HomeMy WebLinkAboutResolution_03-12_04/12/2011 RESOLUTION NO 3 -12
A RESOLUTION OF THE VILLAGE COUNCIL OF THE VILLAGE OF
TEQUESTA, PALM BEACH COUNTY, FLORIDA, AWARDING A
CONTRACT TO FELIX ASSOCIATES OF FLORIDA, INC. FOR THE
TEQUESTA DRIVE DRAINAGE IMPROVEMENTS IN THE AMOUNT
OF $373,175.00 AND INCREASING THE FISCAL YEAR 2011/2012
BUDGET IN THE STORMWATER FUND #403 BY APPROPRIATING
FUND BALANCE IN THE AMOUNT OF $43,175.00 AND AUTHORIZING
THE VILLAGE MANAGER TO EXECUTE ON BEHALF OF THE
VILLAGE.
WHEREAS, the improvements were advertised for bid and Felix Associates of
Florida, Inc., the lowest bidder, has been approved by the Village's engineers to perform
the improvements;
WHEREAS, $330,000.00 was budgeted in the fiscal year 2011/2012 Stormwater
#403 budget for the project;
WHEREAS, an additional $43,175.00 needs to be appropriated in the
Stormwater Fund #403, account # 403 - 250 - 663.663, Drainage Improvements to fund the
improvements;
NOW, THEREFORE, BE IT ORDAINED BY THE VILLAGE COUNCIL OF THE
VILLAGE OF TEQUESTA, PALM BEACH COUNTY, FLORIDA, AS
FOLLOWS:
Section 1 Resolution No. is hereby approved awarding a contract to Felix Associates
of Florida, Inc. for the Tequesta Drive drainage improvements in the amount of
$373,175.00 and increasing the fiscal year 2011/2012 budget in the Stormwater Fund
#403 by appropriating Fund Balance in the amount of $43,175.00 and authorizing the
Village Manager to execute on behalf of the Village.
Section 2 This Resolution shall become effective immediately upon passage.
1
The foregoing Resolution was offered by Council Member D'Ambra who moved its
adoption. The motion was seconded by Vice -Mayor Arena and upon being put to a vote,
the vote was as follows:
For Adoption Against Adoption
Mayor Tom Paterno X
Vice -Mayor Vince Arena X
Council Member Abby Brennan X
Council Member Frank D'Ambra X
Council Member Steve Okun X
The Mayor thereupon declared the Resolution duly passed and adopted this 12 day of
April, 2012.
MAYOR OF TEQUESTA
Tom Paterno'
ATTEST:
LA
0 ,
Lori McWilliams, MMC +N{ 9 �'.A�
Village Clerk �9� :C:
:0,�.< r9�Fo ayes
.�RIDA 00
�� ARCADIS
ARCADIS U.S.,Inc.
Infrastructure, environment, buildings 2081 Vista Parkway
West Palm Beach
Florida 33411
Tel 561.697.7000
Fax 561.697.7751
Michael Couzzo www.arcadis-us.com
Village Manager
Village of Tequesta
345 Tequesta Drive
Tequesta, FL 33469
WATER RESOURCES
Subject:
Village of Tequesta
Tequesta Drive Drainage Improvement Project
Date:
October 24, 2012
Dear Mr. Couzzo:
Contact:
Attached please find three (3) copies of the Certificate of Substantial Completion for Sam Ciminello
the above referenced project. The Contractor requested substantial completion on Phone:
October 19 and based on the inspection performed on October 22, we found this 561-697-7007
project ready for its intended use. As such, we recommend acceptance of the
Certificate of Substantial Completion effective October 19, 2012. If the Village Email:
concurs, please execute and return two copies of the attached certificate to our Samantha.ciminello@arcadis-
us.com
office. Upon receipt we will forward to the Contractor for his records.
