HomeMy WebLinkAboutMinutes_Workshop_01/28/2008MINUTES
VILLAGE OF TEQUESTA
VILLAGE COUNCIL WORKSHOP
MONDAY, JANUARY 28, 2008
CALL TO ORDER AND ROLL CALL
The meeting was called to order by Mayor Jim Humpage at 5:47 p.m. A roll call was
taken by Village Clerk Lori McWilliams. Present were: Mayor Jim Humpage, Vice
Mayor Pat Watkins, Council Member Tom Paterno, Council Member Dan Amero, and
Council Member Calvin Turnquest. Also in attendance were: Village Manager Michael
R. Couzzo, Jr., Village Attorney Trela White, Village Clerk Lori McWilliams, and
Department Heads.
OLD BUSINESS
1. Discussion on the Tequesta Bridge
Mayor Humpage announced that input from the public and Council was needed on the
bridge issue, and commented there were some options the bridge had six spans, two
of which had been replaced; so the two on the west and the two on the east could be
replaced. Mayor Humpage referred to his notes from a prior meeting for the following
options: (1) the bridge could be replaced as it exists by changing out the other spans; or
(2) repair and raise it in the existing locations by capping existing piles so it could be
raised; or (3) remove and replace it at the existing level; or (4} replace the existing
bridge and raise it. It all came down to the cost. To replace the existing four sections
would cost $1.4 million to $1.7 million at the current time-the cost could be more when
it was actually done. The price to replace the bridge in its entirety at the same level
was approximately $3.25 million. The Council had no information on what it would
cost to raise the bridge either by increasing the pilings on the existing structure and
substructure or to construct a completely new bridge with all new substructure and
super structure.
Mayor Humpage advised there were people interested in raising the bridge; 77
residents were affected by the height of the bridge. The Mayor noted his job was to do
what was best for the tax payers. An engineer was present tonight to answer questions,
and this workshop was afact-finding venture to exchange ideas among the Council and
hear input from the audience.
Council Member Amero referred to a letter dated 12/6/07 from Kissenger Campo which
quoted $1.4 million to repair the bridge, but adding the additional costs brought the
figure up to $2.8 million. The bridge they had repaired in Pinellas County was
approximately $2.8 million for 5600 square feet; Tequesta's bridge was approximately
7600 square feet, so it might cost more. No demolition costs were outlined; this was not
a concrete cost--they had not included engineering or design fees which would be
Village Council Workshop Meeting Minutes
January 28, 2008
Page 2
approximately 15%, adding another $500,000. Council Member Amero commented it
would be a huge cost to repair the bridge, and almost double to replace it at the existing
height.
Mayor Humpage commented the Village would be responsible for the water; they would
be responsible for the cable. Council Member Amero noted there were a lot of
additional costs, which would need to be budgeted, and it could take 5 years or more to
replace it. Village Manager Couzzo commented he found the number hard to imagine,
and recommended doing a hard analysis, advising that Brian from Bridge Design
Associates and a gentleman from Kissenger Campo were present and could discuss
those numbers.
Council Member Amero responded there was no time for analysis, referencing a letter
from February a year ago which expressed concern for boater safety due to falling
debris, so something needed to be done sooner than later; the May report last year had
noted five areas on the bridge that_were in severe need of repair, and time was of the
essence.
Mayor Humpage referenced a 2/21/06 letter from Bridge Design Associates which noted
over the next 5 to 7 years the spans would continue to lose strength, so there was some
time, but he did not want to get to that time--costs would continue to rise, and a game
plan was needed.
Council Member Turnquest commented it was hard to come up with a game plan when
there was not a complete cost analysis. Mayor Humpage asked if money should be
spent to look at other options.
Vice Mayor Watkins expressed concern with the pilings; she felt the only reasonable
reason to replace the bridge entirely was if the pilings needed replacement; or if
someone could assure Council that raising the bridge would save them from the jet ski
spray that was helping to corrode the underside of the bridge. There would only be one
opportunity during their lifetime to do whatever was decided, and whatever was done
should last 50 years. The Vice Mayor wanted to be sure they did the best thing possible
for the Village and agreed with Council Member Turnquest it was incumbent upon
Council to do their best.
