VILLAGE OF TEQUESTA
WATER SYSTEM AND GENERAL UTILITY/CIVIL PROJECTS
WORK AUTHORIZATION
Beach Road (SR707) Water Main Replacement
This Work Authorization authorizes ARCADIS G&M, Inc. to perform the work set forth
herein and is issued pursuant to the "Professional Engineering Consulting Services
Agreement for Water System and General Utility/Civil Projects" dated November 17,
2005. All terms and conditions of said agreement shall be applicable to this Work
Authorization.
SCOPE
The Engineer understands that this authorization is to cover engineering services related
to the design, permitting and engineering services during construction for the replacement
of a portion of the Beach Road water main extension from Beach Road to the Intracoastal
Waterway, approximately 750LF.
The following specific tasks will be performed by the Engineer.
1 Prepare design drawings and specifications.
2. Prepare permit support documents and submit to the P.B. County Health
Dept./FDEP and act as the Village's liaison with the Regulatory Agencies during
the permitting process. The Village will be responsible for payment of regulatory
permit fees directly to the agency.
3. Assist the Village with soliciting bids or negotiate the price with an acceptable
contractor and make a recommendation of award.
4. Administer the construction contract including the performance of all `Engineer'
duties as set forth in the construction documents.
5. Provide part-time inspection services including coordination with the Villages'
inspector.
6. Prepare record drawings based upon survey data provided by the contractor, and
certify the project to the appropriate regulatory agency.
Page 1 of 3
COMPENSATION
For Scope Items 1 thru 3 the Engineer shall be paid a lump sum fee of seven thousand
five hundred dollars ($7,500).
For Scope Items 4 thru 6 the Engineer shall be paid a lump sum fee of five thousand five
hundred dollars ($5,500).
TIME OF PERFORMANCE
The Engineer will complete Scope Items 1 thru 3 within 60 days of receipt of an executed
authorization, exclusive of delays beyond the control of the Engineer.
The Engineer will complete Scope Items 4 thru 6 commensurate with the construction
schedule which we anticipate to be 60 days.
This authorization can be cancelled with or without cause by the Village with 30 days
written notice. Should said cancellation occur, the Engineer will be paid for all services
performed through the cancellation date.
Page 2 of 3
ATTEST:
Lori McWilliams, CMC
Village Clerk
OF
[VILLAGE Sl~j SEgL ma
:1
N~ ,NCpRPpRgTED
..yam
VILLAGE OF TEQUESTA
~~ - ~.
Michael Couzzo
Village Manager
APPROVED AS TO FORM AND LEGAL
SUFFICIENCY
Trela White, Es .
Village Attorney
f ~
ARCADIS G&M, INC.
(Beach Road (SR707) Water Main Replacement)
l _.
~~
William ese, P.E., Vice President
DATE: ~ ?~' °~
Page 3 of 3