5,300.00 9,275.00
DAY
63-020 PORTABLE MILLING MACHINE PER HOUR 3 250.00 750.00
63-023 MISCASPHALT(>50 TONS)(INCL TACK)PER TN 59 200.00 11,800.00
63-168 3 CY LOADER TIME PER DAY 1 2,000.00 2,000.00
TOTAL $39,259.00
Digitally signed by Jeremy Allen
Accepted By Jeremy Allen Date:2026.02.14 11:11:36.05'00'
Accepted Date See Digital Signature Date
Page 1 of 1