HomeMy WebLinkAboutAgreement_General_06/24/2011 VILLAGE OF TEQUESTA
WATER SYSTEM AND GENERAL UTILITY /CIVIL PROJECTS
WORK AUTHORIZATION
Tequesta Drive Drainage Improvements
Seabrook Road to Short Avenue
This Work Authorization authorizes ARCADIS G &M, Inc. to perform the work set forth
herein and is issued pursuant to the "Professional Engineering Consulting Services
Agreement for Water System and General Utility /Civil Projects" dated November 17,
2005. All terms and conditions of said agreement shall be applicable to this Work
Authorization.
SCOPE
The Engineer understands that this work authorization shall cover the design and
development of bidding documents for the Tequesta Drive Drainage Improvements for
approximately 1,000 LF of 48 -inch RCP. Note that permitting is not included since it is
anticipated that a permit is not required by the regulatory agencies for what is considered
to be a direct replacement of existing drainage pipe.
The following specific tasks will be performed by the Engineer.
1. Prepare design plans to incorporate the following:
• Replacement of the 48 -inch RCP that runs between Seabrook Road and Short
Avenue., approx. 1,000LF pipe only, drainage structures not included
• Tequesta drive roadway repairs between Seabrook Road and Short Avenue
• Overlay and striping of Tequesta Drive from Seabrook Road to Short Avenue
• A maintenance of traffic plan
• Standard details of construction
2. Prepare bid documents to include the plans noted above, technical specifications and
upfront documents.
3. Attend a bid opening, evaluate the bids and make a recommendation of award.
4. Provide non- fulltime construction oversight in conjunction and support of Village
staff.
5. Perform Contract Administration services.
Page 1 of 3
COMPENSATION
For Scope Ttems 1 thru 3, the Engineer shall be paid a lump sum amount of seventeen
thousand five hundred dollars ($17,500.00).
For Scope Item No. 4 the Engineer shall be paid on a time and material basis in
accordance with the rate schedule in the Agreement for a not to exceed amount of five
thousand dollars ($5,000.00). This amount shall not be exceeded without prior approval
from the Village.
For any services that will be sublet, the Engineer shall order their services after obtaining
the written authorization of the Client. The Subcontractor shall work directly for the
Engineer as delineated within the November 17, 2005 agreement.
Note that the compensation referenced above excludes any permit fees, survey, or legal .
ads required for bidding.
TIME OF PERFORMANCE
The Engineer will complete Scope Items 1 and 2 within 60 days of receipt of an executed
authorization, exclusive of delays beyond the control of the Engineer.
For Scope Item No. 3 the Engineer will complete this work commensurate with the
Village purchase and public bidding requirements for construction projects.
For Scope Items No. 4, the Engineer will complete this work in accordance with the
construction contract.
This authorization can be cancelled with or without cause by the Village with 30 days
written notice. Should said cancellation occur, the Engineer will be paid for all services
performed through the cancellation date.
Page 2 of 3
ACCEPTED BY:
VILLAGE OF TEQUESTA
(Tequesta Drive Drainage Improvements — Seabrook Rd to Short Ave.)
Michael R. Couzzo, Village Manager
DATE: Cy�zs't 1 h
ARCADIS G &M, INC.
(Tequesta Drive Drainage Improvements — Seabrook Rd to Short Ave.)
Thomas C. ensen, P.E., Vi e President
DATE: / 1
Page 3 of 3
AIR" ARCADIS ARCADIS U.S., Inc.
