HomeMy WebLinkAboutDocumentation_Workshop_Tab 01_11/13/2007BRIDGE DESIGN ASSOCIATES, INC.
CONSULTING ENGINEERS
BRIAN C. RHEAULT', P.E.
Presiders t
October 22, 2007
Village of Tequesta
250 Tequesta Drive, Suite 300
Tequesta, Florida 334fi8
ATTENTION: Mike Couzzo
REGARDING: Tequesta Drive Bridge over the north fork of the l._oxahatchee River
PROJECT NO.: Ofi-597
Dear Mike:
Pursuant to your request, Bridge Design Associates, inc. can provide the design and
detailing and construction phase services for the rehabilitation of the existing Tequesta
Drive Bridge.
Our design will include the complete replacement of both sidewalks and traffic barriers and
roadway superstructure except for span #3 which was recently replaced. In addition to the
superstructure repairs we will identify and design repairs to the existing piles, pile caps, and
end bents as required.
Bridge Design is prepared to have the plans and specifications complete for a May 2008
start date. We believe the permitting can be accomplished to meet this schedule.
However, we have no control over the process and can only process the applications in a
timely manor.
Based on current bridge construction prices, we estimate the construction cost for the
bridge work #o be approximately $1.5 million. This does not include utility relocation or
major modfications in the drainage system at the approaches to the bridge.
Our services doe not include roadway or drainage design, utility relocation design, survey
or construction phase services or pemtitting costs.
As discussed, Bridge Design will honor the terms and conditions and rates as outlined in
our Annual agnaemerrt for structural engineering with Palm Beach County (Copy attached).
Tequesta Drive Bridge
Page 2
Our base fees for the services are as follows:
Bridge Design $42,000.00
Permitting $ 8,000.00
If you have any questions, please give me a call.
Respectfully,
BRIDGE DESIGN ASSOCIATES, INC.
Brian C. Rheault, P.E.
President
BCR:kedS:12006-Jobs106-5'[7 Tequesta Drive BridgelCorrespondencelpra 10-22-07.wpd
January 10, 2007
Department of F.eegineerin~
and Public Works
P.O. Box 21229
West Palm Beach. FL 33416-1229
(561} 684-4000
Fax: (561) 000-0000
www.pbcgov.com
^
Palen Beach County
soars. of county
Commissioners
Addie L. Greene, Chairperson
Jeri Koons, vice Chair
Karen T. Marcus
Warren Fl. Newell
Mary McGarry
Burt Aaronson
Tess R. Sanramaria
County Administrator
Robert Weisman
An FquolOPl~'~~n'
Affirnwt/ve Actin ~»rptoya~'
pttrltetl on recycled paper
Bridge Design Associates, Inc.
2035 Vista Parkway, Suite 200
West Palm Beach, FL 334'11
ATTN: Mr. Brian C. Rheault, President
RE: STRUCTURAL SERVICES -ANNUAL AGREEMENT
RESOLUTION NO.: 82004-2557
AGREEMENT DATED: DECEMBER 21, 2004
Mr. Rheau!#:
This fetter serves as your `'Notice to Proceed" with the above referenced
renews! of Annual Service, which was approved by the Board of County
Commissioners (Board) on December 5, 2006 (82006-2579).
The County User Departments wilt be in touch with you when your
services are required.
If you have any questions please feel free to contact me, at 56'1-684-4449..-
Sincerely,
~~
David Young .E.
Special Projects Manager
DY:jd
Attachment
pc: Administrative Services, Fiscal (LOT 8~ attachment)
Contrail Development & Control
Finance Departmenrt
CCNA File (w/original)
Charles Rich, Directar Engineering Services
John Chestier, Director of Capital Improvements
Bevis Beaudet, Dtreilor of Water Utilities
Richard Watesky, Director of E.R.M
Bruce Pelly, Director of Airports
Reading File
ec: Omelio A. Fernandez, P.E., Director, Engineering/Pubfic Works Ops.