Our ref:
Should you have any questions or wish to discuss further, please call. wFSOO�s�.2oo0
SinCer2ly, Florida License Numbers
ARCADIS Engineering
EB00007917
. �_ Geology
s �� � \C, � ��t�<,� G6564
� �� ���-��. �. ���, �
Samantha Ciminello, E.I. Landscape Architecture
Water Resources Engineer I �C2s0002ss
Surveying
L67062
coPy: Russell White, VOT
Enciosed: Certificate of Substantial Completion
Final Punch List
CERTIFICATE OF SUBSTANTIAL COMPLETION
PROJECT: Tequesta Drive Draina e Improvement Pro'ect
DATE OF ISSUANCE: October 19,2012
OWNER: Village of Tequesta
OWNER's Contract No.: N/A
CONTRACTOR: Felix Associates of Florida,Inc.
ENGINEER: ARCADIS US,Inc.
This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following
specified parts thereof:
Complete Project
TO: Village of Tequesta(Owner)
And To: Felix Associates of Florida,Inc. (Contractor)
The Work to which this Certificate applies has been inspected by authorized representatives of OWNER,
CONTRACTOR and ENGINEER,and that Work is hereby declared to be substanrially complete in accordance with the
Contract Documents on
October 19,2012
DATE OF SUBSTANTIAL COMPLETION
A tentative list of items to be completed or conected is attached hereto.This list may not be all-inclusive,and the failure
to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with
the Contract Documents.
EJCDC No. T910-8-D(1990 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America.
From the date of Substantial Completion, the responsibilities between OWNER and CONTRACTOR for security,
operation,safety,maintenance,heat,utiliries,insurance and warranties and guarantees shall be as follows:
RESPONSIBILITIES:
OWNER: All per contract
CONTRACTOR: All per contract
The following documents are attached to and made a part of this Certificate: Final Punch List
[For items to be attached see definition of Substantial Completion as supplemented and other specifically noted
conditions precedent to achieving Substantial Completion as required by Contract Documents.J
This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents nor is it a
release of CONTRACTOR's obligation to complete the Work in accordance with the Contract Documents.
Executed by ENGINEER on 1�Z5 � �� ,2012
ARCADIS US,Inc.
By: ���
Kris Dean, P.E.
CONTRACTOR accepts this Certificate of Substantial Completion ,2012
Felix Associates of Florida,Inc.
By:
Vincent Amato,President
OWNER accepts this Certificate of Substantial Completion on ,2012
Village of Tequesta ___
y
By. /� � �-' � t �'�
Michael Couzzo,Village Manager
FINAL PUNCH LIST
Village of Tequesta
Tequesta Drive Drainage Improvement Project
FINAL PUNCH LIST
October 24, 2012
1. Replacement of light poles to proper working order with new lamps provided by FPL
2. Final striping and placement of RPMs along Tequesta Drive
3. Repaving of asphalt driveways on south side of Tequesta Drive
4. Cleaning up of excess asphalt on concrete driveways on south side of Tequesta Drive
5. Repairing all damage incurred to concrete surfaces due to Contractor activities and equipment
6. Re-grading and repaving of brick driveway on south side of Tequesta Drive
7. Install internal joint seals for leaky joints in new storm sewer
8. Replacement of traffic loops at Tequesta Drive and Seabrook Road
9. Submittal of Record Drawings
1. Streetlight and electrical boxes are also to be noted on plans
10. Submittal of any outstanding shop drawings, test results, reports, etc.
11. Maintenance of Trees along Tequesta Drive
1. Removal of dying branches
2. Shaping of trees that were over trimmed along Tequesta Drive to provide a more
symmetric profile
12. Irrigation Repairs
1. Make necessary repairs along east side of Short Ave where equipment was stored
2. Adjust sprinkler and mister heads along Tequesta Drive to ensure all new sod is being
properly irrigated
13. General Site Restoration
1. Placement of sod near Short Ave.
2. Removal of all excess asphalt near the edge of newly paved areas
3. Maintenance to be performed on new sod to ensure it will allow proper drainage of newly
paved areas and create a more uniform swale
14. Release of Liens
15. Release to Engineer
16. Release to Owner
17. Final Pay Application
18. Balancing Change Order