Brian Row, President of Bridge Design Associates provided a slide show of the existing
conditions of the bridge. Mr. Row felt the bridge could be raised 1-2 feet and keep the
foundations in place, but after 2 feet of raising the current pilings could no longer be
used, and the configuration would have to be different. Anew bridge would be needed
if it were raised anywhere between 2 and 5 feet. Council Member Amero asked for a
cost estimate for raising the bridge between 2 and 4 feet.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 3
Mr. Row explained to repair, replacing the remainder of the decks and some pilings,
would be between $1.3 and $1.7 million -using $1.5 as a median - if they wanted to
now take that repair and raise the bridge another 1 - 2 feet it would add another
$250,000 to the project. Mayor Humpage asked if that was because the pilings had to
be capped. Mr. Row responded there was a gap of about 12 inches between the
bottom side of the deck and the sidewalk, which could be filled in and brought up to the
height of the sidewalk with minimal additional weight to the existing pilings. 1-2 feet
would be doable with the existing substructure and would range between $1-$2 million.
which would mainly be labor costs. Mr. Row explained the spans that were already
done had been designed so that they could be reincorporated into a new project.
Vice Mayor Watkins asked if anyone was looking under the water at the pilings. Mr.
Row advised they had not sent a diver in but based on his 25-year experience, typically
the area where there were oysters or barnacles was the area of concern, and they had
looked at those areas and found nothing that led them to believe they could not do
repairs. The Vice Mayor asked if it would help at all with the issue of water hitting the
bottom of the bridge to move up a foot. Mr. Row commented the water spray from jet
skis was a possible contributing factor; there were now other materials to help with the
penetration, and jet ski spray should not be the only thing to focus on in deciding
whether or not to raise the bridge. Other considerations would be whether there was
stopping distance, aesthetics, or whether a foot or two would do anything for the
boaters.
The effect if the deck were brought up to the sidewalk was discussed. Mr. Row
advised there could be a more crowned bridge-the only restrictions would be sight and
stopping distance. A higher hump would mean speed must be slowed; with only a one
foot raise, the approach would be changed to counteract the distance, which would be
an extra cost. Mr. Row advised he had addressed the bridge issues -there were
ancillary issues; utility, roadways, slopes. To raise the bridge one foot he estimated 6-8
months total time. Repairing existing versus 2 feet would be the same with only 30-40
days difference if the stars were aligned and the right contractor selected. If raised
more, it would have to be done span by span and curing time of 5-7 days for each pile
bent changed would have to be added.
Mr. Row explained that a scour was the amount of soil lost under the bridge due to the
river flowing naturally or tidally; pilings created a disruption to flow which allowed soil to
be washed down the river, but he had not experienced any significant issues. Mayor
Humpage asked if the river was getting shallower, to which Mr. Row responded no, it
was getting deeper.
Joe Hall asked why there was discussion about raising the bridge; Mayor Humpage
explained that Council was just discussing all the options so they could choose the best
one for the Village.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 4
Patrick O'Grady and Dave Thompson of Kissinger Campo and Associates indicated
they had done past water inspections on the bridge structure and no problems with pile
deterioration had been found below the tide mark. The amount of stream bed lost to
scour was not enough to worry about; they had monitored the structure after the
hurricanes, and the channel bottom had behaved well there. The slabs were critical
and the damage was due to the jet skis. Patches in general were over concrete that
was corroded and as the concrete continued to deteriorate, the patches delaminated
and deteriorated. Mr. O'Grady suggested looking to the Coast Guard regarding the
requirements if the bridge were to be raised, and commented he did not believe the
structure had ever had a full scour evaluation, and he did not know if pile driving records
existed for this structure.