Rose Ann Clements, EA (!, Roadway Production Div.
Jorge Hernandez, EA ttt, Roadway Production Division
1=:1ROADWAYICCNAWnnualslStruoturallBridge Design120071ANNUAL NTP BCC.doe
i
BRI~~aE ®IESBGIV AS'S®CiAT'E~,1NC.
CONSULTING ENGINEERS
BRIAN C. RHEAULT, P.E.
President
October 9, 2006
Pa{m Beach County Board of County Commissioners
c/o Engineering & Public Worics Department
2300 N. Jog Road
West Palm Beach, Florida 33411-2745
ATTENTION: David Young, P.E., Special Project Manager
RE: Annual Agreement -Structural Engineering Services
December 21, 2004 {R2004-2557)
Dear Mr. Young:
ROb°~} 2579
oEC o s zoos
This letter services as our official notification of interest in continuing our Agreement with Palm Beach .County for
professional services as specified in the above reference, for the period of December 21, 2006 through December
20, 2007.
We are in agreement that a[1 provisions in the original Agreement remain in full force and effect Per your request,
we are enclosing an updated fee schedule, State Registration, General, Automobile, and Professional Liability
Insurance Certificates and all appropriate affidavits.
Please indicate your acceptance of this proposal by proper signature below and returning same as fully executed
to this office.
Sincerely,
Bridge Design Associates, inc.
Attest ~~ - : ~` ~~
Brian C. Rheault, President
.. _
''' ' ' r CORPORATE ~ flvl'~,~ Y •~~
i~=~• ... -• .; ~'~ SEAL ~' C~. '••• •.~
ti ~ _~.~' ,,~~ ;egg '
~~'~"':::~,~"„;Aac~pted by: Attest: ~ p{ Q~ O~
• ~ Palm B ch County Board of Commissioners Sharon R. Bo Jerk a~d~Com 7 y
i., ~ 0 !IIA
gy: By. '
Addle L. Greene, Chairperson D Jerk 'h,~~~~t~i, •.~.•••.5+2
Approved As To Focm & al Sufficien ~ `''~
Leg cy: proved as to Terms and Conditions:
~ - c ~ ~ ~, Gc~.
S:IPERSONNEL1lGm1 BER 061PBC Renewal.wpd
s
PALM BEACH COUNTY ANNUAL STRUCTURAL CONTRACT
Task Order Basis -Fee Schedule
eta Parkway, Suite 200
Im Beach, Florida 33411
Brian C. Rheault
BRIDGE DESIGN ASSOCIATES, INC.
email: bridgebbd~a7,aol.com
Phone: {561) 686-3660 Fax: (561) 686-3664
Fee Schedule -12/21/06 through 12/20/07
:me: BRIDGE DESIGN ASSOCIATES, INC.
Raw Rate Burdened Rate
;I 45.00 130.50
Manager (Sr. P.E.) 45.00 130.50
Engineer (P.E.) 38.00 110.20
presentative {E.I.) 21.50 62.35
craftsman 31.00 89.90
~suitants NIA
Multiplier
Salary 1.00
Overhead & Fringe 1.59
Subtotal 2.59
12% Profit 0.31
TOTAL 2.90
sign Associates, Inc. will provide "Additional Services, as Authorized and Approved by the Owner, Palm Beach County"
~NNEt,11Gm10CTOB~R Oti1PBC Rate Schedule.wpd
~~
Memo
To: Mayor/Council
From: Michael R. Couzzo, Jr __.b..~..
~ ~ ~ _r._._.._.,~,.:.~ ,
®ate: 5/21 /2007
Re: Engineering Status Report and Recommendations for the Tequesta Drive Bridge
Attached please find a copy of Bridge Design Associates, Inc. assessment report and
recommendations for the Tequesta Drive Bridge. This report is submitted for your review and
consideration.