Infrastructure • Water • Environment Buildings 2081 Vista Parkway
West Palm Beach
Transmittal Letter Florida 33411
Tel 561 697 7000
To: Copies:
Russell K. White Fax 561 697 7751
Public Services Director
Village of Tequesta Florida License Numbers
136 Bridge Road
Tequesta, FL 33469 Engineering
EB00007917
Geology
GB564
From: "C)" Date:
Kris Dean, P.E. June 7, 2011 Surveying
LB7062
Subject: ARCADIS Project No.:
Tequesta Drive Drainage — Seabrook to Short RF005106
We are sending you:
® Attached ❑ Under Separate Cover Via the Following Items:
❑ Shop Drawings ❑ Plans ❑ Specifications ❑ Change Order
❑ Prints ❑ Samples ❑ Copy of Letter ❑ Reports
® Other:
Copies Date Drawing No. Rev. Description Action*
2 6/6/11 Work Authorization
Action`
❑ A Approved ❑ CR Correct and Resubmit ❑ Resubmit Copies
❑ AN Approved As Noted ❑ F File ❑ Return Copies
❑ AS As Requested ® FA For Approval ❑ Review and Comment
❑ Other:
Mailing Method
® U.S. Postal Service 1 51 Class ❑ Courier /Hand Delivery ❑ Fed Ex Priority Overnight ❑ Fed Ex 2 -Day Delivery
❑ Certified /Registered Mail ❑ United Parcel Service (UPS) ❑ Fed Ex Standard Overnight ❑ FedEx Economy
❑ Other:
Comments:
Page:
g;laprolectslwrlrfprojects\lequ ta111- 1061white _tegdrdrainagewe_060711,doc 111
ARCADIS ARCADIS U,S , Inc,
Infrastructure Water• Environment • Buildings 2081 vista Parkway
West Palm Beach
Florida 33411
Russell White Tel 561 697 7000
Village of Tequesta Fax 561 697 7751
345 Tequesta Drive www.arcadls- us.com
Tequesta, FL 33469
Subject:
Existing Drainage System Repairs WATER RESOURCES
Dear Mr. White:
As requested, we have reviewed the area along Tequesta Drive, from Short Avenue
to Seabrook Road (approx. 1050 LF) that has been experiencing drainage pipe joint Date:
failure. We have evaluated several options for the repair of this section of pipe which June 2, 2011
are outlined below:
Contact:
Kris Dean, P.E.
1, Pipe Lining — Line the existing pipe for the full length with Insituform, repair Phone:
three roadway failures and overlay Tequesta Drive from Short Avenue to 561.697.7063
Seabrook Road. This will seal all existing joints and seal any possible pipe
failures for the full length. email:
Kristop her. dean @arcad is-
Estimated Cost: $350,000 us.com
2. Joint Repair — Repair up to 10 known joints that have failed with a
polyurethane coating system installed on the interior of the joint, perform a Our ref:
TV inspection of the remaining portions of the pipeline, repair three
RF005106.0001
roadway failures and overlay Tequesta Drive from Short Avenue to Seabrook
Road. Florida License Numbers
Estimated Cost: $175,000 Engineering
EB00007917
3. Pipe Replacement — Replace the existing pipe for the full length, repair three
roadway failures and overlay Tequesta Drive from Short Avenue to Seabrook Geology
GB564
Road. The existing concrete drainage structures will not be replaced. The
new pipe will be connected to the existing concrete drainage structures. LB7062ng
Estimated Cost: $350,000
Construction costs for Option 1 and Option 3 are approximately the same, yet
Option 3 will result in a new pipeline. Option 2 is significantly less than Option 3 but
only repairs the existing joints that are known to have failed. The results of the TV
inspection, included in Option 2, may require additional joint repairs or possible
replacement in sections which could significantly increase the costs. Based on the
above our recommendation is to proceed with Option 3.
Imagine the result
g:leprojectslwrlrf projectsltequesla \11- 106VWhite existing drainage sys repair letter 060211 doe
ARCADIS Russell White
June 2, 2011
The estimated engineering costs for Option 3 are itemized below.
Design and Bidding Services: $17,500
Construction Oversite: $15,000
Contract Administration: $5,500
Should you have any questions or wish to discuss further, please cell.
Sincerely,
ARCADIS U.S., Inc.
Kris Dean, P.E.
Senior Engineer
Page.