HomeMy WebLinkAboutDocumentation_Regular_Tab 01_07/17/2008VILLAGE OF TEQUESTA
RESIDENT BRIDGE COMMITTEE
MEETING MINUTES
APRIL 22, 2008
1. Call to Order and Roll Call
The Village of Tequesta Resident Bridge Committee held a regularly
scheduled meeting at the Tequesta Village Hall, 345 Tequesta Drive,
Tequesta, Florida, on Tuesday, April 22, 2008. The meeting was called to
order at 5:31 p.m. by Village Clerk Lori McWilliams, who then called the roll:
Present were Pete Pimentel, Mary Hinton, Michael Vacan'o, Jim Mansfield
and Walt Downey. Also in attendance were Mayor Pat Watkins, Council
Member Arena and Village Clerk Lori McWilliams.
2. Approval of Agenda
MOTION: Committee Member Hinton moved approval of the agenda; Committee
Member Vacarro seconded the motion; motion carried unanimously 5-0.
3. Appointment of Chair
Committee Member Hinton nominated Pete Pimentel as Chair.
MOTION: Committee Member Hinton moved to approve Committee Member
Pimentel; seconded by Committee Member Downey; motion carried unanimously 5-
0.
4. Appointrnent of Vice-Chair
MOTION: Committee Member Downey moved to appoint Committee Member
Hinton as Vice-Chair, seconded by Committee Member Mansfie~l; motion carried
unanimously 5-0.
5. Establish Meeting Schedule and Time
M TlON: Committee Member Downey moved to approve holding the meetings
of 5:30 p.m, on April 28, May 72 and May 79, 2008; seconded by Committee
Member Hinton; motion carried unanimously 5-0.
6. Discussion and Assessment of Tequesta Bridge Repair /Replacement
After detailed discussion and citizen input, the committee agreed they wanted the
engineers and the environmental agency to attend the next committee meeting to
address the following issues:
No Text
Resident Bridge Committee
April 22, 2008
Page 2
• Safety
• Long term and ongoing costs to maintain (new vs. repair)
• Permitting
• Bring in traffic engineer to establish where the trips are coming from (i.e.
Martin County / Unincorporated)
• Environmental issues
• Finance
• Downtime
• Elevation & property values
• Power line location
The Committee noted additional concerns were:
• Speed zones not being enforced by law enforcement
• Jet ski's
• Boat safety
• Getting boats out during storms
7. Adjournment
MOTION: Committee Member Hinton moved adjourn the meeting at 6:31 p.m.;
seconded by Committee Member Downey; motion carried unanimously 5-0.
Respectfully submitted,
~1 lSt.c. ~ ~. Qrr}--
Lori McWilliams, CMC
Village Clerk
No Text
VILLAGE OF TEQUESTA
RESIDENT BRIDGE COMMITTEE
MEETING MINUTES
APRIL 28, 2008
1. Call to Order and Roll Call
The Village of Tequesta Resident Bridge Committee held a regularly scheduled meeting at the
Tequesta Village Hall, 345 Tequesta Drive, Tequesta, Florida, on Monday, April 28, 2008.
The meeting was called to order at 5:35 p.m. by Chair Pimentel. Village Clerk McWilliams
called the roll. Present were Pete Pimentel, Michael Vaccaro, Jim Mansfield and Walt
Downey. Vice-Chair Mary Hinton was absent. Also in attendance were Mayor Pat Watkins,
Council Member Vince Arena, Village Manager Michael Couzzo and Village Clerk Lori
McWilliams.
2. Approval of Agenda
Chair Pimentel added discussion on the "Origination StudyA to the agenda.
MOTION: Committee Member Mansfield moved approval of the agenda as modified;
Committee Member Downey seconded the motion; motion carried unanimously 5-0.
3. Presentations:
• Brian Rheault -Bridge Design
• Hank Deibel - Arcadis
Mr. Rheault of Bridge Design provided a short summary on the previous bridge closing and
noted the Village was moving towards a point where the bridge needs ongoing repair work. He
explained the options were to continue to replace bridge components, raise the bridge slightly
(after an analysis the bridge could be raised 12 to 18 inches), or replace the entire bridge. He
noted permitting would not be required to repair; the environmental permit requirements would
be minimized to raise; and signficant permitting would be necessary to replace the bridge. He
advised that with options one and two there were techniques that could be placed on the piles
that would help service the bridge well into the future 25-30 years without problems.
Mr. Deibel of Arcadis commented on the roadway design and felt the bridge could be raised
approximately five feet; and if it was raised too high it would impact the surrounding properties
and the site distance would be an overriding factor.
Mr. Rheault commented that raising the bridge five feet would not solve the jet ski problems;
and raising the bridge five feet would allow for any class of boat to pass through. He
commented on the cumulative total cost to repair and did not expect the Village to have
maintenance costs for a new bridge within the next 25-30 years repair; maintenance would not
be necessary for 15-20 years with a repair. The Committee discussed the relocation of the
power lines and it was agreed that underground placement would be the best.