I believe this subject may be appropriate for discussion by Council at a future workshop.
With regard to engineering recommendations related to existing delamination, our Public Works
Department has been directed to coordinate removal (in boat traffic areas).
Please feel free to contact me should you wish to discuss this matter.
~alr~~ beach ~®~nty, F'1®rfld~
Qver the North Prong of the Loxahatchee River
Prepared by:
BRIDGE DESIGN ASSOCIATES, INC.
April, 2007
~-~~~~~
Brian C. Rheault P.E. 38797
Project Overview
Bridge Design Associates, Inc. was retained to investigate and report on the condition of
the Tequesta Drive Bridge. Recent construction on the bridge includes the replacement
of the center roadway deck in 2006. Inspection of the bridge focused on determining the
areas of the bridge that exhibited signs of corrosion and concrete delamination.
Concrete roadway panels were investigated using visual inspection and soundings from
striking the panel with a metal hammer. Several areas of severe concrete delamination
were observed in the roadway and sidewalk panels. Major areas of concern include the
roadway panels in spans 2 and 4, sidewalk panel in span 3, and the cast-in-place concrete
curb in some locations.
The majority of rail posts were found to be in bad or poor condition. Posts were observed
to have large sections of missing concrete with exposed reinforcement. Reinforcing was
found to be routinely corroded. Concrete rail posts that did not have sections of missing
concrete or exposed reinforcement exhibited moderate to severe cracking.
Cracking and delamination was observed on the corner of the revetment walls on the
southeast, southwest, and northwest revetment. Large cracking and spalling were
observed in these locations. Some of these sections were over the area of existing
patching.
Piping attached to the bridge showed areas of severe corrosion. Some sections had been
completed corroded through the exterior of the pipe. Brackets attached to pipe also
showed areas of corrosion. Traffic barriers on the approach slab had loose connections
between the barrier and post, with some posts not connected to the barrier and some
missing nuts to secure the railing.
Bridge Design Associates, Inc. I
~we~meng ~~8~ ~®ndeta®uu
Severe cracking and delamination was found along the revetment walls in the northwest,
southwest, and southeast corners. In the northwest corner of End Bent IVunlber 1 and
fourteen foot long zone of cracking and delamination was observed. Cricking was
present on the top ,and along rhe~ side of the revetment wall.
Bridge Design Associates, Inc. 2
-- -- -
~4reas of cracking were observed in the same regions as areas that were observed to have
been patched.
~::
>df ~ •. .
~ ~ s
~, ~
~, ~~
'' "~~ .tip ~ ~h" ~~x..,
x ~ t'~ ~A
y'~`'
~.F,~
:~ 2:
~..
Bridge Design Associates, II1C. 3
~;.
Concrete Rail Post Conelition
The condition of the concrete rail posts was found in most cases to be poor or bad. Posts
routinely were observed to have large sections of missing concrete and exposed rebar.
Reinforcing bars were heavily corroded and in some cases completely exposed to the
corrosive environment.
'~'
t .,'
,z:."
.;r+'.~
,F.
e.,
~ „~,.W~ } ~ int..'
{ .`.
,`
h
Bridge Design Associates, Inc. 4
x~_;
~::`:;
;~:
'~;
Bridge Design Associates, Inc. $
Posts were also observed to have moderate to severe cracking. 'This cracking was severe
enough to expect that the rail posts would very shortly have sections of concrete fall off.
_a
',: -,
~k
,,^
`-,'~3`
s
_.
r ut ' ~' ..`h, *'
F Z.
(?r&
i`,
t
-~.
Bridge Design Associates, Inc.
]Pile Cap Condition
Pile caps at the joint between the roadway and sidewalk panels in some areas showed
signs of delamination and cracking. On bent No. 2 there was a section of missing
concrete with exposed reinforcing steel. Bent No.l had a previously patched section that
was delaminated and cracked.