Dave Thompson, Structural Engineer, explained that as a follow up to their inspections
they came up with replacement vs. repair costs ($3.2 million to replace at current
height- based on DOT tools and on a similar project - a rough number that would need
further refinement based on engineering studies). Council Member asked what the
$3.2 million cost figure included. Mr. Thompson responded it was a rough number and
subject to change- indicative of the bridge structure, approach road modifications, and
seawall work that would be required, including new pylons and other components. In
estimating the repair they did not use the most recent cost estimates, they had used
previous similar projects to estimate costs for deck replacement, jacketing of the piles,
etc.
Mayor Humpage asked the longevity comparison of repair, changing out the existing 4
spans and the other elementary work, compared to the replacement of the bridge. Mr.
Thompson responded that generally, new bridges should be designed fora 75-year
service life. Repair costs would be more difficult to gauge, but proposed for the pile
jackets using the cathodic system that prevents further erosion. Cathodic piles were
estimated to last 20-25 years.
Council Member Amero asked if repair would change the vehicle weight that could go
over the bridge. Mr. Thompson responded the current limitation did not require posting;
once the deck was repaired the capacities would come back up. Life expectancy on the
worst deck was difficult to estimate-there had been a problem with the one that
required replacement and at some time in the future there could be a similar situation-
that was a concern that should be addressed. Mr. O'Grady explained the bridge was
posted at 5 tons which was done as a precaution since by keeping heavy loads off it
extended its life.
Mayor Humpage asked if the Village needed to concern itself in repairs that were done
that were failing or if they were sound enough for a year. Mr. Thompson explained that
was difficult to predict, and described how internal stresses were expanded. It was
difficult to gauge how quickly it would deteriorate, and it was a concern. Mayor
Humpage suggested having the police boat monitor it on a schedule.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 5
Mayor Humpage asked why the rebar could not be higher up in the concrete. Mr.
Thompson responded modern design had limitations, but the rebar was most useful at
the bottom of the slab where there was the most tension.
Mayor Humpage asked if the bridge were repaired, the pilings encased, and slabs
changed out, if it would be a 25-year bridge. Mr. Thompson advised 20 years for the
pilings but there were some things that weren't affected such as the depth of the piling.
Also, certain design criteria had to be met with modern design that was not in place
when the original bridge was constructed such as shoulder width, crash tested bridge
rails, etc. Mayor Humpage commented he understood the new slabs that had been
installed were 50 years longevity and they would be placing 8 more 50-year slabs and
25-year pilings.
Mr. Row explained that for the pilings that required jackets, at this point the modern
technology could predict a 25-year life on the pilings that had to be jacketed. There
might be a certain number of pilings that had a lesser life, and there were some piles
that were not showing any deterioration, and preventative maintenance could be done
on those. It was his opinion the substructure was putting it in the 30-35 year life, and
the decks were the weak component in this bridge.
Vice Mayor Watkins clarified total replacement of $3.2 million; asked what the repair
estimate would be. Mr. Thompson explained the repair estimate was $1.7 million, and
he recommended doing a more detailed study and comparing annualized cost of a new
vs. replacement structure. Mayor Humpage summarized that they were looking at a
repair of the substructure, replacement of the super structure, or replacement of the
bridge for $1.7 to $3.2 or $3.5 million; then if they raised the bridge it would be an
additional $250,000 for the first 2 feet to go higher serious studies were needed.
Council Member Amero commented Bridge Design Associates had recommended a
piece by piece replacement and shutting the bridge down every two years to continue
repairs, and asked if that was still their recommendation. Response was that report had
been written under the assumption a replacement would not be done. In that case,
every two years two spans would have to looked at and at that time they should look at
the other spans. The deck slabs would have to be replaced entirely based on the
progression. However, if the Village decided to replace all at one time this would be a
one shot deal.