No Text
Resident Bridge Committee
April 28, 2008
Page 2
• Mary Lindgren -Environmental Services
Ms. Lindgren stated there would be two main permits required: Department of Environmental
Protection (DEP) and the US Army Corps of Engineers. She noted repair of the bridge could
be handled under exemptions; however a replacement would require an extensive permitting
process due to the aquatic preserve and estimates it would be nine to twelve months for the
DEP pem~it. She explained the Army Corps of Engineer process would be more detailed and
time intensive and would require additional agencies be brought in by the Corps of Engineers
for input; she estimated a twelve to eighteen month process. She advised both permits would
run simultaneously.
She explained Environmental Services could perform preliminary biological assessment work
to determine whether there were sea grass and could provide a better picture to determine
timeframes and cost. They did a preliminary data base search and found on the DEP
database there would most likely be sea grass on the east side of the shoreline and would
need to confirm through surveys.
Mr. Deibel advised the cost of 2.3 million could increase due to mitigation requirements. Ms.
Lindgren stated the snails would not be a problem at this location; however the listed species
of sea grass could require a commenting period and she has ideas to help offset the mitigation
and impacts.
5. Discussion on the Origination Study
Mr. Rheault commented on grants and currently the only available would be through Florida
Inland Navigational District (FIND) and they would require public use.
4. Discussion and Assessment of Tequesta Bridge Repair /Replacement
Mr. Downey asked if there would be any bearing on the existing pilings if the sire and height
was increased and was advised the design and components used would be affected. Mr.
Rheault explained the bridge was low rated for different reasons, not because it could not carry
the weight. Mr. Downey provided reasons to raise the bridge including the water table rising
and safety of getting boats out during emergencies.
Mr. Couzzo commented on the traffic origination and destination versus trip count and noted
the police department had already done a trip count. This study would determine where the
trips generated from and where they went.
Consensus of the Commit[~ee agr~eeal to recommend tine Origination Study not be
completed.
No Text
Resident Bridge Committee
April 28, 2008
Page 3
Chair Pimentel opened the meeting to the public for comments. Mr. Russell VonFrank, 489
Dover Road, commented on the San Francisco Bay Bridge being coated with the products Mr.
Rheault mentioned. Mr. Richard Berube, 4 Country Club Circle, believed the Village could
stop the process if it was too expensive and could fall back to the repair plan if necessary.
Mr. Rheault stated the Village was in the three-five year time frame to consider an option for
the bridge and suggested the time frame be limited to eighteen months to two years maximum
to make a decision.
Manager Couzzo recommended engaging the environmental engineers and enter into a
contract to compile a preliminary environmental assessment. Ms. Lindgren advised they would
go a 100 feet minimum outside of the estimated work zone and could work with a preliminary
design.
Consensus of the Committee agreed to proceed with the preliminary environmental
study.
Mr. Pimentel suggested contacting FPL to get a feel for what it would take to place their lines
under the water; Manager Couzzo advised staff could work on this issue. Mr. Downey asked
about building the bridge one span at a time to keep one side open while the build is
happening. Mr. Rheault stated the challenge would be the length of the bridge; however it has
been done and an issue would be maintenance of traffic and would considerably add time to
the project.
6. Adjournment
The meeting was adjourned at 6:45 p.m.
Respectfully submitted,
~~~ ~ .~
Lori McWilliams, CMC
Village Clerk
No Text
RESIDENT BRIDGE COMMITTEE MEETING
SUMMARY MINUTES
JUNE 23, 2008
Committee discussion and Assessment:
The impact the project would have on Seagrass.
Construction procedure and issues concerning turbidity.
Different time lines for project length.
Committee Consensus to Council:
• New bridge
• Expedite project toward permitting
• Raising the Bridge height in accordance with engineering
No Text
VILLAGE OF TEQUESTA
RESIDENT BRIDGE COMMITTEE MEETING
SUMMARY MINUTES
JUNE 23, 2008
Call to Order and Roll Call
The meeting was called to order at 5:34 p.m. by Chair Pete Pimentel. A roll was taken by
Deanna Mayo. Present were: Chair Pete Pimentel, Vice Chair Mary Hinton, and Member Jim
Mansfield. Member Michael Vaccaro arrived late and Member Walt Downey was absent. Also
in attendance were Mayor Pat Watkins and Council Member Arena.
Approval of Agenda
MOTION: Committee Member Mansfield moved approval of the agenda; Vice Chair Hinton
seconded the motion; motion carried unanimously 4-0.
1. Approval of Minutes
MOTION: Vice Chair Hinton moved approval of the minutes; Committee Member Mansfield
seconded the motion; motion carried unanimously 4-0.
Michael Vaccaro arrived at 5:37
2. Approval of Minutes
3. Presentation !Reports
Vice-Chair Mary Hinton's motion for recommendation to Council included
• New bridge
• Expedite project toward permitting
• Raising the Bridge height in accordance with engineering
Respectfully submitted,
(1,~, M e,¢~ ~.er¢.~ cay.
Lori McWilliams, CMC
Village Clerk