'N~ ~~ ~~i i ~~'~ -~~,, - ~_~ s -~ .4~~
~- :~
~~ ~. ~
~' ~~ a'
'~
r'_
l:# ~~~
s~
Bridge Design Associates, Inc. ~
~.<
-_
f
.~'
~ -
` % ~ .. .
'~~
r
1
6
;'.~ i
- ~ `~Cy~ .
~ ~Y~A~
1a".:
~'~~~,
1~1
} '~' A`
~' J
~~ 3
The bottom of the pile cap on the End Bent No. 1 had an area of delamination with
quarter to three quarter inch wide cracks.
Bridge Design Associates, Inc. g
An area of cracking and delamination on the bottom side of Bent No. 4.
Bridge Design Associates, Inc. 9
~ _1 }
h -~~
~ .. _
:. .: ~ _.._ .__... .. ..: .:...:~M
t c - - ~_ - ..-p~.....
.._. . ~ .c ~w ~_ ~--.
C®nca~ete ]Pile C®nclifi®n
Concrete piles were only inspected above the level of low tide. The majority of piles are
considered to be in good condition. Cracking was observed in piles eleven and twelve of
End Bent Number 1 and in pile four of bent number 2. Sections of rust bleeding were
discovered on some piles. The piles' pickup locations were occasionally found to have
exposed reinforcing bars.
Bridge Design Associates, Inc. 10
~:;,
~N1-
f}'r 4$
x
~, ,
~~.,_. _,
L
`~ T - ~~.
s, .a~ _ mil!
.~ ~
~..
~;..",,,r,~...
^'„+eV ,~, a+r
`'
Bridge Design Associates, Inc. 11
concrete ]Panel ECondation
Roadway panels in span 2 had large areas of delamination and cracking. In some cases
delamination and cracking was observed in areas that were previously patched. Areas as
large as Oft by 12ft were observed to be delaminated.
~;;
~1+~..
_~~
~~ 1. ~
~, '~~;
,,,
~:.
~~ ~ _ µ
Bridge Design Associates, Inc. 12
One of the sidewalk panels in span 3 showed signs of severe delamination with the
presence of large cracking.
Roadway panels in span 3 also showed signs of severe delamination and cracking. Some
panels show several separate areas of delamination.
Bridge Design Associates, Inc. 13
~~ _ _ -- ,:
. ~:
_ `_~
- M
'r
~
X
~+
:- 4
~
, o+m
~ f._ ' ~~
The joint between the cast-in-place concrete curb and roadway panels were found to be
routinely cracked. This cracking and delamination was found in some regions that were
previously patched.
Bridge Design Associates, Inc. 14
A patched section that shows signs of delamination and severe cracking on the cast-in-
place curb in span 5.
Fes; ~ . ~ _
.:
>~
ti~'~_ .
Bridge Design Associates, Inc. 15
Sidewalk ~®nd~ti®n
The ground beneath the sidewalk on the northeast corner of the bridge show signs that the
ground beneath the sidewalk has been eroded away. The concrete sidewalks show signs
of cracking along the joint of the cast-in-place concrete curb and the sidewalk panel.
:~
,~
~..
,r
-
.,~a~
Y2r* - a
"
, ~
`. x
_
;~,/
. ~~ ~
?'
h
k
L a .
~:F w
.
i:; - :9
~
~ - ~ ;~`'
.._. x
_ b ,r
Bridge Design Associates, Inc. 16
Bridge Design Associates, Inc. 1~
®thea~ Aa-eas ®f C®ncern
Traffic railing post connections were routinely found to be loose. These connections
were also found to be unattached between rail and post, with several bolts that did not
have any nuts to secure the bolt.
Bridge Design Associates, Inc. 18
Pipes that were connected to the bridge also exhibited signs of deterioration. 'T'his
deterioration included signs of severe corrosion, in some cases entire sections of pipe
cover is no longer present. Connection brackets were also found to be heavily corroded.