Council Member Amero recommended sending them back to look at a couple of
different scenarios: 1) repair at current and 1-2 foot height with the unknowns
addressed (engineering, demolition, retaining walls, roadway approaches, design of
drainage, utility relocation, design and survey, construction phasing, and permitting
costs) and a timeline to do the repair and a cost at existing and at 1-foot and 2-foot
height. He explained the Vice Mayor went to Commissioner Marcus and tried to give
the bridge to Palm Beach County, and they didn't want it unless it was new.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 6
Vice Mayor Watkins expressed her opinion there would only be one shot at this and felt
it was incumbent upon the Council to come up with funding needed for a study of the
bridge to replace it as is or repair, and going up a foot or two, and to be sure the pilings
were safe. The Vice Mayor recommended in order to come to the best decision
possible that the Manager be directed to provide Council with a study, which they were
going to have to fund. She wanted to be sure they had taken the time to come to the
best possible conclusion for the Village. Council Member Amero agreed.
Council Member Paterno commented even if the bridge were repaired the sidewalks
would deteriorate. Mr. Row advised the guard rails, sidewalks, and decks would be
included in the project. Regarding maintenance cost after repair--there would be
components that would need ongoing maintenance-every 3 to 5 years it might cost
$350,000. After replacement, the first 15 years typically no repairs would be needed
Council Member Paterno advised his first concern was the safety of the residents and
then cost; he wanted it done so that sa#ety was not a problem at any cost, and noted it
sounded like potentially the replacement could be the same cost as the repair wi#hin the
first 15 years.
Mr. O'Grady commented with many repaired bridges, when inspection was done they
were still listed as functionally obsolete and that would probably be the case here
because the original construction did not meet current standards. Mr. Row commented
the repair proposed for $1.5 million would remove the clearance and barrier problems
being discussed. Mr. Row advised it was unknown what the Coast Guard and other
environmental agencies would impose for a new structure, and if the bridge were
replaced it would expose the Village to a totally new redesign, Coast Guard issues,
environmental issues, and water beds -surrounding bridges had had to raise
significantly due to these new outside requirements. Other issues that would have to
be addressed included engineering studies, permitting, right-of-way acquisitions, etc.
Mr. Row advised if the Village was doing maintenance and not substantially changing
there would be much less bureaucracy, although the agencies would all have to be
satisfied; while going to a new replacement could take 3-5 years due to permit issues.
Actual construction could take one year. If doing a repair there were ways to structure
the contract to minimize the time the bridge would have to be closed- bringing it down
to months in lieu of years.
Council Member Turnquest commented he saw an open bidding war between the two
engineers. He was seeing punch, counterpunch versus repair and replace.
Mr. Thompson suggested a study to determine actual costs. Council Member
Turnquest commented that over a 10-15 year period, repair vs. replace came out to
basically the same costs. With replacement, residents would not have to be burdened
every few years; and he was concerned to inconvenience residents and businesses
Village Council Workshop Meeting Minutes
January 28, 2008
Page 7
with repair. Council Member Turnquest asked how long after permits were issued it
would take to replace the bridge, and what could be done offsite to shorten the time.
Mr. Thompson responded that new bridge construction could be speeded up by having
new capstones in position; looking at the maintenance of traffic issues such as detours
or staged construction; alignment of the bridge could be offset slightly to assist in the
staged construction. Council Member Turnquest asked how structurally sound would it
be to have one lane open when one side was being demolished safely. Mr. Thompson
commented that would have to be reviewed through astudy-they would have to look
at a post tension structure and make allowances, but it was important to look at this in
engineering studies.
Mr. Row clarified that repair of the existing bridge would not require any road closure
and maintenance would be of the substructure, and it was doable to use one span only.
Discussion ensued regarding power lines that could be a problem.
Vice Mayor Watkins commented this could not wait five years, she didn't want to bet on
the integrity of the bridge, because the Council was responsible for the safety of the
residents first and foremost.
Village Manager Couzzo commented if they looked at the replacement, everything done
during the 0-5 years would then be thrown away, and there would potentially be some
inconvenience. The analysis had gone from 4 to 2 scenarios and an analysis could be
created to assist in a decision with shutting down of the bridge, cost of reassigning
public safety personnel, the impact of it over time; and he agreed if this was done as
aggressively as possible, it could be done in 45 days. The Manager commented they
needed a spreadsheet of the costs and particulars, which staff could put together.
