Meeting: Regular Council - May 14 2026
Staff Contact: Doug Chambers, Director of Public Department: Public Works
Works
Consider Approval of Tequesta Drive Full-Width Milling and Resurfacing from Seabrook Road to
Short Avenue Change Order
This change order increases the existing purchase order with Wynn and Sons Environmental
Construction Services, LLC for FY2026 Capital Roadway Improvements Project.
The original contract amount is $614,319.09. This change order adds $57,405.00, resulting in a new
total contract amount of $671,724.09. This modification also increases Purchase Order No. 26-
001052 accordingly.
The change is necessary due to multiple open-cut roadway repairs within the project area. The
contractor performing the water main work is also completing open-cut repairs along Tequesta Drive.
Standard requirements call for milling and paving 50 feet beyond each open-cut repair. If completed
individually, this would result in multiple patches along the roadway.
To provide a more uniform and durable roadway surface, Wynn and Sons will mill and pave both
travel lanes on Tequesta Drive from Seabrook Road to Short Avenue, rather than completing isolated
patches.
Funding for this change order is budgeted and available in account 303-210-546.350.
This document and any attachments may be reproduced upon request in an alternative format by
completing our Accessibility Feedback Form, sending an e-mail to the Village Clerk or calling 561-
768-0443.
BUDGET INFORMATION:
BUDGET AMOUNT AMOUNT AVAILABLE EXPENDITURE AMOUNT:
$710)000.00 $911856.16 $571405.00
FUNDING SOURCES: 303-210-546.350 IS THIS A PIGGYBACK:
❑ Yes 0 N/A
DID YOU OBTAIN 3 QUOTES?
❑ Yes 0 N/A
Page 97 of 409
Agenda Item V.
COMMENTS/EXPLANATION ON SELECTIONThis is a current contract with Wynn and Sons
Environmental Construction Services Co. LLC.
.POTENTIAL MOTION / DIRECTION REQUE.
Staff recommends approval of the Change Order with Wynn and Sons Environmental Construction
Services, LLC in the amount of$57,405-00, increasing the total contract amount to $671,724.09.
XTTACHMENTS:
1.
Change Order
Estimate 10599 from WYNN SONS ENVIRONMENTAL CONSTRUCTION CO LLC
PurchaseOrder 26-001052
Page 98 of 409
Change Order No, 020_0
b elidep ite m V. Effective D ate
own 0 r: VIIJago of 7'eq n Usti
Contractor.* 'Fai0s)Rio 4,/ co 16 vd�0 ow
Contractors P roi-e a No.; lbf;
Engineer, Er7 Ir•IeeF'5 Project Pq Ao%9
o,:
Project. Wtf*A
Contract Name,
TIC e Co ntra Q i s m o d ifi-e d as fol I o W-5 up o n exec Uti a ri of t h is Cha nge Dade r.-
Descriptio n:M 1111 rig and Paving extend.L,,3d on Tecluesta Dr'Ive from Seabrook to Snort Ave, Insteado `
Patches and scattering rr�i1li� avi F� _have � f having�
ve I mill and pave so tNie, resur•f8cing is uniform
CHANGE IN CONTRACT PRICE CHAN G E i WCONTRACT TI M ES
n ate changes in ile nes if applicab18)
r� i r� J Contract OrO n-a I Con tra ct Ti rrl es:
Subst-antJai Completion"
/Y/0
} _ _ Ready for Final Payment:
days ordatL�s
J1ncrea_5e1 [Decreas-e] from preVIOUSlY aPPMVed Ch-angt2 [Inci-easel [DecFeas-el from previouslyroved
Change
r NfQ, to No,_ a Orders No- to No. •
SUbSta nti-21 COMpletion /V/A
-
,,,-• Ready for Final PI-3yment:
Contract Price p r•i o r to this Change Order: Co ntract Tip mes pri or to tPi i�Cha n e 0 rder:
u6steribal Completion: A�19
..._,
Ir
R-eady for rinal pay1ripi�
days or dates
[In-crease Decrease] of this Change Order: [I nc r j [De r a f this Changerd
er.
.
ubstarrti r-a I Ua pletion: A140 7 O heady for F1na I Payment
1
days or dates
Contract Price incorporating this Change Order; Contrast T-1Me5 wi th all approved Chap e 0rder•s:
-7
Ubstainbaf MpletEon:
—67/1 c2 V 1) R ea dy f o r F ina I Pay rye nt�
days or dates
RECOMMENDED: ACCEPTED. A CCE PTED:
By;
_ BY:
Own-e F(Auto frli r� u rra F rah i errs r•
Title,
; �1 t 6 Title Title
�, DateDate `
Page 99 of 409
Change order ----
page 1ofI
Agenda Item #7.