~,
~~
..>
• f, ..
ti - „.:.
'~ a.
1 °y '
~ ..:
~_-. _
~ ~
I ;.
6~F.C^:•
Bridge Design Associates, Inc. 19
Conclusion
Based on the observed condition of bridge, there are several areas of concern. Concrete
roadway panels in spans 2 and 4 showed signs of severe delamination. The southern
sidewalk panel .in span 3 had areas of severed cracking and delamination. There is
concern over the danger of sections of concrete falling from the deck onto boats below
the bridge.
Concrete rail posts were found to be mostly in poor to bad condition. Several posts had
large sections of missing concrete with exposed reinforcing strands. Other posts had
areas of cracking that will give way if hit.
The concrete piles of the bridge were in good condition, with the exception of a few' piles
that had areas of cracking. Piles were only investigated above the waterline, so Bridge
Design Associates, Inc. is unable to affirm the below water condition of any pile.
Pile caps were found to be in mostly good condition. There were some areas of
delamination and cracking observed in the pile. These areas of concern were generally
found at the corner between the roadway and sidewalk panels. Tw_o pier caps showed
areas of delamination.
Recommendations
Based on our site observation:
Spans number 2 and number 4 need to be replaced within the next 24 months.
The sidewalk slabs and railings need to be replaced within the next 24 months.
We also recommend removing any loose patches or spalling concrete for boater
safety.
Based on the inspections it is clear that within four to five years the entire bridge deck
will have to be replaced. We recommend the village decide to continue the piece by
piece replacement basically closing the bridge down every two years to continue the
repairs or take steps to replace the bridge in the next 24 months.
It is our opinion that concrete repairs on span number 2 and 4 and the sidewalk slabs of
span number 3 will not extend the life of the deck slabs significantly enough to justify the
expense.
5:\2006-Jobs\06-517 Tequesta Drive Bridge\report\06-517 Tequesta.doc
Bridge Design Associates, Inc. 20
PROJECT: Tequesta Dr.
NUMBER: 06-517
Date: 3-22-07
Tequesta Drive Bridge Inspection 06-517
Post Number Condition Notes Post Number Condition Notes
N 1 Good S 1 Good XB
N 2 Good S 2 Bad
N 3 Poor S 3 Bad
N 4 Bad XB S 4 Bad
N 5 Poor S 5 Poor CR
N 6 Bad S 6 Bad MC
N 7 Bad XB S 7 Bad MC
N 8 Poor S 8 Bad
N
N 9 Poor
10 Bad PT S
S 9
10 Bad
Bad MC, XB
N
N
N 11 Bad
12 Poor
13 Bad MC
CR
MC, XB S
S
S 11
12
13 Good
Bad
Bad PT, CR
MC, XB
CR
N 14 Bad MC, XB S 14 Bad PT
N 15 Bad S 15 Bad CR
N 16 Bad MC, XB S 16 Good
N 17 Bad MC S 17 Poor
N 18 Poor S 18 Poor
N 19 Bad MC, XB S 19 Poor
N 20 Bad MC, XB S 20 Poor
N
N 21 Bad
22 Bad
MC S
S 21
22 Bad
Bad MC, XB
XB
N 23 Bad MC, XB S 23 Bad
N 24 Poor S 24 Poor
N 25 Bad XB S 25 Poor
N
N 26 Good
27 Poor PT S
S 26
27 Bad
Poor XB, CR
N 28 Bad MC, XB S 28 Poor
N
N I 29 Poor
3G IGood I CR
li S
S i 29
3G ( Bad
Good ~ XB
I
MC Missing concrete sections
XB Exposed Rebar
CR Cracked Concrete
PT Existing Patch
Post numbers begin at the west side of bridge
The absence of a note does not necessarily imply that missing concrete, exposed rebar, cracked
concrete or existing patches were not present.
Christopher LaPorte, E.I.