Mayor Humpage asked the time frame to raise the bridge 2 feet, to which Mr. Row
responded approximately 1 week per bend, so with 6 bends it would take an additional
six weeks for cure times. Council Member Paterno noted that would add cost; Mr. Row
responded the contractor should sequence it out. Mayor Humpage suggested working
24/7 to cut down the time. Mr. Row noted many things could be structured into the
contract for contractor enticements.
Mayor Humpage announced to the audience that the numbers they were hearing are
preliminary numbers, and the engineers were not getting paid to be present they had
come from Tampa and were present to help Council make a decision. He expressed
his thanks to the engineers. The Mayor commented there was $90,000 in this year's
budget to do the design, and consensus was needed to direct the Manager to spend
some money on serious engineering in order to answer all their questions. Mayor
Humpage advised the residents there would be a time when financing would have to be
considered and asked residents to let Council know what they wanted. Council
Member Amero indicated he felt it would be premature to proceed with spending the
Village Council Workshop Meeting Minutes
January 28, 2008
Page 8
$90,000 for bridge design, asking that the Manager first come back with two options-
one to keep the bridge as is; the additional cost, and raising 1-2 feet. Mayor Humpage
added that numbers were also needed for the amount of overtime during the period the
bridge was shut down.
Village Manager Couzzo commented there was an account with money in it which could
be used for a cost estimate report, which would provide pros and cons for the scenarios.
The Vice Mayor asked if the Village Manager needed official direction to use some of
the $90,000 the funds for the study. Council Member Amero asked the engineers for
an estimate; the Manager commented he did not think it would be a lot. Council
Member Paterno expressed his opinion the Manager's office could supply a lot of these
numbers. Village Manager Couzzo advised that his office was currently working with
other utilities to relocate their lines and place them under the water, commented his
office could not supply drainage design, etc., and indicated he would like to use both
companies. Vice Mayor Watkins expressed her opinion the Council needed to direct
the Manager to spend a dollar amount to provide a complete study.
PUBLIC COMMENT
Joe Baker, 73 Fairview East, asked why raise bridge at all if it did not buy anything but
would just waste money; and commented Council should decide what was wanted and
then go out to bid. Village Manager Couzzo advised that at the moment they were
looking for help doing some of the estimating components for two scenarios, hiring
professional consultants based on their professional expertise, that you didn't bid the
dollars, you bid the professional qualifications. Mr. Baker commented if they didn't
know a firm's professional qualifications they could go out with the same requirements
for everyone to place bids. The Village Manager explained there was a State statute
which required this to be done a certain way-an RFP for consultants was based on
who had the best expertise in the area to do what was needed. Discussion ensued.
Village Attorney White advised under State statute Chapter 287, the Competitive
Negotiations Act, which applied to engineers, landscape engineers, architects, and
surveyors, there was a threshold below which one did not have to use the practice; for
example, if it was under $25,000 for a planning consultant one did not have to go
through this process. The Village was at that threshold. They were looking for a little
more information on whether to replace or repair. Once that was determined then the
Village would have to go out for RFQ-Request for Qualifications--which a committee
would narrow down and bring to Council to choose according to expertise in the field;
then they would negotiate a price. If a price could not be reached with the first choice, it
would go to the second, third, etc. Attorney White advised she was hearing that they
were not quite there yet and still needed information. The question to Council was
would they allow the Manager to utilize some of these experts to get this information for
him. The Vice Mayor commented that she had been talking about using funds for the
study. Council Member Amero asked if they were going to pay each consultant
approximately $18,000 to do the study; Mayor Humpage reminded Council they had
been adamant about having a second report. The Village Manager advised the cost for
Village Council Workshop Meeting Minutes
January 28, 2008
Page 9
a study would be much less. Mr. Baker commented he lived on the west side of bridge
and wanted to minimize the time he had to go around the other side of the country club.