WYNN &SONS ENVIRONMENTAL CONSTRUCTION CO. LLC
7268 BELVEDERE ROAD
WEST PALM BEACH, FL 33411 US
+15616866077
rick.wynnandsons@a yahoo.com
Estimate
ADDRESS SHIP TO ESTIMATE 10599
DOUG CHAMBERS Mr. Doug Chambers DATE 10/28/2025
VILLAGE OF TEQ U ESTA Open Cut Removal, Replacement with Densities,Asphalt
136 Bridge Road Repair,Mill&Pave
Tequesta, FL 33469
pbc annual contract 2022-063
ACTIVITY DESCRIPTION QTY RATE AMOUNT
Open Cut Repair-1--,Tequesta Drive&Riverside Drive
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 35 2.00 70.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 4 10.00 40.00
63-009 FINISH EXISTING ROCK BASE PER SY 7 7.50 52.50
63-012 6"BASE(INCL PRIME COAT)PER SY 7 10.00 70.00
63-013 8"BASE INCL PRIME COAT PER SY 7 20.00 140.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 2 200.00 400.00
63-169 1 112 CY BACKHOE PER DAY 1 2,000.00 21000.00
Open Cut Repair-2-404 Tequesta Drive
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 200 2.00 400.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 12 10.00 120.00
63-009 FINISH EXISTING ROCK BASE PER SY 45 7.50 337.50
63-012 6"BASE(INCL PRIME COAT)PER SY 45 10.00 450.00
63-013 8"BASE INCL PRIME COAT PER SY 45 20.00 900.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 6 200.00 11200.00
63-169 1 1/2 CY BACKHOE PER DAY 1 2,000.00 2,000.00
Open Cut Repair-3-Short Avenue
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 650 2.00 1,300.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 58 10.00 580.00
63-009 FINISH EXISTING ROCK BASE PER SY 130 7.50 975.00
63-012 6"BASE(INCL PRIME COAT)PER SY 130 10.00 1,300.00
63-013 8"BASE INCL PRIME COAT PER SY 130 20.00 21600.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 18 200.00 31600.00
63-169 1 112 CY BACKHOE PER DAY 1 2,000.00 2,000.00
Open Cut Repair-4-Medical Center Entrance
Page 1 of Page 100 of 409
Agenda Item #7.
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 200 2.00 400.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 12 10.00 120.00
63-009 FINISH EXISTING ROCK BASE PER SY 45 7.50 337.50
63-012 6"BASE(INCL PRIME COAT)PER SY 45 10.00 450.00
63-013 8"BASE INCL PRIME COAT PER SY 45 20.00 900.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 12 200.00 21400.00
63-169 1 112 CY BACKHOE PER DAY 1 21000.00 21000.00
Mill &Pave Short Avenue East to Traffic Loop Seabrook
Road
63-019 MILL EXISTING ASPHALT PAVEMENT(<5000 SY)PER 1/2 6 5,300.00 311800.00
DAY
63-020 PORTABLE MILLING MACHINE PER HOUR 10 250.00 21500.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 265 200.00 53,000.00
Open Cut Repair-5-N.Cypress Drive&Tequesta
63-005 REMOVE EXISTINGASPHALT(FULL DEPTH)PER SY 150 2.00 300.00
63-007 SHALLOW EXCAVATION (DEPTH <4 FT)PER CY 17 10.00 170.00
63-009 FINISH EXISTING ROCK BASE PER SY 32 7.50 240.00
63-012 6"BASE(INCL PRIME COAT)PER SY 32 10.00 320.00
63-013 8"BASE INCL PRIME COAT PER SY 32 20.00 640.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 5 200.00 11000.00
63-169 1 1/2 CY BACKHOE PER DAY 1 2,000.00 2,000.00
Mill &Pave
63-019 MILL EXISTING ASPHALT PAVEMENT(<5000 SY)PER 112 2 50300.00 10,600.00
DAY
63-020 PORTABLE MILLING MACHINE PER HOUR 3 250.00 750.00
63-022 MISC.ASPHALT(0-50 TONS)(INCL TACK)PER TN 41 200.00 8,200.00
TOTAL $1385662.50
Accepted By
Accepted Date
Page 2 of 2 Page 101 of 409
#7.
Purchase Order
Village of Tequesta
345 Tequesta Drive P.O. NO. REQ. NO. ORDER DATE D O
Tequesta, FL 33469 26-001052 26-001052 12/22/2025 01052
•
VENDOR ADDRESS: SHIP TO:
01052
WYNN &SONS ENVIRONMENTAL CONST CO
7268 BELVEDERE RD
WEST PALM BEACH, FL 33411 ,
ry Date ORDERED BY PRICE SOURCE DEPARTMENT
LLIBBEY PIGGY-BACK PW
PO DESCRIPTION: ROAD IMPROVEMENTS FY 2026
QUANTITY DESCRIPTION UNIT PRICE AMOUNT
1 ROAD IMPROVEMENTS FY 2026 6147319.09 614,319.09
303-210-546.350 R&M-ROADS 614,319.09
NET TOTAL: 614,319.09
ROAD IMPROVEMENTS FY 2026
VILLAGE OF TEQUESTA
FINANCE DIRECTOR DATE
Page 102 of 409