21
PROJECT: Tequesta Bridge
NUMBER: 06-517
Date: 3/29/07
Span Panel Notes
w2
R 2 Minor BL 4 in
R3
Span 1 R a
R5
R6
7
W3
SW 1 BL
sw 2
R 1 PT-XB
R2 PTw/DL
R 3 PT w/ DL
Span 2 R a
R 5 DL w/ SP, 4 ft by 12 ft
R 6 PT w/ SP and DL, aft by 8 ft
R 7 DL, 3 ft by 4 ft - DL, 3 ft by 5 ft - CR along ed e btw R 7 and SW 3
SW 3
SW 1 DL, 3 ft by 6 ft section
SW 2 CR and SP alon joint btw SW 1 and R 1
R1
R2
3
Span 3 R b Recently replaced panels
all appear in
ood conditio
,
g
n
s
R7
SW 3 PT 2 locations
SW 4 XB - PT
SW 2 DL - 2 locations
R 1 DL and CR along edge btw sidewalk and road panel
R2 PT wiDL
R 3 PT w/ DL
Span 4 R 4 DL
R 5 DL, 1 ft by 1 ft - DL, 1 ft by 2 ft
R 6 Pt w/ DL, 6 ft by 4 ft
R 7 PT w/ DL and SP, 1 ft by 1 ft - DL, 3 ft by 6 ft
W3
SW 4 DL
SW 2 XB, 3 in
pan 5 R 1
R2
R3
R 4
R5
R6 DL w/ DL along edge btw SW 2 and R 1
S R 7
W 3 PT w/ DL SP and CR along edge btw R 7 and SW 3, 5 ft - BL
D ~ ., L. .... i.. _ _ ~
u"cIJ a' c 'Bleed' DL f ~Delam nat on Prese ortC;RX Crackeds SPR Spalled P M1Ex stingoPatcte; BL -Rust ~
Christopher La orte E.I.
22
PROJECT: Tequesta Bridge
NUMBER: 06-517
DATE: 3/29/2007
i equesta Drive Bridge - 06-517 Pile Condition
Pile Bent Pile Notes
Pile Cap DL btw 1 and 2 - PT btw 7-8-9 - XB north of pile 12 - PT w/ CR north of pile 12, 15 ft horiz
9 in either side of corner- PT w/ DL south of pile 1
2
3
4 BL
End Bent 5
No.1 s
7 PT
8 PT
9 PT
~o
11 CR4ftvert-BL
12 CR4ftvert-BL
Pile Cap XB over pile 1 west side - PT w/ SP btw piles 4 and 5 west side
Bent No ~
. 2
1 3
4 XB at pick up location
Pile Cap PT w/ DL over pile 1 - MC XB btw pile 4 and 5 east side - CR along east bottom corner -
DL bottom btw 4 and 5 -plant growing over pile 1
Bent 1
No.2 2
3
4
B
t Pile Cap
~ CR btw pile 1 and 2 west side - Cr btw pile 4 and 5 bottom - DL btw pile 4 and 5
en 2
No.3 s
4 CR SP 5' vert
Pile Cap T '1 nl L. ., 1 A ,J L.
over pne 5 - ~~ ~,t~~ pipe ~+ any 5 ~ottviii east corner - CR btw pile i and c" west side -
CR above pile cap south side
Bent i
No.4 2
3
4
Pile Cap CR south of pile 1, 5 ft horiz - PT w/ some DL south of pile 1, 15 ft - CR 1 ft over pile 5 -
BL north pile 12
i
2
3
4
End Bent 5 BL
No.7 s
8
9
10 BL
11 BL
12 BL
Piles are numbered from the south to the north; XB -Exposed Rebar; MC -Missing Concrete; BL - st Bleed;
DL - Delamination Present; CR -Cracked; SP - Spalled; PT -Existing Patch '~-
Cristopher LaPorte E.I.
23
Page is too large to OCR.