Mayor Humpage responded if the bridge were repaired it would last 25-30 years; if it
were replaced it would last 75 years.
Joe Hall, 159 Country Club Drive, asked why they were talking about raising the bridge,
and that this was the second meeting on the bridge and they were still at the beginning.
The Mayor explained Council had requested another opinion; and raising the bridge
was an issue of longevity which would create a 75-year bridge; to repair was only a 25-
30 year bridge.
Brad Mayo, Bermuda Terrace, commented one of the main reasons people on the other
side of the bridge wanted it raised was to accommodate bigger boats. The Mayor
advised there were 77 taxpayers who had bigger boats. Mr. Mayo suggested having
Martin County and Palm Beach County people chip in to help pay; and expressed his
opinion that accommodating bigger boats would raise the tax base and the Village
would see their $250,000 expenditure come back in a reasonable time frame.
Bill Watkins, 167 River Drive, commented raising the bridge would lessen the damage
to the underside of the bridge due to salt spray.
Betty Nagy, Shay Place, commented since these people did not live in Tequesta it was
unfair to raise taxes on residents for them to have bigger boats. Mayor Humpage
responded that whatever Council decided was fair to their 77 taxpayers, if it were
decided to raise the bridge that would also benefit the residents, then they could
approach non-taxpayers to see if they want to help fund as long as it didn't
inconvenience Village taxpayers, and it was not fair to burden the 3200 ad valorem
taxpayers with what would benefit only 77. Council Member Amero advised a
disgruntled resident suggested making it a toll bridge for non residents.
Joe Baker commented he understood the money aspect, and he lived on west side of
the bridge and if raised it would be an inconvenience to him to have to drive around.
Jeff Davis, 136 Gulfstream Drive, suggested privatization, charging a user fee to utilize,
and let the Village make money off of it by leasing it out.
Bill Hayes, 148 Gulfstream, commented he was glad to have Jeff's idea, and asked to
have different structures, using different materials to make it more structurally sound, or
even a tunnel, and suggested alternatives methods be considered in the study. The
Mayor reported someone had suggested building the bridge somewhere else,
demolishing the old bridge, and inserting the new one all in one day.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 10
Mr. Row, Bridge Design Associates, commented there were alternative materials but
they had already been incorporated. The Vice Mayor commented they needed to be
sensitive to the time frame.
Dottie Campbell, 30 Eastwinds Circle, commented she owned property on Tradewinds
Circle and resided on Eastwinds Circle, so she was 2 of the 77. She encouraged
Council not to not change the bridge to allow more water traffic. Mrs. Campbell
recommended using the money for compliance--she saw the young kids on their water
craft without their safety gear. Mrs. Campbell recalled there once was a plan to have
another bridge, which never happened. This bridge originally belonged to the county
and Tequesta did not want it, but the county gave it to the Village because they did not
want the maintenance. Mrs. Campbell urged everyone to show up and vote in the next
day's election.
Randy Crop, Turtle Creek, Martin County, commented he was a bridge builder, and
explained that raising the bridge during new construction would not take additional time;
raising during rehabilitation would take additional time. If the bridge were raised it would
eliminate the jet ski spray problem. Mr. Crop cautioned to be careful on spending
double fees because it was not necessary--competitive negotiations were needed.
Council Member Paterno questioned if half and half could realistically be done, to which
Mr. Crop responded yes, but costs would be increased more than 25%. He advised that
getting the utilities off the bridge would allow construction to go much faster.
Bob McClockling, Starboard Way, asked how much the longevity of the bridge would be
increased with it raised 1 foot for the jet ski spray. Mr. Thompson responded there
would not be a significant difference, it might improve, but it was hard to say.
Brad Mayo asked if coating the concrete with epoxy would minimize the jet ski spray
damage as opposed to raising the bridge, to which the response was the difficulty was
sealers could retain moisture.
