HomeMy WebLinkAboutMinutes_Workshop_04/23/1991VILLAGE OF TEQUESTA
Post Office Box 3273 • 357 Tequesta Drive
Tequesta, Florida 33469-0273 (407) 575-6200
FAX: (407) 575-6203
V I L L A G E O F T E Q II E S T A
V I L LAG E C O II N C I L yP O R R 8 H O P
_ M E E T I N G M I N II T E S
APR I L 2 3, 1 9 9 1
I. The Tequesta Village Council held a Village Council Workshop
meeting at the Village Hall, 357 Tequesta Drive, Tequesta,
Florida, on Tuesday, April 23, 1991. The meeting was called
to order at 9:00 A.M. by Mayor Joseph N. Capretta. A roll
call was taken by the Recording Secretary, Fran Bitters.
Councilmembers present were: Mayor Joseph N. Capretta, Vice
Mayor Ron T. Mackail, Earl L. Collings, and Edward Howell.
William E. Burckart was not in attendance. Village Officials
present were: Village Manager, Thomas G. Bradford; and Wendy
Harrison, Assistant to Village Manager. Tom Hall, Water
System Manager, and Bill Reese, Engineering Consultant, were
also in attendance.
II. APPROVAL OF AGENDA OPTIONS
The Agenda was approved as submitted.
III. DISCIISSION OF WATER PROJECTS BY STAFF
Mayor Capretta. stated that the purpose of this Workshop is to
determine the schedule of the water project, projected plans
and present status, and establish a basis for future
monitoring to determine whether the program is or is not on
schedule.
Village Manager Bradford explained that the project is called
in-house the Wells and Tank Project. Internally, this project
was divided into two areas for administration: 1) Tank,
handled by Wendy Harrison, and 2) Wells and associated piping,
handled by Tom Hall. An overview of the storage reservoir
will be given today, as well as discussion of permitting, and
the pipeline issue and the wells.
Recycled Paper
Village Council Workshop
Meeting Minutes
April 23, 1991
Page 2
-------------------------------
A) Storage Reservoir: Wendy Harrison gave an overview: The
Storage Project began with a consultant selection process
which took place in the summer of 1990. In October 1990,
Reese Macon & Associates were selected to do the design work
and construction observation for the Storage Reservoir. Reese
Macon proceeded with programming and schematic design at that
time, which was completed in January 1991. Some of the
products of the programming process caused Village Staff to
re-evaluate the Project. The projected Budget was in excess
of budgeted funds. Therefore, the water system, and demand
projection were re-studied. It was decided to scale back the
Storage Tank from a three million gallon (3mg) tank to a two
million gallon (2mg) tank. This also allows the option of
room for an additional 2mg storage on the site.
The Project is presently approximately 30 days behind
schedule. The Project is presently at the 60~ Design process.
The next step will be permitting. Design will be finished
during Permitting. At the completion of Permitting,
Construction will begin, scheduled to be completed by February
1992.
Councilmember Collings asked how an estimate of a 3mg tank
could change to a 2mg tank, and how could there be such an
over-estimate of withdrawal or demand. Wendy Harrison
explained that the original plan was 2mg. During the
Budgetary process last year the point was made that as long
as a 2mg tank was planned, why not build a 3mg tank. The 3mg
tank was considered to allow enough storage in case the
Village went to R/O. Tom Hall explained further that part of
it was due to the fact of the estimated projected demand on
the system for the next 5-10 years. A 2mg tank will bring
total gallonage to 2.750mg available to be pumped under
auxiliary power compared to the present .75omg. The storage
supply will therefore be more than doubled.
Vice Mayor Mackail felt the decision for a 2mg tank was an
economic decision versus a long-term approach to the needs.
Considering the Permitting process to be completed regarding
Martin County and considering the demands for the next 5-10
years, it would be wise to make a decision that would warrant
that. Economics are important, but it is also necessary to
consider today's needs versus 5-10 years in the future.
village Council Workshop
Meeting Minutes
April 23, 1991
Page 3
Wendy Harrison stated that demand projections were studied and
it was discovered that the highest demand projections were for
8.Omgd in the year 2000. Those projections were made before
the implementation of the tiered-rate structure. With the
tiered-rate structure, demands have actually decreased from
1989 to 1990. A 2mg tank does allow sufficient storage.
Mayor Capretta asked if the tiered-rate structure will
eventually be eliminated when the drought is over. Village
Manager Bradford stated it might need to be modified, but
probably would never be eliminated.