Council Member Turnquest expressed his opinion a better cost analysis was needed on
three scenarios: repair, repair with increased height, and replacement. Council
Member Amero agreed with getting a better cost analysis. Village Manager Couzzo
suggested the analysis cost not to exceed $5,000.
Consensus of Council was to get cost analysis on repair, repair with increased height,
and replacement, not to exceed $5,000.
A break was taken at 7:55 p.m.
The meeting reconvened at 8:17 p.m.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 11
2. Discussion on Annexation Issues
Mayor Humpage announced Council direction was needed, and asked what the goal
was in regard to annexation. Council Member Amero responded, to square off borders,
and increase the tax base. Council Member Paterno commented, efficiency. The Vice
Mayor cautioned to be careful because some areas could increase costs and she was
not in favor of anything that was not voluntary residential.
Village Attorney White explained the annexation process. Voluntary annexation by
petition was the easy method; the only other way to annex an area with registered
voters in it was to have a referendum, and if it failed that area could not be proposed for
annexation again for two years. Attorney White explained the process for annexing
commercial land, but it was her understanding the Village was only looking at annexing
residential. There was also involuntary annexation where the Village could pass an
Ordinance and then it would go to Referendum in the proposed annexed area. Council
Member Amero commented the only way to get those areas would be to provide an
incentive.
Council Member Paterno suggested using the VIP program as an incentive; and
possibly not extending the lease for the County Fire Department so that the people had
to pay or involuntarily annex. He wanted to approach it in a more positive way. Council
Member Amero suggested raising the bridge as an incentive; annexation or a toll
bridge.
The Mayor commented that incentives of services that were available to residents were
okay but the real issues in unincorporated pocket areas were code-landscaping,
fences, etc., and this would be a dramatic impact in Bermuda Terrace. They could be
given 3-5 years to come into compliance; they would save 25% on water bills by no
longer paying a surcharge; the bridge was a volatile issue. The Village had made $900
at the last movie by charging non-residents and everyone had been happy. Someone
who was proactive with these groups was needed to educate on Village services; the
County charged these residents 2.8 mills for services that we would provide. The
Mayor also wanted to be proactive by educating the people, commenting the two
reasons people didn't want to come in were taxes and code problems. Council
Member Paterno asked if the Village could soften the taxes by grandfathering or
prorating to bring them in. Attorney White advised that would have to be looked into to
see if it could be done.
Mayor Humpage commented a game plan was needed, and the condos in the
unincorporated section of Beach Road should be considered. The Village needed the
County to step up to the plate and say they were violating County codes. Mayor
Humpage suggested each Council member appoint a person and form a committee and
bring back input to Council.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 12
PUBLIC COMMENT
Brad Mayo, Bermuda Terrace, agreed no one wanted to pay the higher taxes-they did
not feel the services would offset the higher cost, and knew the Fire Department would
respond anyway if their house caught fire. Mr. Mayo suggested by offering incentives
and lightening the codes the Village would gain a better foothold; and commented there
were guys who people in Bermuda Terrace would like to clean up their lots. It was a
comfort to Bermuda Terrace residents to be able to have their boats in their front yards
to work on for aweekend-if someone left it there too long the other residents would
complain they had their own little police force. Also, they felt Tequesta had a petty
and bored police force who went out of their way to do unnecessary things. Council
Member Paterno asked for an example. Mr. Mayo responded, pulling kids over for no
reason; telling kids there was an ordinance that they couldn't skateboard in the parking
lots; targeting people they didn't like. The Village Manager asked for a list of items that
he could share with the Police Chief, and the Mayor agreed. Mr. Mayo expressed his
opinion a lot of the Bermuda Terrace residents would be happy to come in but have it
tempered by something like a 5-year plan. Mr. Mayo asked if the 2.8 mills now paid to
the County would go to Tequesta if they annexed, which was confirmed; he asked how
their taxes would go up. The Village Manager responded they would pay their
assessed value times the Village millage rate, less their homestead. Council Member
Amero suggested a meeting hosted by County P&Z staff and give out a brochure that
would break down the taxes and the offset in savings; Jupiter had done that and had
been successful on every single annexation in the `90s. Mr. Mayo suggested doing this
type meeting for all unincorporated areas, and commented almost everyone he talked to
who Lived on the other side of the bridge wanted it raised. Council Member Paterno
asked if over the last 5 years the newer people that had moved in were more for
annexation, to which Mr. Mayo responded yes. Council Member Amero commented he
had misspoken-Jupiter did not annex Jonathan's Landing-the reason being they had
bridges and roads that needed repair and it would have been a tremendous amount of
money to fix them.
Mayor Humpage commented he had spoken to Waterway Village residents; they would
love to come in but there were serious drainage problems. He had suggested the
possibility of the Village working with them over a 5-year period and assessing them for
half with them picking up the other half, and they were not unreceptive to that.
Discussion ensued.
Vice Mayor Watkins commented the only viable way was voluntary annexation, and
everyone was going to ask what the benefit would be to them; the Village's best assets
that were easy to sell were police and fire, and then the cost for the parks and
recreation for which they would now be charged as non residents. Non-resident fees
were only for special events and classes. Council Member Paterno commented on the
cost of the parks and recreation to the Village and felt the Village could be more
positively aggressive on taking care of their own by charging 100%. Vice Mayor
Village Council Workshop Meeting Minutes
January 28, 2008
Page 13
Watkins commented Tequesta had children here that used JCP and if Tequesta started
charging to use the parks they would be opening a can of worms.
Tod Mowrey, Cotleur and Hearing, talked about divisiveness among entities which
caused issues and the need to determine the goal, whether voluntary or involuntary.
Voluntary was easier and could be done first, and those people would talk about how
great it was to become part of the Village. Mr. Mowrey suggested creative ways to help
annexation-instead of looking to code enforcement, create a special district for a
particular neighborhood so they could work through their neighborhood; the Village
could change the zoning later if they wanted; water and sewer issues were tough. Mr.
Mowrey commented Jupiter Teen Challenge looked forward to becoming a part of the
Village as a voluntary annexation.
Vice Mayor Watkins commented she had no problem speaking to anyone positively
about this Village. She did have an issue with all of a sudden starting to charge for
everything and didn't know how this would be perceived; the long time residents were
used to using these facilities. The Vice Mayor commented she and her husband had
lived in Bermuda Terrace. She stated she would have difficulty charging for parks and
recreation.
Mayor Humpage suggested since the Business Forum went well to promote something
similar to open dialogue. Council Member Turnquest asked if separate communities
should meet on different nights. The Mayor thought it would be more impressive to fill
the Council chambers with everyone. Vice Mayor Watkins recommended the first one
be done as an open house. The Mayor suggested having the Village Clerk pull up the
comparisons for the residents on the Property Appraiser's site.
Council Member Paterno commented Tequesta's garbage pickup cost around $12 a
month and Bermuda Terrace was going to $21 a month, and all those things added up.
Council Member Paterno asked if the attorney knew of anything other communities had
done that worked. Village Attorney White advised they had done a brochure and
community campaigns, going to homeowner associations to tell them how it would be
better for them as opposed to punishing them; Lantana tried to annex across I-95 for a
long time and were only able to get one piece.
Consensus was to hold a meeting in March; the Village Clerk was asked to contact
Council for open dates in March after the election, on a weekend or evening at 6:30 or
7:30 p.m.
Joe Hall asked if Karen Marcus was trying to get Bermuda Terrace to annex into the
Village, but was told no. Another areas were mentioned, which could be invited. A
resident mentioned there was some animosity between Village residents and people in
the unincorporated areas.
Village Council Workshop Meeting Minutes
January 28, 2008
Page 14
Adjournment
Council Member Turnquest moved to adjourn the meeting; seconded by Vice Mayor
Watkins, and unanimously carried.
Respectfully submitted,
~~n~civ~ee~
Lori McWilliams, CMC