Mayor Capretta asked what brought about the decision for a 2mg
tank. Bill Reese, of Reese Macon, explained one deciding
factor was water quality. Water would sit in a 3mg tank too
long before it gets out into the system. Another deciding
factor was that when the existing 3/4mg tank was built, a 20-
foot wall was built. Because of the hydraulics of the plant,
the tanks will have to be kept at the same height; otherwise,
overflow would take place. A 3mg tank with a 20-foot wall
section is not an efficient design. Some of the economy of
scale of going from a 2mg tank to a 3mg tank is not as much
as it would be, otherwise. Regulations require that half of
max-day (defined by plant capacity, plus what is purchased
from Jupiter) usage be stored. That is calculated by
projecting water usage to some point in the future, take half
of that, to determine the amount of storage that is reasonable
for now.
It was the consensus of the Village Council that a 2mg tank
would suffice for storage and budgeting purposes.
village Council Workshop
Meeting Minutes
April 23, 1991
Page 4
-------------------------------
B) Permitting: Martin County Engineering - Roads - a U2
permit needed for the Village to do work with Martin County
roads. It will also be needed if the Village attached to any
Martin County bridges. Palm Beach County Engineering - Roads
- a general permit needed for work with any Palm Beach County
roads. DER - Well Sites - not a mandatory permit. Its
purpose is to get DER to sign off on specific well sites.
This needs to be done as early as possible. DER - Well
Equipment ~ Piping - sFWMD - Well sites & CIIP (Consumptive
IIse Permit) - Tequesta should already have this permit. The
only significant thing about this one is that it does tie the
Village in with the ability to move the well sites a few
hundred feet without having to re-permit. PBCHD - Well Site,
Well Equipment i Piping - DERM - Well Site - a Palm Beach
County Agency, only to be involved if the well is in Palm
Beach County. DER/PBCD/DERM - Release For IIse - Only
applicable for Palm Beach County locations.
It was the consensus to postpone plans to go before the Martin
County Commission relative to outstanding issues until all
applicable Martin County permits for this project are in hand.
C) Pipeline: Tom Hall explained that Reese Macon has been
authorized to begin Phase II (30$ Design) of the Wells, and
most recently has been authorized to accelerate that process
to Phase III (60~ Design) relative to the northern route, to
get the permitting process underway. The northern route of
the pipeline (i.e., County Line Road which would include Well
24 site - Psychiatric Hospital; Well 25 site - entrance to
Turtle Creek; Well 26 within Turtle Creek; and Well 27 -
adjacent to Country Club Drive), as opposed to the sub-
aqueous route, regarding time and money, is thought to be more
beneficial to pursue. The sub-aqueous crossing would cost
between $90,000-$150,000 more than originally planned, with
5-8 more months of permitting time. Piping for the northern
route would be substantially less expensive in both time and
money. There is approximately a $100,000 difference between
the two approaches. A 10"-12" pipe would be used for the
northern route. The Village Manager reminded Mr. Reese of the
need to provide pipes of a size sufficient to handle increased
supply from existing proposed wells and new wells in the
future. Mr. Reese assured the Village Manager that this would
be calculated nd accounted for in pipe size determination.
Village Council Workshop
Meeting Minutes
April 23, 1991
Page 5
-------------------------------
It was the consensus to pursue the northern route versus the
sub-aqueous route as already chosen by Village Staff.
D) Production Wells (24, 25, 26 and 27): Village Manager
Bradford explained there is one decision not yet made: Well
24, next to the hospital could be done now and start the line
from there to Seabrook Road which would give 300,000 extra
gallons per day, the pro of which is water soon, and the con
is economy of scale. Economy of scale (i.e., putting in a
project of one well vs. four all together and length of
pipeline of x number of feet vs. the whole line. Bringing the
hospital well on line would bring the Village up to permitted
capacity on the eastern peninsula.
Councilmember Collings asked what the next step. Village
Manager Bradford responded that the next step would be to
obtain the permits and to decide within the next few weeks or
so whether to break out Well 24.
%I. ADJOORNMENT
The meeting was adjourned at 10:15 A.M.
Respectfully submitted,
~~
Fran Bitters
Recording Secretary
ATT
Bill C. scavelis
Finance Direc or/Village Clerk
DATE APPROVED:
`~.~. /6 , i 4 9 ~